Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 04/24/24 at 08:10:44




COPENHAGEN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 23-02-01-04
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
19-0254   Reconstruction               0-001-016  01/22/20     DONE    DONE       DONE      08/15/19   07/29/19   05/01/18   01/14/19   2,4,8,9,10,155,15,16   5,147,626     5,147,626  JLB             0           0           0 William Taylor Architects, PL           0      02/05/21                       07/29/19           
21-1981   Reconstruction               0-001-017  08/02/22     DONE    DONE       DONE      06/15/22   06/14/22   04/04/22   05/17/22   4                        100,000       100,000  WLC             0           0           0 Bergmann Associates                     0      11/17/22                       06/14/22           
22-2345   Reconstruction               0-001-018  07/17/23     DONE    DONE       DONE      06/09/23   06/08/23   04/11/23   05/16/23   4                        100,000       100,000  WLC             0           0           0 Bergmann Associates                     0      11/17/23                       06/08/23           

          Bus Garage (demolition 2020):
19-1158   Reconstruction               4-003-004  01/22/20     DONE    DONE       DONE      01/14/20   01/14/20   05/01/18   01/14/19   16                        30,000             0  JLB             0           0           0                                         0        /  /                         01/14/20           

          Bus Garage:
19-0255   Reconstruction               5-002-008  01/22/20     DONE    DONE       DONE      08/15/19   07/28/19   05/01/18   01/14/19   2,4,7,8,9,155,15,16      622,534       622,534  JLB             0           0           0 William Taylor Architects, PL           0      02/10/21                       07/28/19           
  -       Reconstruction               5-002-009                                              /  /       /  /       /  /       /  /     10                             0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Press Box:
19-0817   New Construction             7-004-001  01/22/20     DONE    DONE       DONE      12/13/19   12/12/19   11/12/19   01/14/19   02 - 16                   30,000             0  JLB             0           0           0                                         0      02/10/21                       12/12/19           

          Concession Stand:
  -    PR New Construction             7-005-001                                              /  /       /  /     07/15/20     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
20-0658   New Construction             7-005-001  01/08/21     DONE    DONE       DONE      10/21/20   10/19/20   07/15/20   01/14/19   02 - 16                  150,000             0  JLB             0           0           0 Bergmann Associates, Engineer           0        /  /                         10/19/20           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HARRISVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 23-03-01-04
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elem. & High School K-12:
18-0742   Reconstruction               0-001-013  05/07/19     DONE    DONE       DONE      10/26/18   10/25/18   01/29/18   11/04/14   16                       260,000       260,000  SLC             0           0           0 March Associates                        0        /  /                         10/25/18           
19-0734   Reconstruction               0-001-015  01/15/20     DONE    DONE       DONE      11/07/19   10/29/19   06/20/19   05/21/19   4,8,9,155,15,16          100,000       100,000  SLC             0           0           0 March Associates                        0      06/24/20                       10/29/19           
19-0910   Reconstruction               0-001-016  03/25/20     DONE    DONE       DONE      12/03/19   11/20/19   07/26/19   09/30/19   155,15,16                500,000       500,000  SLC             0           0           0 March Associates                        0      08/04/21                       11/20/19           
19-1138   Reconstruction               0-001-017  03/25/20     DONE    DONE       DONE      01/03/20   12/20/19   11/20/19   09/30/19   9,16                     500,000       500,000  SLC             0           0           0 March Associates                        0      08/04/21                       12/20/19           
20-0282   Reconstruction               0-001-018  10/17/20     DONE    DONE       DONE      08/31/20   08/20/20   07/23/20   06/16/20   4                        100,000       100,000  SLC             0           0           0 March Associates                        0      05/18/21                       08/20/20           
22-0125   Reconstruction               0-001-019  11/14/22     DONE    DONE       DONE      07/20/22   07/19/22   07/28/21   05/17/22   8,16                     100,000       100,000  SLC             0           0           0 March Associates                        0      06/08/23                       07/19/22           
23-0096   Reconstruction               0-001-020  09/21/23     DONE    DONE       DONE      07/17/23   07/17/23   06/07/23   05/16/23   8,15,16                  100,000       100,000  MSK             0           0           0 March Associates                        0        /  /                         07/17/23           

          Bus Garage:
21-0232   Reconstruction               5-002-009  11/04/21     DONE    DONE       DONE      08/26/21   08/25/21   08/05/21   05/18/21   8,16                     100,000       100,000  SLC             0           0           0 March Associates                        0      06/14/22                       08/25/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LOWVILLE ACADEMY & CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 23-09-01-04
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Academy School:
19-0422   Reconstruction               0-001-015  11/04/19     DONE    DONE       DONE      09/18/19   09/13/19   07/26/19   05/21/19   8                        100,000       100,000  SLC             0           0           0 Mosaic Associates                       0      06/01/20                       09/13/19           
  -    XX Reconstruction               0-001-016                         CANCELLED            /  /       /  /     05/19/20     /  /                                    0    44,274,466  SLC             0           0           0                                         0        /  /                           /  /             
19-1731XX Reconstruction               0-001-016                         CANCELLED            /  /       /  /     05/19/20     /  /                                    0    44,274,466  SLC             0           0           0                                         0        /  /                           /  /             
19-1844SB Reconstruction               0-001-017               DONE                           /  /       /  /     06/15/20     /  /     16                             0             0  SLC             0           0           0                                         0        /  /                           /  /             
20-0556   Reconstruction               0-001-017  12/11/20     DONE    DONE       DONE      10/07/20   09/28/20   06/15/20   06/08/20   16                       295,000             0  SLC             0           0           0 March Associates                        0      04/30/21                       09/28/20           
20-0558   Reconstruction               0-001-018  12/24/20     DONE    DONE       DONE      10/07/20   10/01/20   09/14/20   06/16/20   14                       100,000       100,000  SLC             0           0           0 March Associates                        0      06/25/21                       10/01/20           
20-1387   Reconstruction               0-001-019  05/26/21     DONE    DONE       DONE      03/08/21   03/04/21   01/21/21   05/18/21   4,14                     100,000       100,000  SLC             0           0           0 March Associates                        0      12/30/21                       03/04/21           
22-0192   Reconstruction               0-001-020  11/06/22     DONE    DONE       DONE      07/29/22   07/28/22   04/25/22   05/17/22   8                        100,000       100,000  SLC             0           0           0 March Associates                        0      06/20/23                       07/28/22           
22-0411FA Reconstruction               0-001-021  11/28/22     DONE    DONE       DONE      09/07/22   07/28/22   04/29/22   03/24/21   16                       574,584             0  SLC             0           0           0 March Associates                        0        /  /                         07/28/22           
  -    PR Alterations                  0-001-022                                              /  /       /  /     12/06/22     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             
22-2285   Alterations                  0-001-022  10/12/23     DONE    DONE       DONE      05/24/23   05/18/23   12/06/22   10/25/22   02 - 16               14,500,000    14,500,000  MSK             0           0           0 March Associates                        0        /  /                         05/18/23           
23-0591   Reconstruction               0-001-023  12/21/23     DONE    DONE       DONE      10/02/23   10/02/23   08/01/23   05/16/23   8,9,155,16               100,000       100,000  JLB             0           0           0 March Associates                        0        /  /                         10/02/23           
  -    XX Reconstruction               0-001-BA2                         CANCELLED            /  /       /  /       /  /       /  /     16                             0    44,274,466  SLC             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               0-001-BA3               DONE                           /  /       /  /       /  /       /  /     16                             0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
22-2286   Reconstruction               5-005-008  10/12/23     DONE    DONE       DONE      05/24/23   05/18/23   12/20/22   10/25/22   2,155                    300,000       300,000  MSK             0           0           0 March Associates                        0        /  /                         05/18/23           

          New Press Box:
22-2287   New Construction             7-018-001  10/12/23     DONE    DONE       DONE      05/24/23   05/18/23   03/30/23   10/25/22   02 - 16                  100,000             0  MSK             0           0           0 March Associates                        0        /  /                         05/18/23           

          XXVolunteer Fire Dept. Mtg Hall-Canc:
  -    XX Reconstruction               8-015-001                         CANCELLED            /  /       /  /     07/24/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          XXSt.Peters Catholic Church Basement:
  -    XX Reconstruction               8-016-001                         CANCELLED            /  /       /  /     07/24/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          XXLCJCC Educ Ctr Classrooms-Canceled:
  -    XX Reconstruction               8-017-001                         CANCELLED            /  /       /  /     07/24/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




DOLGEVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 23-10-03-04
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          XXDugout 1 - wrong Distr #:
  -    XX New Construction             7-011-001                         CANCELLED          10/07/20   09/28/20   06/11/20   02/25/20   02 - 16                   18,600             0  SLC             0           0           0 SEI Design Group                        0        /  /                         09/28/20           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SOUTH LEWIS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 23-11-01-04
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          South Lewis ES-MS-HS (formerly HS):
18-1934PR Additions and Alterations    0-013-018               DONE                         05/10/19     /  /     06/29/17     /  /     02 - 16                        0    34,943,991  MTM             0           0           0 SEI Design Group                        0        /  /                           /  /             
19-0413   Additions and Alterations    0-013-018  01/06/20     DONE    DONE       DONE      09/17/19   09/06/19   06/29/17   10/23/18   02 - 16               38,664,600    25,537,315  JLB             0           0     200,307 SEI Design Group                        0      09/17/21                       09/06/19           
18-2072   Reconstruction               0-013-021  07/12/19     DONE    DONE       DONE      06/07/19   06/03/19   03/14/19   05/21/19   2,4,7,8,9,155,15,16      100,000       100,000  JLB             0           0           0 SEI Design Group                        0      02/25/20                       06/03/19           
19-1642   Reconstruction               0-013-022  06/18/20     DONE    DONE       DONE      03/30/20   03/25/20   01/15/20   06/09/20   2,4,8,9,155,15,16        100,000       100,000  JLB             0           0           0 SEI Design Group                        0      02/24/21                       03/25/20           
21-0448   Reconstruction               0-013-023  10/27/21     DONE    DONE       DONE      09/30/21   09/28/21   04/14/21   05/18/21   8                        100,000       100,000  JLB             0           0           0 SEI Design Group                        0      06/16/22                       09/28/21           
  -    XX Additions and Alterations    0-013-024                         CANCELLED            /  /       /  /     08/31/21     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-0006   Reconstruction               0-013-025  09/16/22     DONE    DONE       DONE      07/01/22   06/29/22   03/24/22   05/17/22   9,155,15,16              100,000       100,000  SLC             0           0           0 SEI Design Group                        0      06/21/23                       06/29/22           
  -    PR Additions and Alterations    0-013-026               DONE                           /  /       /  /     10/26/23     /  /     02 - 16                        0    44,866,542  MSK             0           0           0                                         0        /  /                           /  /             

          Biomass Boiler Bldg.@ES-MS-HS:
22-1814   Reconstruction               0-018-003  05/24/23     DONE    DONE       DONE      03/10/23   03/08/23   01/31/23   05/16/23   155                      100,000       100,000  JLB             0           0           0 SEI Design Group                        0      10/18/23                       03/08/23           
  -       Reconstruction               0-018-004                                              /  /       /  /     10/26/23     /  /     2,7                            0             0  MSK             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
19-0414   Reconstruction               5-001-008  01/06/20     DONE    DONE       DONE      09/17/19   09/06/19   06/29/17   10/23/18   2,8,9,10,155,15,16       202,900       202,900  JLB             0           0           0 SEI Design Group                        0      09/17/21                       09/06/19           
  -       Reconstruction               5-001-009                                              /  /       /  /     10/26/23     /  /     2,4,8,9,14,155,15,16           0             0  MSK             0           0           0                                         0        /  /                           /  /             

          XXBiomassBoilerBldg.@ES-MS-HSsee0018:
19-0415   Additions and Alterations    7-018-002  01/06/20     DONE    DONE       DONE      09/17/19   09/06/19   06/29/17   10/23/18   02 - 16                   22,300             0  JLB             0           0           0 SEI Design Group                        0      09/17/21                       09/06/19           

          Concession Building:
20-1235   New Construction             7-019-001  03/15/21     DONE    DONE       DONE      02/02/21   02/01/21   06/29/17   10/23/18   02 - 16                  523,700             0  JLB             0           0           0 SEI Design Group                        0      09/20/22                       02/01/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BEAVER RIVER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 23-13-01-04
last updated on 04/24/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building K-12:
18-2163   Reconstruction               0-002-018  12/04/19     DONE    DONE       DONE      06/19/19   06/12/19   10/30/18   10/11/18   2,7,8,9,10,155,15,16   6,974,000     6,974,000  SLC             0           0           0 King & King Architects                  0      01/31/21                       06/12/19           
19-1676   Reconstruction               0-002-019  06/22/20     DONE    DONE       DONE      04/09/20   03/27/20   06/12/19   05/21/19   16                       100,000       100,000  SLC             0           0           0 King & King Architects                  0      12/09/20                       03/27/20           
20-1386   Reconstruction               0-002-020  04/15/21     DONE    DONE       DONE      03/08/21   03/01/21   01/21/21   06/16/20   9,16                     100,000       100,000  SLC             0           0           0 King & King Architects                  0      03/01/22                       03/01/21           
21-1011   Reconstruction               0-002-021  02/09/22     DONE    DONE       DONE      01/03/22   12/30/21   10/19/21   05/18/21   8,9,16                   100,000       100,000  SLC             0           0           0 King & King Architects                  0      02/03/23                       12/30/21           
22-0726   Reconstruction               0-002-022  02/14/23     DONE    DONE       DONE      10/14/22   10/14/22   09/27/22   05/17/22   2,9                      100,000       100,000  WLC             0           0           0 King & King Architects                  0      01/02/24                       10/14/22           
23-1054   Reconstruction               0-002-023  01/11/24     DONE    DONE       DONE      11/28/23   11/22/23   11/16/23   05/16/23   8,15,16                  100,000       100,000  JLB             0           0           0 King & King Architects                  0        /  /                         11/22/23           

          Bus Garage:
18-2164   New Construction             5-004-001  12/04/19     DONE    DONE       DONE      06/19/19   06/12/19   11/01/18   10/11/18   02 - 16                5,000,000     5,000,000  SLC             0           0           0 King & King Architects                  0      01/31/21                       06/12/19           

          House-Demolition Only:
19-0521DB Discovered Building          7-001-001  12/04/19     DONE    DONE       DONE      10/07/19   10/03/19   09/23/19     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         10/03/19           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED