WEST CANADA VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-03-02-04
last updated on 04/19/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Central School:
22-0979FB Reconstruction 0-003-017 04/04/23 DONE DONE DONE 11/16/22 09/14/22 01/05/22 11/09/21 2,4,7,8,9,10,155,15, 5,865,816 5,865,816 WLC 0 0 0 Synthesis Architects,L.L.P. 0 09/05/23 YES 09/14/22
22-0593 Reconstruction 0-003-018 06/13/22 DONE DONE DONE 09/26/22 09/26/22 07/07/22 06/13/22 155 81,000 81,000 WLC 0 0 0 Synthesis Architects,L.L.P. 0 02/24/23 09/26/22
23-0887 Reconstruction 0-003-019 UNREVIEWED 11/06/23 11/03/23 06/01/23 05/16/23 2,4,8,9,13,16 0 0 WLC 0 0 0 Synthesis Architects,L.L.P. 0 / / 11/03/23
- SB Reconstruction 0-003-BA1 DONE / / / / / / / / 10 0 0 WLC 0 0 0 0 / / / /
High School Bus Garage:
22-0980FA Reconstruction 5-005-007 04/04/23 DONE DONE DONE 11/16/22 09/14/22 01/04/22 11/13/21 2,8,9,155,15,16 454,523 454,523 WLC 0 0 0 Synthesis Architects,L.L.P. 0 / / 09/14/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
FRANKFORT-SCHUYLER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-04-02-06
last updated on 04/19/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Junior-Senior High School:
18-1685 Reconstruction 0-001-014 05/28/19 DONE DONE DONE 03/19/19 03/08/19 / / 05/23/19 4,7 197,900 197,900 SLC 0 0 0 Bonacci Architects 0 06/13/20 03/08/19
- PR Reconstruction 0-001-015 DONE / / / / 11/30/22 / / 2,4,7,8,9,10,155,15, 0 21,826,713 SLC 0 0 0 0 / / / /
23-0585 Reconstruction 0-001-015 03/26/24 DONE DONE DONE 10/02/23 09/27/23 11/30/22 10/18/22 2,4,7,8,9,10,155,15, 3,324,000 3,324,000 MSK 0 0 0 King & King Architects 0 / / 09/27/23
- Reconstruction 0-001-016 / / / / 03/14/24 / / 2,4,7,8,9,10,155,15, 0 0 MSK 0 0 0 0 / / / /
Reese Road Elementary School:
21-1424PR Additions and Alterations 0-002-012 DONE 03/03/22 / / 01/18/22 / / 02 - 16 0 13,155,318 SLC 0 0 0 0 / / / /
23-0586 Additions and Alterations 0-002-012 03/26/24 DONE DONE DONE 10/02/23 09/27/23 01/18/22 10/18/22 02 - 16 1,182,000 1,182,000 MSK 0 0 0 King & King Architects 0 / / 09/27/23
- PR Additions and Alterations 0-002-013 / / / / 03/14/24 / / 02 - 16 0 0 MSK 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HERKIMER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-06-01-06
last updated on 04/19/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Senior High School:
19-0916 Reconstruction 0-001-014 03/06/20 DONE DONE DONE 12/05/19 11/22/19 05/21/19 12/04/18 2,8,9,155 7,574,000 7,574,000 JLB 0 0 0 King & King Architects 0 10/04/21 11/22/19
20-0873 Reconstruction 0-001-015 01/11/21 DONE DONE DONE 11/20/20 11/10/20 06/17/20 06/09/20 16 100,000 100,000 JLB 0 0 0 King & King Architects 0 05/10/21 11/10/20
21-1745 Reconstruction 0-001-016 07/29/22 DONE DONE DONE 05/03/22 04/29/22 12/16/21 12/04/18 2,4,8,9,10,155,15,16 4,470,000 4,470,000 JLB 0 0 0 King & King Architects 0 / / 04/29/22
Herkimer Elementary:
19-0917 Reconstruction 0-006-013 03/06/20 DONE DONE DONE 12/05/19 11/22/19 05/21/19 12/04/18 2,8,9,155 4,265,000 4,265,000 JLB 0 0 0 King & King Architects 0 10/04/21 11/22/19
19-0188 Reconstruction 0-006-014 09/16/19 DONE DONE DONE 07/30/19 07/25/19 06/17/19 05/21/19 16 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/15/20 07/25/19
21-0652 Reconstruction 0-006-015 12/22/21 DONE DONE DONE 11/04/21 11/04/21 04/07/21 05/18/21 16 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/03/22 11/04/21
21-1746 Reconstruction 0-006-016 07/29/22 DONE DONE DONE 05/03/22 04/29/22 12/16/21 12/04/18 2,8,9,10,155,15,16 1,452,000 1,452,000 JLB 0 0 0 King & King Architects 0 / / 04/29/22
22-0404 Reconstruction 0-006-017 10/14/22 DONE DONE DONE 09/07/22 09/02/22 08/03/22 05/17/22 16 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/15/23 09/02/22
23-0221 Reconstruction 0-006-018 10/03/23 DONE DONE DONE 08/09/23 08/09/23 03/30/23 05/16/23 8,16 100,000 100,000 JJH 0 0 0 King & King Architects 0 / / 08/09/23
Bus Garage:
19-0918 Reconstruction 5-009-005 03/06/20 DONE DONE DONE 12/05/19 11/22/19 05/21/19 12/04/18 9,155 135,000 135,000 JLB 0 0 0 King & King Architects 0 10/04/21 11/22/19
21-1747 Reconstruction 5-009-006 07/29/22 DONE DONE DONE 05/03/22 04/29/22 12/16/21 12/07/18 8,9 30,000 30,000 JLB 0 0 0 King & King Architects 0 / / 04/29/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
LITTLE FALLS CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-08-00-05
last updated on 04/19/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Benton Hall Elementary:
19-0155 Additions and Alterations 0-001-012 01/06/20 DONE DONE DONE 07/24/19 07/22/19 04/18/18 05/15/18 02 - 16 8,350,000 8,093,473 JSS 0 0 0 Synthesis Architects,L.L.P. 0 11/09/21 07/22/19
Middle School/High School:
19-0156 Additions and Alterations 0-008-014 01/06/20 DONE DONE DONE 07/24/19 07/22/19 04/18/18 05/15/18 02 - 16 20,575,000 20,223,490 JSS 0 0 568,670 Synthesis Architects,L.L.P. 0 10/26/21 07/22/19
School Bus Garage:
19-0157 Additions and Alterations 5-003-003 01/06/20 DONE DONE DONE 07/24/19 07/22/19 01/14/19 05/15/18 02 - 16 1,500,000 1,500,000 JSS 0 0 0 Synthesis Architects,L.L.P. 0 08/28/20 07/22/19
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
DOLGEVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-10-03-04
last updated on 04/19/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
James A Green School:
19-0646 Reconstruction 0-001-017 11/01/19 DONE DONE DONE 10/31/19 10/30/19 08/16/19 08/20/19 7,155,16 25,000 25,000 SLC 0 0 0 SEI Design Group 0 11/15/19 10/30/19
20-0553 Reconstruction 0-001-018 01/31/21 DONE DONE DONE 10/07/20 09/28/20 12/26/19 02/25/20 2,4,9,155,16 1,000,000 1,000,000 SLC 0 0 0 SEI Design Group 0 10/15/21 09/28/20
21-0655 Reconstruction 0-001-019 02/10/22 DONE DONE DONE 11/04/21 11/04/21 04/16/21 06/16/20 7,9,10 95,000 95,000 SLC 0 0 0 SEI Design Group 0 08/23/22 11/04/21
21-0656 Reconstruction 0-001-020 03/29/22 DONE DONE DONE 11/04/21 11/04/21 09/09/21 02/25/20 2,4,9,155,16 100,000 100,000 MSK 0 0 0 SEI Design Group 0 04/28/23 11/04/21
22-1410 Reconstruction 0-001-021 04/06/23 DONE DONE DONE 01/06/23 01/05/23 05/12/22 03/01/22 7 1,173,800 1,173,800 JLB 0 0 0 SEI Design Group 0 / / 01/05/23
22-1411 Reconstruction 0-001-022 04/06/23 DONE DONE DONE 01/06/23 01/05/23 05/12/22 03/01/22 2,4,7,8,9,155,15,16 11,984,100 11,984,100 JLB 0 0 0 SEI Design Group 0 / / 01/05/23
22-1470FA Reconstruction 0-001-023 01/18/23 DONE DONE DONE 01/11/23 01/05/23 05/12/22 12/20/22 2 893,025 0 SLC 0 0 0 SEI Design Group 0 / / 01/05/23
22-1471FC Reconstruction 0-001-024 02/07/23 DONE DONE DONE 01/11/23 12/20/22 05/12/22 12/20/22 7,155 849,675 0 SLC 0 0 0 SEI Design Group 0 09/13/23 12/20/22
- Reconstruction 0-001-025 / / / / 08/25/22 / / 155,15 0 0 SLC 0 0 0 0 / / / /
Bus Garage (fmly 4-004):
20-1356 Reconstruction 5-004-002 04/20/21 DONE DONE DONE 03/02/21 02/17/21 11/23/20 12/15/20 13 35,000 35,000 SLC 0 0 0 SEI Design Group 0 10/15/21 02/17/21
- PR Additions and Alterations 5-004-003 / / / / 05/16/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-1412 Additions and Alterations 5-004-003 04/06/23 DONE DONE DONE 01/06/23 01/05/23 05/16/22 03/01/22 02 - 16 847,900 847,900 JLB 0 0 0 SEI Design Group 0 / / 01/05/23
XXPress Box/Storage Demo:
22-1413 Reconstruction 7-005-002 04/06/23 DONE DONE DONE 01/06/23 01/05/23 11/18/22 03/01/22 2 50,000 0 JLB 0 0 0 SEI Design Group 0 / / 01/05/23
Dugout 1:
20-0554 New Construction 7-011-001 01/31/21 DONE DONE DONE 10/07/20 09/28/20 06/11/20 01/21/20 02 - 16 18,600 0 SLC 0 0 0 SEI Design Group 0 06/24/21 09/28/20
XXDugout 2 - no storage - cancelled:
- XX New Construction 7-012-001 CANCELLED / / / / 06/11/20 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
Concession Stand:
- PR New Construction 7-013-001 / / / / 05/18/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-1414 New Construction 7-013-001 04/06/23 DONE DONE DONE 01/06/23 01/05/23 05/18/22 03/01/22 02 - 16 1,157,900 0 JLB 0 0 0 SEI Design Group 0 / / 01/05/23
Press Box:
- PR New Construction 7-014-001 / / / / 05/18/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-1415 New Construction 7-014-001 04/06/23 DONE DONE DONE 01/06/23 01/05/23 05/18/22 03/01/22 02 - 16 54,000 0 JLB 0 0 0 SEI Design Group 0 / / 01/05/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
POLAND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-11-03-04
last updated on 04/19/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
19-0453 Reconstruction 0-002-026 11/22/19 DONE DONE DONE 09/20/19 09/16/19 06/13/19 05/16/17 2,16 600,000 0 JSS 0 0 0 March Associates 0 07/29/21 09/16/19
19-1267 Reconstruction 0-002-027 06/05/20 DONE DONE DONE 01/27/20 01/21/20 06/27/19 05/19/20 9,155,15,16 138,750 138,750 JSS 0 0 0 March Associates 0 08/17/21 01/21/20
22-1861FB Reconstruction 0-002-028 05/19/23 DONE DONE DONE 03/17/23 01/27/23 11/07/22 01/06/21 2,4,8,9,10,155,15,16 1,538,579 1,538,579 JJH 0 0 0 March Associates 0 / / 01/27/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
VAN HORNESVILLE-OWEN D YOUNG CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-17-01-04
last updated on 04/19/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
K-12 Main Building:
18-1700 Reconstruction 0-001-020 05/01/19 DONE DONE DONE 03/21/19 03/18/19 01/02/19 06/24/15 7 265,000 265,000 JLB 0 0 0 King & King Architects 0 08/01/20 03/18/19
19-1386 Reconstruction 0-001-021 03/13/20 DONE DONE DONE 02/07/20 01/30/20 12/09/19 05/21/19 7,9 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/15/20 01/30/20
20-0830 Reconstruction 0-001-022 03/23/21 DONE DONE DONE 11/16/20 11/05/20 06/23/20 06/09/20 7,8,9 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/24/21 11/05/20
21-0850 Reconstruction 0-001-023 01/26/22 DONE DONE DONE 12/06/21 12/06/21 11/03/21 05/18/21 7,8 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/30/22 12/06/21
21-1965FA Reconstruction 0-001-024 11/15/22 DONE DONE DONE 06/13/22 06/10/22 06/13/22 01/26/22 13,16 300,000 300,000 JLB 0 0 0 King & King Architects 0 / / 06/10/22
21-2019 Reconstruction 0-001-025 10/17/22 DONE DONE DONE 06/22/22 06/22/22 06/16/22 11/30/21 2,4,7,8,9,10,155,15, 3,500,000 3,500,000 JLB 0 0 0 0 / / 06/22/22
22-0134 Reconstruction 0-001-026 11/15/22 DONE DONE DONE 07/22/22 07/08/22 07/12/22 05/17/22 10 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/27/23 07/08/22
23-0667 Reconstruction 0-001-027 03/20/24 DONE DONE DONE 10/10/23 10/06/23 09/15/23 05/16/23 9,16 100,000 100,000 JLB 0 0 0 King & King Architects 0 / / 10/06/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
TOWN OF WEBB UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-19-01-02
last updated on 04/19/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
19-0405 Reconstruction 0-001-026 12/06/19 DONE DONE DONE 09/12/19 09/09/19 05/23/19 05/21/19 8,9,155,15,16 100,000 100,000 SLC 0 0 0 Bernier Carr Associates 0 04/24/20 09/09/19
19-0847 Reconstruction 0-001-027 03/16/20 DONE DONE DONE 11/21/19 11/14/19 09/06/19 10/22/19 4,8,9,155,15,16 275,000 0 JSS 0 0 0 Bernier Carr Associates 0 08/31/20 11/14/19
- Reconstruction 0-001-028 / / / / 08/04/20 / / 4,9,15 0 0 JSS 0 0 0 0 / / / /
20-0757 Reconstruction 0-001-029 02/03/21 DONE DONE DONE 10/30/20 10/27/20 08/12/20 06/09/20 8 100,000 100,000 JSS 0 0 0 Bernier Carr Associates 0 06/18/21 10/27/20
21-0307 Reconstruction 0-001-030 03/09/22 DONE DONE DONE 09/08/21 09/08/21 06/11/21 05/18/21 4,8,9,155,15,16 250,000 0 SLC 0 0 0 Bernier Carr Associates 0 / / 09/08/21
21-0835 Reconstruction 0-001-031 02/17/22 DONE DONE DONE 12/03/21 11/23/21 10/27/21 05/18/21 16 100,000 100,000 SLC 0 0 0 Bernier Carr Associates 0 06/10/22 11/23/21
22-0392 Reconstruction 0-001-032 12/21/22 DONE DONE DONE 09/02/22 09/01/22 06/13/22 05/17/22 7 460,000 460,000 WLC 0 0 0 Bernier Carr Associates 0 09/13/23 09/01/22
22-0482 Reconstruction 0-001-033 10/14/22 DONE DONE DONE 09/14/22 09/12/22 07/18/22 05/17/22 8,9,155,15,16 100,000 100,000 WLC 0 0 0 Bernier Carr Associates 0 05/11/23 09/12/22
23-0313 Reconstruction 0-001-034 11/03/23 DONE DONE DONE 08/23/23 08/23/23 07/28/23 05/16/23 9,10,15,16 100,000 100,000 WLC 0 0 0 Bernier Carr Associates 0 04/12/24 08/23/23
- PR Additions and Alterations 0-001-035 / / / / 03/06/24 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
- Reconstruction 0-001-036 / / / / 04/16/24 / / 8,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
Industrial Art Bld:
- Reconstruction 0-004-006 / / / / 03/06/24 / / 2,4,7,9,155,16 0 0 WLC 0 0 0 0 / / / /
House at 139 Park Avenue Demolition:
- DB Discovered Building 7-011-001 / / / / 11/13/19 / / 0 0 JSS 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
MT. MARKHAM CSD (FMLYBRIDGWTRWWINFIE STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-20-01-04
last updated on 04/19/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Mount Markham Middle School:
22-1134 Reconstruction 0-001-018 05/09/23 DONE DONE DONE 12/05/22 11/30/22 02/07/22 12/07/21 2,4,7,8,9,155,15,16 7,515,360 7,515,360 WLC 0 0 0 King & King Architects 0 / / 11/30/22
22-0864 Reconstruction 0-001-019 12/28/22 DONE DONE DONE 10/31/22 10/28/22 06/09/22 05/17/22 13,155 100,000 100,000 WLC 0 0 0 King & King Architects 0 06/15/23 10/28/22
- Reconstruction 0-001-020 / / / / 03/01/24 / / 2,4,8,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
Mount Markham Elementary:
22-1135 Reconstruction 0-004-013 05/09/23 DONE DONE DONE 12/05/22 11/30/22 02/07/22 12/07/21 2,4,7,8,9,155,15,16 6,339,560 6,339,560 WLC 0 0 0 King & King Architects 0 / / 11/30/22
23-0648 Reconstruction 0-004-014 12/14/23 DONE DONE DONE 10/06/23 10/05/23 06/23/23 05/16/23 9,16 100,000 100,000 WLC 0 0 0 King & King Architects 0 / / 10/05/23
- Reconstruction 0-004-015 / / / / 03/01/24 / / 2,4,7,8,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
- Reconstruction 0-004-016 / / / / 03/01/24 / / 9,16 0 0 WLC 0 0 0 0 / / / /
Mt. Markham Sr. High:
19-1580 Reconstruction 0-011-016 05/13/20 DONE DONE DONE 03/16/20 03/12/20 02/27/20 05/21/19 9 100,000 100,000 JSS 0 0 0 King & King Architects 0 06/29/21 03/12/20
20-0831 Reconstruction 0-011-017 02/16/21 DONE DONE DONE 11/16/20 10/09/20 02/27/20 06/09/20 9 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/29/21 10/09/20
20-1623 Reconstruction 0-011-018 06/02/21 DONE DONE DONE 04/23/21 04/21/21 03/17/21 05/18/21 8,9 100,000 100,000 JLB 0 0 0 King & King Architects 0 09/01/21 04/21/21
22-1136 Reconstruction 0-011-019 05/09/23 DONE DONE DONE 12/05/22 11/30/22 02/07/22 12/07/21 2,4,8,9,155,15,16 7,478,640 7,478,640 WLC 0 0 0 King & King Architects 0 / / 11/30/22
- Reconstruction 0-011-020 / / / / 03/01/24 / / 9,155,15,16 0 0 WLC 0 0 0 0 / / / /
- Reconstruction 0-011-021 / / / / 03/01/24 / / 2,4,7,8,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
Bus Garage:
22-1137 Reconstruction 5-009-011 05/09/23 DONE DONE DONE 12/05/22 11/30/22 02/07/22 12/07/21 2,4,8,9,14,155,15,16 4,561,440 4,561,440 WLC 0 0 0 King & King Architects 0 / / 11/30/22
- Reconstruction 5-009-012 / / / / 03/01/24 / / 4,7,8,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
CENTRAL VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-21-01-04
last updated on 04/19/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Central Valley Academy:
20-0829 Reconstruction 0-001-014 02/10/21 DONE DONE DONE 11/16/20 10/29/20 07/01/20 06/09/20 9 100,000 100,000 JSS 0 0 0 King & King Architects 0 06/24/21 10/29/20
22-0063 Reconstruction 0-001-015 11/15/22 DONE DONE DONE 07/11/22 07/08/22 05/26/22 05/17/22 2,9 490,000 490,000 SLC 0 0 0 King & King Architects 0 / / 07/08/22
22-1067 Reconstruction 0-001-016 12/06/22 DONE DONE DONE 11/28/22 11/25/22 11/10/22 05/17/22 13 60,000 60,000 SLC 0 0 0 King & King Architects 0 / / 11/25/22
23-0540 Reconstruction 0-001-017 DONE ADD. REQ'D DONE 09/22/23 09/21/23 07/11/23 05/17/22 2,4,7,8,9,10,155,15, 11,468,000 11,468,000 MSK 0 0 0 King & King Architects 0 / / 09/21/23
23-0878 Reconstruction 0-001-018 UNREVIEWED 11/03/23 10/30/23 09/29/23 09/20/23 2,10,16 0 0 MSK 0 0 0 King & King Architects 0 / / 10/30/23
- Reconstruction 0-001-019 / / / / 10/05/23 / / 2,10,16 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-001-020 / / / / 02/26/24 / / 9 0 0 MSK 0 0 0 0 / / / /
Fisher Elem School:
21-0653 Reconstruction 0-003-003 12/30/21 DONE DONE DONE 11/04/21 11/04/21 04/14/21 05/18/21 9,16 100,000 100,000 SLC 0 0 0 King & King Architects 0 06/24/22 11/04/21
23-0541 Reconstruction 0-003-004 DONE ADD. REQ'D DONE 09/22/23 09/21/23 07/11/23 05/17/22 2,4,7,8,9,10,155,15, 2,982,000 0 MSK 0 0 0 King & King Architects 0 / / 09/21/23
District-Wide:
23-0349 Reconstruction 7-999-001 10/11/23 DONE DONE DONE 08/30/23 08/29/23 05/25/23 05/16/23 100,000 100,000 JLB 0 0 0 King & King Architects 0 / / 08/29/23
23-0780SB Reconstruction 7-999-002 DONE / / / / 10/23/23 / / 0 0 MSK 0 0 0 0 / / / /
23-1138 Reconstruction 7-999-002 UNREVIEWED 12/07/23 12/06/23 / / 11/04/14 0 0 MSK 0 0 0 King & King Architects 0 / / 12/06/23
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 JSS 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
BOCES HERKIMER-FULTON-HAMILT-OTSEGO STATUS REPORT ON CAPITAL PROJECTS
District No.: 21-90-00-00
last updated on 04/19/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Busacker Educational Complex:
23-0099 Reconstruction 0-007-020 01/25/24 DONE DONE DONE 07/17/23 07/17/23 02/08/22 09/27/22 2,4,7,8,9,10,155,15, 23,972,000 23,972,000 WLC 0 0 0 King & King Architects 0 / / 07/17/23
Remington Educational Complex:
21-0657DB Discovered Building 0-021-001 11/18/21 DONE DONE DONE 11/05/21 / / 09/17/21 / / 2,4,7,8,9,155,15,16 0 18,617,954 JLB 0 0 0 0 / / / /
22-1302 Reconstruction 0-021-002 04/25/23 DONE DONE DONE 12/21/22 12/21/22 02/08/22 12/08/22 2,4,7,8,9,10,155,15, 175,000 175,000 WLC 0 0 0 King & King Architects 0 02/01/24 12/21/22
East German Street:
22-1299TQ Temporary Quarters 8-022-001 DONE ADD. REQ'D DONE 12/21/22 12/15/22 02/08/22 / / 0 0 WLC 0 0 0 0 / / 12/15/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED