ADIRONDACK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-04-01-06
last updated on 04/25/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Boonville Central(Elementary):
19-0894 Reconstruction 0-002-008 02/27/20 DONE DONE DONE 12/03/19 11/13/19 08/06/18 05/15/18 2,4,7,8,9,10,155,15, 3,355,798 3,355,798 JLB 0 0 0 King & King Architects 0 11/19/21 11/13/19
19-0983 Reconstruction 0-002-009 01/08/20 DONE DONE DONE 12/11/19 11/25/19 09/13/19 08/13/19 14 80,000 80,000 JLB 0 0 0 King & King Architects 0 06/30/20 11/25/19
West Leyden Elementary School:
19-0895 Reconstruction 0-013-008 02/28/20 DONE DONE DONE 12/03/19 11/13/19 08/06/18 05/15/18 2,4,7,8,9,155,15,16 1,732,000 1,732,000 JLB 0 0 0 King & King Architects 0 05/12/21 11/13/19
Senior High School:
19-0896 Reconstruction 0-017-011 02/28/20 DONE DONE DONE 12/03/19 11/13/19 08/06/18 05/15/18 2,4,7,8,9,10,13,155, 7,845,000 7,845,000 JLB 0 0 0 King & King Architects 0 10/18/21 11/13/19
19-0647 Reconstruction 0-017-012 01/08/20 DONE DONE DONE 10/31/19 10/17/19 05/31/19 05/21/19 9,155,15,16 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/30/20 10/17/19
20-0575 Reconstruction 0-017-013 12/04/20 DONE DONE DONE 10/13/20 10/09/20 06/17/20 06/09/20 155 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/24/21 10/09/20
21-1903 Reconstruction 0-017-014 11/09/22 DONE DONE DONE 05/31/22 05/27/22 01/19/22 05/15/18 2,4,8,9,10,155,15,16 300,000 300,000 WLC 0 0 0 King & King Architects 0 07/06/23 05/27/22
22-0170PR Alterations 0-017-015 STARTED 07/27/22 / / 04/25/22 / / 0 0 WLC 0 0 0 0 / / / /
22-0130 Reconstruction 0-017-016 10/25/22 DONE DONE DONE 07/22/22 07/21/22 06/14/22 05/17/22 16 100,000 100,000 WLC 0 0 0 King & King Architects 0 04/14/23 07/21/22
22-2289 Reconstruction 0-017-017 07/05/23 DONE DONE DONE 05/30/23 05/25/23 05/02/23 05/16/23 4,9 100,000 100,000 WLC 0 0 0 King & King Architects 0 10/26/23 05/25/23
- Reconstruction 0-017-018 / / / / 03/11/24 / / 155 0 0 WLC 0 0 0 0 / / / /
Bus Garage:
21-0055 Reconstruction 5-001-007 08/06/21 DONE DONE DONE 07/16/21 07/15/21 05/06/21 05/18/21 13,15,16 100,000 100,000 JLB 0 0 0 King & King Architects 0 02/14/22 07/15/21
21-0428 Reconstruction 5-001-008 11/17/21 DONE DONE DONE 09/24/21 09/24/21 05/06/21 05/15/18 2,4,14,15,16 2,009,800 2,009,800 JLB 0 0 0 King & King Architects 0 12/16/22 09/24/21
23-0592XX Reconstruction 5-001-009 CANCELLED 10/02/23 10/02/23 03/15/23 10/24/23 16 0 0 WLC 0 0 0 King & King Architects 0 / / 10/02/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
CAMDEN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-06-01-04
last updated on 04/25/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Middle School:
21-0087 Reconstruction 0-001-025 12/01/21 DONE DONE DONE 07/23/21 07/21/21 04/19/21 05/18/21 8,155,15,16 632,935 632,935 JLB 0 0 0 Hunt Engineers,Architects & l 632,935 06/09/23 07/21/21
21-0457 Reconstruction 0-001-026 04/12/22 DONE DONE DONE 10/01/21 09/30/21 08/10/21 05/18/21 2,4,7,8,9,155,15,16 1,942,194 1,942,194 JLB 0 0 0 Hunt Engineers,Architects & l 0 09/21/23 09/30/21
22-1060 Reconstruction 0-001-027 06/06/23 DONE DONE DONE 11/28/22 11/25/22 10/05/22 05/18/21 2,4,7,8,9,155,15,16 5,622,874 5,622,874 JJH 0 0 0 Hunt Engineers,Architects & l 0 / / 11/25/22
22-1108FA Reconstruction 0-001-028 04/05/23 DONE DONE DONE 12/02/22 11/25/22 10/05/22 12/13/22 7,155,16 821,968 821,968 JJH 0 0 0 Hunt Engineers,Architects & l 0 / / 11/25/22
Camden Elementary:
21-0088 Reconstruction 0-003-019 12/01/21 DONE DONE DONE 07/23/21 07/21/21 04/19/21 05/18/21 8,16 281,074 281,074 JLB 0 0 0 Hunt Engineers,Architects & l 281,074 06/09/23 07/21/21
21-0072 Reconstruction 0-003-020 10/04/21 DONE DONE DONE 07/20/21 07/19/21 05/21/21 05/18/21 9 100,000 100,000 JLB 0 0 0 Hunt Engineers,Architects & l 0 05/02/22 07/19/21
21-0458 Reconstruction 0-003-021 04/12/22 DONE DONE DONE 10/01/21 09/30/21 08/10/21 05/18/21 2,7,9,155,15,16 2,730,929 2,730,929 JLB 0 0 0 Hunt Engineers,Architects & l 0 09/21/23 09/30/21
McConnellsville Elementary:
19-0062 Reconstruction 0-007-011 08/16/19 DONE DONE DONE 07/12/19 07/05/19 06/18/19 05/21/19 9 100,000 100,000 JLB 0 0 0 King & King Architects 0 03/01/20 07/05/19
- PR Additions and Alterations 0-007-012 / / / / 07/01/20 / / 02 - 16 0 942,225 JLB 0 0 0 0 / / / /
22-1061 Additions and Alterations 0-007-012 06/06/23 DONE DONE DONE 11/28/22 11/25/22 07/01/20 05/18/21 02 - 16 9,461,556 6,861,786 JJH 0 0 0 Hunt Engineers,Architects & l 0 / / 11/25/22
21-0089 Reconstruction 0-007-013 12/01/21 DONE DONE DONE 07/23/21 07/21/21 04/19/21 05/18/21 8,16 42,242 42,242 JLB 0 0 0 Hunt Engineers,Architects & l 42,242 06/09/23 07/21/21
21-0459 Reconstruction 0-007-014 04/12/22 DONE DONE DONE 10/01/21 09/30/21 08/10/21 05/18/21 2,4,7,9,155,15,16 249,103 249,103 JLB 0 0 0 Hunt Engineers,Architects & l 0 09/21/23 09/30/21
Camden High School:
21-0090 Reconstruction 0-012-020 12/01/21 DONE DONE DONE 07/23/21 07/21/21 04/19/21 05/18/21 8,155,15,16 972,725 972,725 JLB 0 0 0 Hunt Engineers,Architects & l 972,725 06/09/23 07/21/21
21-0460 Reconstruction 0-012-021 04/12/22 DONE DONE DONE 10/01/21 09/30/21 08/10/21 05/18/21 2,8,9,155,15,16 4,999,553 4,999,553 JLB 0 0 0 Hunt Engineers,Architects & l 0 09/21/23 09/30/21
22-1062 Reconstruction 0-012-022 06/06/23 DONE DONE DONE 11/28/22 11/25/22 10/05/22 05/18/21 2,4,7,8,9,155,15,16 3,360,031 3,360,031 JJH 0 0 0 Hunt Engineers,Architects & l 0 / / 11/25/22
22-1109FA Reconstruction 0-012-023 04/05/23 DONE DONE DONE 12/02/22 11/25/22 10/05/22 12/12/22 7,155,16 964,436 964,436 JJH 0 0 0 Hunt Engineers,Architects & l 0 / / 11/25/22
23-1739 Reconstruction 0-012-024 UNREVIEWED 04/03/24 04/02/24 03/15/24 / / 7 0 0 JJH 0 0 0 Hunt Engineers,Architects & l 0 / / 04/02/24
Bus Maintenance Facility:
20-0212 Reconstruction 5-008-009 10/06/20 DONE DONE DONE 08/13/20 07/16/20 03/10/20 06/09/20 7 100,000 100,000 JLB 0 0 0 Hunt Engineers,Architects & l 0 06/08/21 07/16/20
21-0091 Reconstruction 5-008-010 12/01/21 DONE DONE DONE 07/23/21 07/21/21 04/19/21 05/18/21 8,16 35,853 35,853 JLB 0 0 0 Hunt Engineers,Architects & l 35,853 06/09/23 07/21/21
21-0461 Reconstruction 5-008-011 04/12/22 DONE DONE DONE 10/01/21 09/30/21 08/10/21 05/18/21 2,155,16 308,632 308,632 JLB 0 0 0 Hunt Engineers,Architects & l 0 09/21/23 09/30/21
23-0352 Reconstruction 5-008-012 10/04/23 DONE DONE DONE 08/30/23 08/28/23 08/16/23 05/16/23 8,9,155,16 100,000 100,000 JJH 0 0 0 Hunt Engineers,Architects & l 0 / / 08/28/23
23-1783 Reconstruction 5-008-013 UNREVIEWED 04/08/24 04/08/24 03/15/24 / / 8,9,155,15,16 0 0 JJH 0 0 0 Hunt Engineers,Architects & l 0 / / 04/08/24
Multi Sports Dugout 1:
- PR New Construction 7-018-001 / / / / 10/05/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-1063 New Construction 7-018-001 06/06/23 DONE DONE DONE 11/28/22 11/25/22 10/05/22 05/18/21 02 - 16 56,950 0 JJH 0 0 0 Hunt Engineers,Architects & l 0 / / 11/25/22
Multi Sports Dugout 2:
- PR New Construction 7-019-001 / / / / 10/05/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-1064 New Construction 7-019-001 06/06/23 DONE DONE DONE 11/28/22 11/25/22 10/05/22 05/18/21 02 - 16 56,950 0 JJH 0 0 0 Hunt Engineers,Architects & l 0 / / 11/25/22
Baseball Pressbox&Concess:
- PR New Construction 7-020-001 / / / / 10/05/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-1065 New Construction 7-020-001 06/06/23 DONE DONE DONE 11/28/22 11/25/22 10/05/22 05/18/21 02 - 16 504,320 0 JJH 0 0 0 Hunt Engineers,Architects & l 0 / / 11/25/22
Multi Sports Pressbox:
- PR New Construction 7-021-001 / / / / / / / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-1066 New Construction 7-021-001 06/06/23 DONE DONE DONE 11/28/22 11/25/22 / / 05/18/21 02 - 16 182,000 0 JJH 0 0 0 Hunt Engineers,Architects & l 0 / / 11/25/22
District-Wide:
20-0316SB Reconstruction 7-999-003 DONE / / / / 09/02/20 / / 16 0 0 JLB 0 0 0 0 / / / /
20-1316 Reconstruction 7-999-003 09/14/21 DONE DONE DONE 02/18/21 02/12/21 09/02/20 11/04/14 16 1,676,800 1,676,800 JLB 0 0 0 Hunt Engineers,Architects & l 0 / / 02/12/21
22-0161 Reconstruction 7-999-004 09/09/22 DONE DONE DONE 07/25/22 07/25/22 / / 05/17/22 100,000 100,000 JLB 0 0 0 Hunt Engineers,Architects & l 0 06/20/23 07/25/22
- SB Reconstruction 7-999-BA3 DONE / / / / / / / / 16 0 0 JLB 0 0 0 0 / / / /
Administration:
21-0092 Reconstruction 9-002-004 12/01/21 DONE DONE DONE 07/23/21 07/21/21 04/19/21 05/18/21 8,16 29,572 0 JLB 0 0 0 Hunt Engineers,Architects & l 29,572 06/09/23 07/21/21
21-0462 Reconstruction 9-002-005 04/12/22 DONE DONE DONE 10/01/21 09/30/21 08/10/21 05/18/21 155,16 35,675 0 JLB 0 0 0 Hunt Engineers,Architects & l 0 09/21/23 09/30/21
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
NEW YORK MILLS UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-15-04-02
last updated on 04/25/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
K-12 School:
19-0400 Reconstruction 0-002-013 10/01/19 DONE DONE DONE 09/11/19 09/03/19 03/07/19 05/21/19 2,10,16 100,000 100,000 SLC 0 0 0 Teitsch-Kent 0 06/01/20 09/03/19
20-0159 Reconstruction 0-002-014 10/09/20 DONE DONE DONE 08/07/20 07/30/20 12/04/19 12/03/19 2,4,8,9,10,155,15,16 67,000 67,000 SLC 0 0 0 Teitsch-Kent 0 / / 07/30/20
20-0381 Reconstruction 0-002-015 12/02/20 DONE DONE DONE 09/16/20 09/10/20 06/18/20 06/09/20 4,8,9,10,155,15,16 100,000 100,000 SLC 0 0 0 Teitsch-Kent 0 06/16/21 09/10/20
20-1498 Reconstruction 0-002-016 02/26/22 DONE DONE DONE 03/26/21 03/19/21 08/21/20 10/22/20 2,4,8,9,10,155,15,16 1,271,660 1,271,660 SLC 0 0 0 Teitsch-Kent 1,271,660 11/29/23 03/19/21
20-0702 Reconstruction 0-002-017 02/09/21 DONE DONE DONE 10/28/20 10/26/20 09/14/20 12/03/19 2,4,8,9,10,16 1,472,250 1,472,250 SLC 0 0 0 Teitsch-Kent 0 08/09/22 10/26/20
21-0383 Reconstruction 0-002-018 12/13/21 DONE DONE DONE 09/20/21 09/20/21 05/26/21 05/18/21 4,8,9,10,155,15,16 100,000 100,000 SLC 0 0 0 Teitsch-Kent 0 05/23/22 09/20/21
23-1035 Reconstruction 0-002-019 12/20/23 DONE DONE DONE 11/17/23 11/16/23 05/24/23 05/16/23 4,8,9,155,16 100,000 100,000 MSK 0 0 0 Teitsch-Kent 0 / / 11/16/23
- PR Additions and Alterations 0-002-020 / / / / 01/25/24 / / 02 - 16 0 0 MSK 0 0 0 0 / / / /
Beekman Gym -UsedForAdmin-NoBldgAid:
20-1499 Reconstruction 0-005-008 02/26/22 DONE DONE DONE 03/26/21 03/19/21 08/21/20 10/22/20 2,4,8,9,10,155,15,16 103,190 0 SLC 0 0 0 Teitsch-Kent 103,190 11/29/23 03/19/21
Bus Garage:
20-1500 Reconstruction 5-003-006 02/26/22 DONE DONE DONE 03/26/21 03/19/21 08/21/20 10/22/20 2,4,8,9,10,155,15,16 13,305 13,305 SLC 0 0 0 Teitsch-Kent 13,305 11/29/23 03/19/21
21-0384 Reconstruction 5-003-007 10/03/21 DONE DONE DONE 09/20/21 09/20/21 07/27/21 08/03/21 2,4,9,15 125,000 125,000 SLC 0 0 0 Teitsch-Kent 0 12/08/21 09/20/21
22-0390 Reconstruction 5-003-008 11/15/22 DONE DONE DONE 09/02/22 09/01/22 05/23/22 05/17/22 2,9,16 100,000 100,000 SLC 0 0 0 Teitsch-Kent 0 05/22/23 09/01/22
Press Box:
20-0703 Reconstruction 7-004-001 02/09/21 DONE DONE DONE 10/28/20 10/26/20 01/29/20 12/03/19 2,8,10,16 4,500 0 SLC 0 0 0 Teitsch-Kent 0 08/09/22 10/26/20
District-Wide:
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
ROME CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-18-00-01
last updated on 04/25/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Francis Bellamy School:
20-0407 Reconstruction 0-001-008 02/17/21 DONE DONE DONE 09/22/20 07/21/20 04/23/20 12/18/19 10,155,16 519,203 519,203 JLB 0 0 0 C&S Companies 519,203 / / 07/21/20
- Reconstruction 0-001-009 / / / / 09/09/21 / / 2,4,7,8,9,10,155,15, 0 0 JLB 0 0 0 0 / / / /
Jerry C. Clough Elementary:
19-0386PR Additions and Alterations 0-004-012 STARTED 09/09/19 / / 12/19/18 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
20-0408 Reconstruction 0-004-013 02/17/21 DONE DONE DONE 09/22/20 07/21/20 04/23/20 12/18/19 9,155,16 559,749 559,749 JLB 0 0 0 C&S Companies 559,749 / / 07/21/20
20-1454 Reconstruction 0-004-014 05/03/21 DONE DONE DONE 03/23/21 03/15/21 09/30/20 10/08/20 2,9,15 72,762 72,762 JLB 0 0 0 Labella Associates, P.C. 0 / / 03/15/21
23-0190 Reconstruction 0-004-015 01/11/24 DONE DONE DONE 08/04/23 08/04/23 09/09/21 03/22/22 2,4,8,9,10,155,15,16 33,000 33,000 WLC 0 0 0 LaBella Associates P.C. 0 / / 08/04/23
Gansevoort Elementary:
20-0409 Reconstruction 0-008-014 02/17/21 DONE DONE DONE 09/22/20 07/21/20 04/23/20 12/18/19 10,155,16 414,462 414,462 JLB 0 0 0 C&S Companies 414,462 / / 07/21/20
- Reconstruction 0-008-015 / / / / 09/09/21 / / 2,4,7,8,9,10,155,15, 0 0 JLB 0 0 0 0 / / / /
Strough Middle School:
20-0410 Reconstruction 0-012-023 02/17/21 DONE DONE DONE 09/22/20 07/21/20 04/23/20 12/18/19 10,155,16 305,885 305,885 JLB 0 0 0 C&S Companies 305,885 / / 07/21/20
23-0191 Reconstruction 0-012-024 01/11/24 DONE DONE DONE 08/04/23 08/04/23 10/31/22 03/22/22 4,7,9,10,155,15,16 181,500 181,500 WLC 0 0 0 LaBella Associates P.C. 0 / / 08/04/23
Ridge Mills Elementary:
20-0415 Reconstruction 0-013-009 02/17/21 DONE DONE DONE 09/24/20 09/23/20 04/23/20 12/18/19 10,155,16 318,755 318,755 JLB 0 0 0 C&S Companies 318,755 / / 09/23/20
- Reconstruction 0-013-010 / / / / 09/09/21 / / 2,4,7,8,9,10,155,15, 0 0 JLB 0 0 0 0 / / / /
Staley Upper ES:
18-0100 Reconstruction 0-016-018 05/21/19 DONE DONE DONE 07/23/18 07/19/18 07/03/18 07/20/17 155,15,16 1,317,042 0 MTM 0 0 0 C&S Companies 1,317,042 / / 07/19/18
- Reconstruction 0-016-020 / / / / 09/09/21 / / 2,4,8,9,10,155,15,16 0 0 JLB 0 0 0 0 / / / /
Stokes Elementary:
20-0411 Reconstruction 0-017-016 02/17/21 DONE DONE DONE 09/22/20 07/21/20 04/23/20 12/18/19 10,155,16 355,024 355,024 JLB 0 0 0 C&S Companies 355,024 / / 07/21/20
- Reconstruction 0-017-017 / / / / 09/09/21 / / 2,4,7,8,9,10,155,15, 0 0 JLB 0 0 0 0 / / / /
John Joy Elementary:
20-0412 Reconstruction 0-018-014 02/17/21 DONE DONE DONE 09/22/20 07/21/20 04/23/20 12/18/19 10,155,16 309,130 309,130 JLB 0 0 0 C&S Companies 309,130 / / 07/21/20
- Reconstruction 0-018-015 / / / / 09/09/21 / / 2,4,7,8,9,10,155,15, 0 0 JLB 0 0 0 0 / / / /
Denti Elementary:
20-0413 Reconstruction 0-023-014 02/17/21 DONE DONE DONE 09/22/20 07/21/20 04/23/20 12/18/19 10,155,16 596,473 596,473 JLB 0 0 0 C&S Companies 596,473 / / 07/21/20
- Reconstruction 0-023-015 / / / / 09/09/21 / / 2,4,7,8,9,10,155,15, 0 0 JLB 0 0 0 0 / / / /
Rome Free Academy (High School):
18-0101 Reconstruction 0-026-005 05/21/19 DONE DONE DONE 07/23/18 07/19/18 07/03/18 07/20/17 10,155,15,16 3,610,958 3,610,958 JLB 0 0 0 C&S Companies 3,610,958 08/19/20 07/19/18
19-1757 Additions and Alterations 0-026-006 06/09/20 DONE DONE DONE 05/22/20 05/04/20 01/02/19 12/18/19 02 - 16 2,649,730 2,649,730 JLB 0 0 0 LaBella Associates P.C. 0 / / 05/04/20
20-0414 Reconstruction 0-026-007 02/17/21 DONE DONE DONE 09/22/20 07/21/20 04/23/20 12/18/19 155 206,319 206,319 JLB 0 0 0 C&S Companies 206,319 / / 07/21/20
20-0973 Reconstruction 0-026-008 03/05/21 DONE DONE DONE 12/15/20 12/07/20 11/06/20 12/18/19 2,4,7,8,9,13,155,15, 7,996,325 7,996,325 JLB 0 0 0 LaBella Associates P.C. 0 / / 12/07/20
21-1237 Reconstruction 0-026-009 07/29/22 DONE DONE DONE 02/07/22 02/03/22 08/09/21 12/18/19 2,8,9,10,16 1,998,750 1,998,750 FMJ 0 0 0 LaBella Associates 0 / / 02/03/22
22-2144 Reconstruction 0-026-010 01/19/24 DONE DONE DONE 05/05/23 05/04/23 09/09/21 03/22/22 2,4,7,8,9,10,13,155, 14,624,386 14,624,386 WLC 0 0 0 LaBella Associates P.C. 0 / / 05/04/23
Bellamy Elementary Storage:
- PR New Construction 2-050-001 / / / / 04/06/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
Concession-Toilet Bldg:
- PR New Construction 7-053-001 / / / / 01/27/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
RFA Baseball Pressbox:
- PR New Construction 7-055-001 / / / / 10/19/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
23-1383 New Construction 7-055-001 01/19/24 DONE DONE DONE 01/17/24 11/15/23 10/19/23 03/22/22 02 - 16 246,000 0 WLC 0 0 0 LaBella Associates P.C. 0 / / 11/15/23
RFA-BH (Home Dugout):
- PR New Construction 7-056-001 / / / / 10/19/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
23-1384 New Construction 7-056-001 01/19/24 DONE DONE DONE 01/17/24 11/15/23 10/19/23 03/22/22 02 - 16 138,000 0 WLC 0 0 0 LaBella Associates P.C. 0 / / 11/15/23
RFA-BV (Dugout Visitor):
- PR New Construction 7-057-001 / / / / 10/19/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
23-1385 New Construction 7-057-001 01/19/24 DONE DONE DONE 01/17/24 11/15/23 10/19/23 03/22/22 02 - 16 138,000 0 WLC 0 0 0 LaBella Associates P.C. 0 / / 11/15/23
RFA-SH (Softball Dugout Home):
- PR New Construction 7-058-001 / / / / 10/19/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
23-1386 New Construction 7-058-001 01/19/24 DONE DONE DONE 01/17/24 11/15/23 10/19/23 03/22/22 02 - 16 138,000 0 WLC 0 0 0 LaBella Associates P.C. 0 / / 11/15/23
RFA-SV Softball Dugout Visitor:
- PR New Construction 7-059-001 / / / / 10/19/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
23-1387 New Construction 7-059-001 01/19/24 DONE DONE DONE 01/17/24 11/15/23 10/19/23 03/22/22 02 - 16 138,000 0 WLC 0 0 0 LaBella Associates P.C. 0 / / 11/15/23
Averdi Storage @ Ridge Mills ES:
- TQ Temporary Quarters 8-034-001 / / / / 09/09/21 / / 0 0 JLB 0 0 0 0 / / / /
Averdi Storage @ Stokes ES:
- TQ Temporary Quarters 8-035-001 / / / / 09/09/21 / / 0 0 JLB 0 0 0 0 / / / /
Averdi Storage@ Denti ES:
- TQ Temporary Quarters 8-036-001 / / / / 09/09/21 / / 0 0 JLB 0 0 0 0 / / / /
Averdi Storage @ Clough ES:
- TQ Temporary Quarters 8-037-001 / / / / 09/09/21 / / 0 0 JLB 0 0 0 0 / / / /
Averdi Storage@ John Joy ES:
- TQ Temporary Quarters 8-038-001 / / / / 09/09/21 / / 0 0 JLB 0 0 0 0 / / / /
Averdi Storage @ Gansevoort ES:
- TQ Temporary Quarters 8-039-001 / / / / 09/09/21 / / 0 0 JLB 0 0 0 0 / / / /
Stokes Elem. Modular:
22-0220XX Reconstruction 8-040-001 CANCELLED 08/03/22 / / 09/09/21 / / 0 0 WLC 0 0 0 0 / / / /
Gansevoort Elem. Modular:
22-0221XX Reconstruction 8-041-001 CANCELLED 08/03/22 / / 09/09/21 / / 0 0 WLC 0 0 0 0 / / / /
Bellamy Modular:
22-0222XX Reconstruction 8-042-001 CANCELLED 08/03/22 / / 09/09/21 / / 0 0 WLC 0 0 0 0 / / / /
Ridge Mills ES Modular:
22-0223XX Reconstruction 8-043-001 CANCELLED 08/03/22 / / 09/09/21 / / 0 0 WLC 0 0 0 0 / / / /
John Joy ES Modular:
22-0224XX Reconstruction 8-044-001 CANCELLED 08/03/22 / / 09/09/21 / / 0 0 WLC 0 0 0 0 / / / /
Denti Elementary Modular:
- XX Reconstruction 8-045-001 CANCELLED / / / / 11/18/21 / / 0 0 JLB 0 0 0 0 / / / /
Storage #1 @ John Joy ES:
- TQ Temporary Quarters 8-046-001 / / / / 03/21/22 / / 0 0 JLB 0 0 0 0 / / / /
Storage Unit #2 @ John Joy ES:
- TQ Temporary Quarters 8-047-001 / / / / 03/21/22 / / 0 0 JLB 0 0 0 0 / / / /
STorage Unit #3 @ John Joy ES:
- TQ Temporary Quarters 8-048-001 / / / / 03/21/22 / / 0 0 JLB 0 0 0 0 / / / /
Storage Unit #4 @ John Joy ES:
- TQ Temporary Quarters 8-049-001 / / / / 03/21/22 / / 0 0 JLB 0 0 0 0 / / / /
Bellamy Modular:
22-0225XX Reconstruction 8-051-001 CANCELLED 08/03/22 / / 07/19/22 / / 0 0 WLC 0 0 0 0 / / / /
Jerry Cough Elem Modular:
22-0226XX Reconstruction 8-052-001 CANCELLED 08/03/22 / / 07/19/22 / / 0 0 WLC 0 0 0 0 / / / /
West Dominick St District Offices:
23-1069TQ Temporary Quarters 8-054-001 01/18/24 DONE DONE DONE 11/29/23 11/29/23 09/22/23 / / 0 0 WLC 0 0 0 0 / / 11/29/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HOLLAND PATENT CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-22-01-06
last updated on 04/25/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Gen. Wm. Floyd Elementary:
19-1194 Reconstruction 0-001-015 05/22/20 DONE DONE DONE 01/10/20 01/07/20 06/12/19 05/17/16 2,9 1,124,084 1,124,084 JLB 0 0 0 King & King Architects 0 11/12/21 01/07/20
19-1441 Reconstruction 0-001-016 05/22/20 DONE DONE DONE 02/20/20 02/14/20 06/12/19 05/21/19 2,7,8,9,155,15,16 852,000 852,000 JLB 0 0 0 King & King Architects 0 09/03/21 02/14/20
19-1632 Reconstruction 0-001-017 05/29/20 DONE DONE DONE 03/25/20 03/03/20 06/12/19 05/21/19 2,9 100,000 100,000 JLB 0 0 0 King & King Architects 0 04/30/21 03/03/20
19-0586 Reconstruction 0-001-018 02/06/20 DONE DONE DONE 10/21/19 10/08/19 07/10/19 05/21/19 7,155,15,16 1,190,000 1,190,000 JLB 0 0 0 King & King Architects 0 08/18/21 10/08/19
- Reconstruction 0-001-019 / / / / 02/28/24 / / 2,7,9,10,155,15,16 0 0 JJH 0 0 0 0 / / / /
Middle School:
18-1837 Reconstruction 0-003-016 05/30/19 DONE DONE DONE 04/11/19 04/10/19 06/07/18 05/15/18 9 100,000 100,000 MTM 0 0 0 King & King Architects 0 02/21/20 04/10/19
19-1442 Reconstruction 0-003-017 05/22/20 DONE DONE DONE 02/20/20 02/14/20 06/12/19 05/21/19 2,7,8,9,155,15,16 1,300,000 1,300,000 JLB 0 0 0 King & King Architects 0 09/03/21 02/14/20
19-0587 Reconstruction 0-003-018 02/06/20 DONE DONE DONE 10/21/19 10/08/19 07/10/19 05/21/19 7,155,15,16 1,220,000 1,220,000 JLB 0 0 0 King & King Architects 0 08/18/21 10/08/19
23-1261 Reconstruction 0-003-019 UNREVIEWED 12/21/23 12/21/23 08/11/23 05/16/23 2,4,8,9,10,155,15,16 0 0 JJH 0 0 0 King & King Architects 0 / / 12/21/23
Garage and Shop:
19-1443 Reconstruction 0-004-011 05/22/20 DONE DONE DONE 02/20/20 02/14/20 06/12/19 05/21/19 2,4,16 60,500 0 JLB 0 0 0 King & King Architects 0 10/18/21 02/14/20
Holland Patent Elementary:
19-1444 Reconstruction 0-005-014 05/22/20 DONE DONE DONE 02/20/20 02/14/20 06/12/19 05/21/19 2,4,7,8,9,10,155,15, 899,000 899,000 JLB 0 0 0 King & King Architects 0 09/03/21 02/14/20
Senior High School:
18-1064 Reconstruction 0-008-018 04/26/19 DONE DONE DONE 12/14/18 12/10/18 06/21/18 05/20/14 8 500,000 500,000 JLB 0 0 0 King & King Architects 0 12/01/20 12/10/18
19-1445 Reconstruction 0-008-019 05/22/20 DONE DONE DONE 02/20/20 02/14/20 06/12/19 05/21/19 2,4,7,8,9,155,15,16 1,576,000 1,576,000 JLB 0 0 0 King & King Architects 0 09/03/21 02/14/20
19-0588 Reconstruction 0-008-020 02/06/20 DONE DONE DONE 10/21/19 10/08/19 07/10/19 05/21/19 7,155,15,16 2,077,500 2,077,500 JLB 0 0 0 King & King Architects 0 08/18/21 10/08/19
20-1348 Reconstruction 0-008-021 03/25/21 DONE DONE DONE 02/24/21 02/16/21 11/13/20 06/09/20 2,9 100,000 100,000 JLB 0 0 0 King & King Architects 0 10/07/21 02/16/21
21-1028 Reconstruction 0-008-022 03/01/22 DONE DONE DONE 01/03/22 01/03/22 10/29/21 05/18/21 2,9 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/22/23 01/03/22
23-1262 Reconstruction 0-008-023 UNREVIEWED 12/21/23 12/21/23 08/11/23 05/16/23 2,9,155,15,16 0 0 JJH 0 0 0 King & King Architects 0 / / 12/21/23
23-0647 Reconstruction 0-008-024 11/16/23 DONE DONE DONE 10/06/23 10/05/23 08/23/23 05/17/22 2,9 100,000 100,000 JJH 0 0 0 King & King Architects 0 / / 10/05/23
- Reconstruction 0-008-025 / / / / 02/28/24 / / 2,4,8,9,10,155,15,16 0 0 JJH 0 0 0 0 / / / /
Bus Garage:
19-1446 Reconstruction 5-006-011 05/22/20 DONE DONE DONE 02/20/20 02/14/20 06/12/19 05/21/19 2,4,8,9,155,15,16 664,000 664,000 JLB 0 0 0 King & King Architects 0 10/18/21 02/14/20
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
UTICA CITY SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-23-00-01
last updated on 04/25/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Proctor High School:
18-1772 Reconstruction 0-002-010 05/29/19 DONE DONE DONE 03/29/19 03/21/19 02/11/19 07/29/08 2,8,9,155,15,16 1,350,000 1,350,000 SLC 0 0 27,000 Stieglitz Snyder Architecture 0 09/12/22 03/21/19
19-1124 Reconstruction 0-002-011 04/08/20 DONE DONE DONE 01/02/20 12/20/19 12/06/19 07/29/08 4,7,8,9,155,15,16 3,120,000 3,120,000 SLC 0 0 62,400 Stieglitz Snyder Architecture 0 09/12/22 12/20/19
21-0156PR Additions and Alterations 0-002-012 UNREVIEWED 08/11/21 08/10/21 08/09/21 / / 02 - 16 0 118,118,276 SLC 0 0 0 0 / / 08/10/21
23-1074FA Additions and Alterations 0-002-012 03/18/24 DONE DONE DONE 11/30/23 10/02/23 08/09/21 12/07/21 02 - 16 21,995,000 6,157,062 MSK 0 0 0 LaBella Associates P.C. 0 / / 10/02/23
21-1180FC Reconstruction 0-002-013 02/18/22 DONE DONE DONE 01/21/22 01/21/22 11/24/21 11/16/21 9,155,15,16 11,100,000 0 SLC 0 0 0 Stieglitz Snyder Architecture 0 02/06/24 01/21/22
Albany Street School:
21-1181FC Reconstruction 0-003-008 02/18/22 DONE DONE DONE 01/21/22 01/21/22 11/24/21 11/16/21 9,155,15,16 2,040,000 0 SLC 0 0 0 Stieglitz Snyder Architecture 0 02/06/24 01/21/22
- Reconstruction 0-003-009 / / / / 04/05/24 / / 2,8,9,155,15,16 0 0 MSK 0 0 0 0 / / / /
Chris Columbus School:
19-1153 Reconstruction 0-007-011 03/30/20 DONE DONE DONE 01/03/20 12/12/19 12/06/19 07/29/08 2,4,8,9,155,15,16 2,400,000 2,400,000 SLC 0 0 48,000 Stieglitz Snyder Architecture 0 09/12/22 12/12/19
23-0965XX Reconstruction 0-007-012 01/22/24 CANCELLED 11/13/23 10/02/23 09/26/23 08/22/23 4,8,9 2,033,000 0 MSK 0 0 0 LaBella Associates 0 / / 10/02/23
- Reconstruction 0-007-013 / / / / 03/14/24 / / 2,155,16 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-007-014 / / / / 04/05/24 / / 2,8,9,155,15,16 0 0 MSK 0 0 0 0 / / / /
Roscoe Conkling School:
- Reconstruction 0-008-008 / / / / 03/14/24 / / 2,155,16 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-008-009 / / / / 04/05/24 / / 2,8,9,155,15,16 0 0 MSK 0 0 0 0 / / / /
John F Hughes School:
23-0971FA Reconstruction 0-009-009 01/17/24 DONE DONE DONE 11/13/23 10/02/23 09/25/23 08/22/23 2 540,000 0 MSK 0 0 0 LaBella Associates 0 / / 10/02/23
- Reconstruction 0-009-010 / / / / 04/05/24 / / 2,8,9,155,15,16 0 0 MSK 0 0 0 0 / / / /
Thomas Jefferson School:
23-0972FA Reconstruction 0-010-009 01/17/24 DONE DONE DONE 11/13/23 10/02/23 09/25/23 08/22/23 2 540,000 0 MSK 0 0 0 LaBella Associates 0 / / 10/02/23
- Reconstruction 0-010-010 / / / / 03/14/24 / / 2,155,16 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-010-011 / / / / 04/05/24 / / 2,8,9,155,15,16 0 0 MSK 0 0 0 0 / / / /
Hugh R. Jones School:
19-1122XX Reconstruction 0-011-010 04/06/20 CANCELLED 01/02/20 12/20/19 12/06/19 07/29/08 9,155,16 360,000 360,000 SLC 0 0 7,200 Stieglitz Snyder Architecture 0 / / 12/20/19
21-1182FC Reconstruction 0-011-011 02/18/22 DONE DONE DONE 01/21/22 01/21/22 11/24/21 11/16/21 8,9,155,15,16 3,240,000 0 SLC 0 0 0 Stieglitz Snyder Architecture 0 02/06/24 01/21/22
23-0973FA Reconstruction 0-011-012 01/17/24 DONE DONE DONE 11/13/23 10/02/23 09/25/23 08/22/23 2 450,000 0 MSK 0 0 0 LaBella Associates 0 / / 10/02/23
- Reconstruction 0-011-013 / / / / 04/05/24 / / 2,8,9,155,15,16 0 0 MSK 0 0 0 0 / / / /
Kernan School:
23-1039 Reconstruction 0-013-013 UNREVIEWED 11/17/23 10/02/23 09/25/23 07/25/23 2 300,000 0 MSK 0 0 0 LaBella Associates 0 / / 10/02/23
- Reconstruction 0-013-014 / / / / 04/05/24 / / 2,8,9,155,15,16 0 0 MSK 0 0 0 0 / / / /
Watson Williams - New K-6:
- Reconstruction 0-015-010 / / / / 03/14/24 / / 2,155,16 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-015-011 / / / / 04/05/24 / / 2,8,9,155,15,16 0 0 MSK 0 0 0 0 / / / /
M. L. King School:
- Reconstruction 0-016-010 / / / / 04/05/24 / / 2,8,9,155,15,16 0 0 MSK 0 0 0 0 / / / /
John F Kennedy Junior H.S.:
18-1394 Reconstruction 0-026-011 05/31/19 DONE DONE DONE 02/06/19 01/25/19 12/20/18 08/14/18 2,10 2,560,000 2,560,000 SLC 0 0 0 Stieglitz Snyder Architecture 0 12/15/21 01/25/19
23-0974FA Reconstruction 0-026-012 01/17/24 DONE DONE DONE 11/13/23 10/02/23 09/25/23 08/22/23 2 270,000 0 MSK 0 0 0 LaBella Associates 0 / / 10/02/23
- PR Additions and Alterations 0-026-013 / / / / 04/04/24 / / 02 - 16 0 0 MSK 0 0 0 0 / / / /
Donovan Middle School:
23-0966FA Reconstruction 0-031-009 01/22/24 DONE DONE DONE 11/13/23 10/02/23 02/11/19 07/25/23 4,7 1,765,000 0 MSK 0 0 0 LaBella Associates 0 / / 10/02/23
23-0967FA Reconstruction 0-031-010 12/14/23 DONE DONE DONE 11/13/23 10/02/23 09/25/23 08/22/23 155,16 1,500,000 0 MSK 0 0 0 LaBella Associates 0 / / 10/02/23
- PR Additions and Alterations 0-031-011 / / / / 09/25/23 / / 02 - 16 0 0 MSK 0 0 0 0 / / / /
23-0968FA Additions and Alterations 0-031-011 01/12/24 DONE DONE DONE 11/13/23 10/02/23 09/25/23 08/22/23 02 - 16 375,000 0 MSK 0 0 0 LaBella Associates 0 / / 10/02/23
- PR Additions and Alterations 0-031-012 / / / / 04/04/24 / / 02 - 16 0 0 MSK 0 0 0 0 / / / /
:
- XX New Construction 1-047-001 CANCELLED / / / / 05/16/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
- XX New Construction 1-049-001 CANCELLED / / / / 05/16/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
Proctor Field Storage Building:
- PR New Construction 2-046-001 DONE / / / / 05/16/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
19-0834 New Construction 2-046-001 04/10/20 DONE DONE DONE 11/19/19 11/07/19 05/16/19 08/14/18 02 - 16 250,000 0 SLC 0 0 0 Stieglitz Snyder Architecture 0 06/14/22 11/07/19
School Shop:
- Reconstruction 3-024-004 / / / / 08/27/19 / / 2,7 0 0 SLC 0 0 0 0 / / / /
JFK Field Building:
23-0969FA Reconstruction 7-006-001 01/08/24 DONE DONE DONE 11/13/23 10/02/23 09/25/23 08/22/23 4,7,8,9 237,500 0 MSK 0 0 0 LaBella Associates 0 / / 10/02/23
Proctor Stadium Press Box:
18-2129DB Discovered Building 7-045-001 07/09/19 DONE DONE DONE 06/14/19 06/13/19 03/22/19 / / 0 0 SLC 0 0 0 0 / / 06/13/19
Donovan Fields Support Building:
19-0832 New Construction 7-047-001 04/10/20 DONE DONE DONE 11/19/19 11/07/19 05/16/19 08/14/18 02 - 16 500,000 0 SLC 0 0 0 Stieglitz Snyder Architecture 0 12/15/21 11/07/19
Proctor Stadium Concession Building:
- PR New Construction 7-048-001 DONE / / / / 05/16/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
19-0835 New Construction 7-048-001 04/10/20 DONE DONE DONE 11/19/19 11/07/19 05/16/19 08/14/18 02 - 16 500,000 0 SLC 0 0 0 Stieglitz Snyder Architecture 0 / / 11/07/19
Proctor Stadium Support Building:
19-0833 New Construction 7-049-001 04/10/20 DONE DONE DONE 11/19/19 11/07/19 05/16/19 08/14/18 02 - 16 3,120,000 0 SLC 0 0 0 Stieglitz Snyder Architecture 0 06/14/22 11/07/19
District-Wide:
23-0970FA Reconstruction 7-999-006 01/31/24 DONE DONE DONE 11/13/23 10/02/23 09/25/23 08/30/23 16 2,215,000 0 MSK 0 0 0 LaBella Associates 0 / / 10/02/23
Utica Academy of Science HS&ES:
15-0393TQ Temporary Quarters 8-002-001 09/17/19 DONE DONE DONE 09/01/15 08/27/15 05/01/15 / / 0 0 JMB 0 0 0 0 09/20/19 08/27/15
18-1834TQ Temporary Quarters 8-002-002 10/01/19 DONE DONE DONE 04/10/19 04/10/19 04/08/19 / / 0 0 SLC 0 0 0 0 / / 04/10/19
19-1422TQ Temporary Quarters 8-002-003 10/26/20 DONE DONE DONE 02/19/20 02/18/20 01/14/20 / / 0 0 SLC 0 0 0 0 / / 02/18/20
20-1257 Reconstruction 8-002-004 08/12/21 DONE DONE DONE 02/08/21 01/12/21 11/24/20 11/10/20 2,4,7,8,9,155,15,16 3,310,000 0 SLC 0 0 0 Lake Architectural 0 08/20/21 01/12/21
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
WESTMORELAND CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-28-01-04
last updated on 04/25/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Westmoreland Jr/Sr High School:
18-1975 Reconstruction 0-001-017 09/26/19 DONE DONE DONE 05/16/19 05/14/19 09/13/17 11/13/18 2,4,7,8,9,10,13,14,1 5,469,550 5,469,550 BMJ 0 0 0 March Associates 0 06/01/21 05/14/19
23-1640 Reconstruction 0-001-018 UNREVIEWED 03/15/24 03/15/24 02/27/24 02/13/24 7 0 0 JJH 0 0 0 March Associates 0 / / 03/15/24
- Reconstruction 0-001-019 / / / / 02/27/24 / / 2,8,155,15,16 0 0 JJH 0 0 0 0 / / / /
Elementary School:
18-1976 Reconstruction 0-003-012 09/26/19 DONE DONE DONE 05/16/19 05/14/19 09/13/17 11/13/18 2,4,7,8,9,10,155,15, 593,000 593,000 BMJ 0 0 0 March Associates 0 06/01/21 05/14/19
23-0307 Reconstruction 0-003-013 09/25/23 DONE DONE DONE 08/23/23 08/23/23 06/07/23 05/16/23 9,16 100,000 0 JJH 0 0 0 March Associates 0 / / 08/23/23
- Reconstruction 0-003-014 / / / / 02/27/24 / / 2,8,9,10,155,15,16 0 0 JJH 0 0 0 0 / / / /
Middle Sch (Upper Elem):
18-1977 Reconstruction 0-012-005 09/26/19 DONE DONE DONE 05/16/19 05/14/19 09/13/17 11/13/18 9,155,16 322,000 322,000 BMJ 0 0 0 March Associates 0 06/01/21 05/14/19
20-0119 Reconstruction 0-012-006 09/02/20 DONE DONE DONE 07/24/20 07/20/20 10/15/19 05/21/19 4,8,9,16 100,000 0 JLB 0 0 0 March Associates 0 06/01/21 07/20/20
20-1203 Reconstruction 0-012-007 06/01/21 DONE DONE DONE 01/27/21 01/22/21 12/11/20 05/18/21 2,4,7,8,9,10,13,14,1 100,000 100,000 JSS 0 0 0 March Associates 0 06/15/22 01/22/21
22-1503 Reconstruction 0-012-008 03/06/23 DONE DONE DONE 01/18/23 01/17/23 11/15/22 05/17/22 8 100,000 100,000 JJH 0 0 0 March Associates 0 / / 01/17/23
- Reconstruction 0-012-009 / / / / 02/27/24 / / 2,7,8,9,155,15,16 0 0 JJH 0 0 0 0 / / / /
Bus Garage:
18-1978 Additions and Alterations 5-004-007 09/26/19 DONE DONE DONE 05/16/19 05/14/19 09/13/17 11/13/18 02 - 16 1,051,000 1,051,000 BMJ 0 0 0 March Associates 0 06/01/21 05/14/19
District-Wide:
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 JLB 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
WHITESBORO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 41-29-02-06
last updated on 04/25/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Parkway School:
20-0837 Reconstruction 0-001-018 04/14/21 DONE DONE DONE 11/18/20 11/02/20 07/05/19 05/21/19 2,4,7,8,9,10,155,15, 2,361,175 2,361,175 SLC 0 0 0 March Associates 0 12/19/22 11/02/20
21-1220 Reconstruction 0-001-019 06/22/22 DONE DONE DONE 02/02/22 02/02/22 12/02/21 05/21/19 2,4,7,8,9,10,155,15, 600,840 600,840 SLC 0 0 0 March Associates 0 09/11/23 02/02/22
21-2032FC Reconstruction 0-001-020 09/26/22 DONE DONE DONE 06/24/22 06/08/22 02/14/22 01/06/21 2,8,16 65,322 0 SLC 0 0 0 March Associates 0 / / 06/08/22
23-0931 Reconstruction 0-001-021 UNREVIEWED 11/10/23 11/07/23 07/28/23 02/14/23 155,15,16 0 0 MSK 0 0 0 March Associates 0 / / 11/07/23
- Reconstruction 0-001-022 / / / / 08/10/23 / / 2,7,8,9,10,155,15,16 0 0 MSK 0 0 0 0 / / / /
Whitesboro Middle School:
18-2030 Reconstruction 0-002-019 10/15/19 DONE DONE DONE 05/31/19 05/24/19 11/30/18 12/15/14 2,8,9,10,14,155,16 705,000 705,000 SLC 0 0 0 March Associates 0 01/18/21 05/24/19
20-0838 Reconstruction 0-002-020 04/14/21 DONE DONE DONE 11/18/20 11/02/20 07/05/19 05/21/19 2,4,7,8,9,10,155,15, 3,681,675 3,681,675 SLC 0 0 0 March Associates 0 12/19/22 11/02/20
20-0259 Reconstruction 0-002-021 10/16/20 DONE DONE DONE 08/24/20 08/13/20 11/25/19 05/21/19 4,9 100,000 100,000 SLC 0 0 0 March Associates 0 05/03/21 08/13/20
21-2033FC Reconstruction 0-002-022 09/26/22 DONE DONE DONE 06/24/22 06/08/22 02/14/22 01/06/21 2,8,16 185,079 0 SLC 0 0 0 March Associates 0 / / 06/08/22
22-1190FC Reconstruction 0-002-023 04/03/23 DONE DONE DONE 12/09/22 11/22/22 05/02/22 09/13/22 7,9,155,16 190,000 190,000 JLB 0 0 0 March Associates 0 / / 11/22/22
23-0932 Reconstruction 0-002-024 UNREVIEWED 11/10/23 11/07/23 07/28/23 02/14/23 7,155,15,16 0 0 MSK 0 0 0 March Associates 0 / / 11/07/23
- Reconstruction 0-002-025 / / / / 08/10/23 / / 2,4,7,8,9,10,155,15, 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-002-026 / / / / 04/15/24 / / 2,9 0 0 MSK 0 0 0 0 / / / /
Harts Hill Elementary:
19-0920 Reconstruction 0-004-021 06/24/20 DONE DONE DONE 12/05/19 11/25/19 07/05/19 05/21/19 2,4,7,8,9,10,155,15, 1,518,750 1,518,750 SLC 0 0 0 March Associates 0 10/15/21 11/25/19
21-0208 Reconstruction 0-004-022 11/08/21 DONE DONE DONE 08/23/21 08/19/21 02/08/21 06/09/20 2,4,7,9,10 100,000 0 SLC 0 0 0 March Associates 0 / / 08/19/21
21-2034FC Reconstruction 0-004-023 09/26/22 DONE DONE DONE 06/24/22 06/08/22 02/14/22 01/06/21 2,8,16 130,645 0 SLC 0 0 0 March Associates 0 / / 06/08/22
22-1191FC Reconstruction 0-004-024 04/03/23 DONE DONE DONE 12/09/22 11/22/22 05/02/22 09/13/22 7,9,155,16 170,000 170,000 JLB 0 0 0 March Associates 0 / / 11/22/22
23-0933 Reconstruction 0-004-025 UNREVIEWED 11/10/23 11/07/23 07/28/23 02/14/23 7,155,15,16 0 0 MSK 0 0 0 March Associates 0 / / 11/07/23
- Reconstruction 0-004-026 / / / / 08/10/23 / / 2,4,7,8,9,10,155,15, 0 0 MSK 0 0 0 0 / / / /
Marcy Elementary School:
19-0921 Reconstruction 0-006-020 06/24/20 DONE DONE DONE 12/05/19 11/25/19 07/05/19 05/21/19 2,4,7,8,9,10,155,15, 1,815,750 1,815,750 SLC 0 0 0 March Associates 0 10/15/21 11/25/19
21-2035FC Reconstruction 0-006-021 09/26/22 DONE DONE DONE 06/24/22 06/08/22 02/14/22 01/06/21 2,8,16 141,531 0 SLC 0 0 0 March Associates 0 / / 06/08/22
22-1192FC Reconstruction 0-006-022 04/03/23 DONE DONE DONE 12/09/22 11/22/22 05/02/22 09/13/22 7,9,155,16 170,000 170,000 JLB 0 0 0 March Associates 0 / / 11/22/22
23-0934 Reconstruction 0-006-023 UNREVIEWED 11/10/23 11/07/23 07/28/23 02/14/23 7,155,15,16 0 0 MSK 0 0 0 March Associates 0 / / 11/07/23
- Reconstruction 0-006-024 / / / / 08/10/23 / / 2,4,7,8,9,10,155,15, 0 0 MSK 0 0 0 0 / / / /
Deerfield Elementary:
19-0922 Reconstruction 0-009-018 06/24/20 DONE DONE DONE 12/05/19 11/25/19 07/05/19 05/21/19 2,4,7,8,9,10,14,155, 1,402,650 1,402,650 SLC 0 0 0 March Associates 0 10/15/21 11/25/19
21-2036FC Reconstruction 0-009-019 09/26/22 DONE DONE DONE 06/24/22 06/08/22 02/14/22 01/06/21 8,16 130,645 0 SLC 0 0 0 March Associates 0 / / 06/08/22
22-1193FC Reconstruction 0-009-020 04/03/23 DONE DONE DONE 12/09/22 11/22/22 05/02/22 09/13/22 7,9,155,16 170,000 170,000 JLB 0 0 0 March Associates 0 / / 11/22/22
23-0935 Reconstruction 0-009-021 UNREVIEWED 11/10/23 11/07/23 07/28/23 02/14/23 7,155,15,16 0 0 MSK 0 0 0 March Associates 0 / / 11/07/23
- Reconstruction 0-009-022 / / / / 08/10/23 / / 2,4,7,8,9,10,155,15, 0 0 MSK 0 0 0 0 / / / /
Westmoreland Rd Elementary:
19-0923 Reconstruction 0-010-017 06/24/20 DONE DONE DONE 12/05/19 11/25/19 07/05/19 05/21/19 2,4,7,8,9,10,14,155, 877,500 877,500 SLC 0 0 0 March Associates 0 10/15/21 11/25/19
21-2037FC Reconstruction 0-010-018 09/26/22 DONE DONE DONE 06/24/22 06/08/22 02/14/22 01/06/21 8,16 141,531 0 SLC 0 0 0 March Associates 0 / / 06/08/22
22-1194FC Reconstruction 0-010-019 04/03/23 DONE DONE DONE 12/09/22 11/22/22 05/02/22 09/13/22 7,9,155,16 255,000 255,000 JLB 0 0 0 March Associates 0 / / 11/22/22
23-0936 Reconstruction 0-010-020 UNREVIEWED 11/10/23 11/07/23 07/28/23 02/14/23 7,155,15,16 0 0 MSK 0 0 0 March Associates 0 / / 11/07/23
- Reconstruction 0-010-021 / / / / 08/10/23 / / 2,4,7,8,9,10,155,15, 0 0 MSK 0 0 0 0 / / / /
- Reconstruction 0-010-022 / / / / 04/15/24 / / 2,8,9 0 0 MSK 0 0 0 0 / / / /
Senior High School:
18-2031 Reconstruction 0-012-031 10/15/19 DONE DONE DONE 05/31/19 05/24/19 11/30/18 12/15/14 2,7,8,9,155,16 1,784,000 1,784,000 SLC 0 0 0 March Associates 0 01/16/21 05/24/19
20-0839 Reconstruction 0-012-032 04/14/21 DONE DONE DONE 11/18/20 11/02/20 07/05/19 05/21/19 2,4,7,8,9,10,155,15, 5,338,825 5,338,825 SLC 0 0 0 March Associates 0 12/19/22 11/02/20
21-1221 Reconstruction 0-012-033 06/22/22 DONE DONE DONE 02/02/22 02/02/22 12/02/21 05/21/19 2,8,9 534,880 534,880 SLC 0 0 0 March Associates 0 09/11/23 02/02/22
21-2038FC Reconstruction 0-012-034 09/26/22 DONE DONE DONE 06/24/22 06/08/22 02/14/22 01/06/21 8,16 293,951 0 SLC 0 0 0 March Associates 0 / / 06/08/22
22-1195FC Reconstruction 0-012-035 04/03/23 DONE DONE DONE 12/09/22 11/22/22 05/02/22 09/13/22 7,9,155,16 625,000 625,000 JLB 0 0 0 March Associates 0 / / 11/22/22
22-0625 Reconstruction 0-012-036 01/16/23 DONE DONE DONE 10/03/22 10/03/22 05/02/22 05/18/21 8,9,16 100,000 100,000 SLC 0 0 0 March Associates 0 / / 10/03/22
22-1453 Reconstruction 0-012-037 03/09/23 DONE DONE DONE 01/09/23 01/09/23 05/16/22 05/17/22 8,9 100,000 100,000 JLB 0 0 0 March Associates 0 / / 01/09/23
23-0937 Reconstruction 0-012-038 UNREVIEWED 11/10/23 11/07/23 07/28/23 02/14/23 7,155,15,16 0 0 MSK 0 0 0 March Associates 0 / / 11/07/23
- Reconstruction 0-012-039 / / / / 08/10/23 / / 2,4,7,8,9,10,155,15, 0 0 MSK 0 0 0 0 / / / /
Storage Building:
22-1697DB Discovered Building 2-021-001 05/24/23 DONE DONE DONE 02/17/23 02/14/23 10/15/20 / / 0 0 JLB 0 0 0 March Associates 0 / / 02/14/23
Maintenance Garage:
20-0840 Reconstruction 3-005-005 04/14/21 DONE DONE DONE 11/18/20 11/02/20 07/05/19 05/21/19 4,8,16 371,000 0 SLC 0 0 0 March Associates 0 12/19/22 11/02/20
23-0938 Reconstruction 3-005-006 UNREVIEWED 11/10/23 11/07/23 07/28/23 02/14/23 155,16 0 0 MSK 0 0 0 March Associates 0 / / 11/07/23
- Reconstruction 3-005-007 / / / / 08/10/23 / / 7,9,16 0 0 MSK 0 0 0 0 / / / /
Transporation (Bus) Garage:
20-0841 Reconstruction 5-008-010 04/14/21 DONE DONE DONE 11/18/20 11/02/20 07/05/19 05/21/19 2,8,155,15,16 2,008,675 2,008,675 SLC 0 0 0 March Associates 0 12/19/22 11/02/20
23-0939 Reconstruction 5-008-011 UNREVIEWED 11/10/23 11/07/23 07/28/23 02/14/23 155,16 0 0 MSK 0 0 0 March Associates 0 / / 11/07/23
- Reconstruction 5-008-012 / / / / 08/10/23 / / 7,9,155,16 0 0 MSK 0 0 0 0 / / / /
Concession Stand/Middle School:
20-0842 Reconstruction 7-015-004 04/14/21 DONE DONE DONE 11/18/20 11/02/20 07/05/19 05/21/19 2,9,15,16 52,000 0 SLC 0 0 0 March Associates 0 12/19/22 11/02/20
23-0940 Reconstruction 7-015-005 UNREVIEWED 11/10/23 11/07/23 07/28/23 02/14/23 155,16 0 0 MSK 0 0 0 March Associates 0 / / 11/07/23
- Reconstruction 7-015-006 / / / / 08/10/23 / / 4,7,9,16 0 0 MSK 0 0 0 0 / / / /
HS Concession/Toilet/StorageShed:
20-0843 Reconstruction 7-016-002 04/14/21 DONE DONE DONE 11/18/20 11/02/20 07/05/19 05/21/19 2,4,7,8,9,10,155,15, 556,000 0 SLC 0 0 0 March Associates 0 12/19/22 11/02/20
Grandstand/Press Box:
20-0844 Reconstruction 7-018-002 04/14/21 DONE DONE DONE 11/18/20 11/02/20 09/03/20 05/21/19 7,8,9,16 16,000 0 SLC 0 0 0 March Associates 0 12/19/22 11/02/20
District-Wide:
18-1919 Reconstruction 7-999-002 07/25/19 DONE DONE DONE 05/02/19 05/01/19 08/11/17 11/04/14 2,9,155,16 2,114,307 0 SLC 0 0 0 March Associates 0 / / 05/01/19
XXLocker Rooms 1 Const Swing Space:
- XX New Construction 8-022-001 CANCELLED / / / / 05/17/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
XXLocker Rooms 2 Const Swing Space:
- XX New Construction 8-023-001 CANCELLED / / / / 05/17/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
XXLocker Rooms 3 Const Swing Space:
- XX New Construction 8-024-001 CANCELLED / / / / 05/17/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
XXLocker Rooms 4 Const Swing Space:
- XX New Construction 8-025-001 CANCELLED / / / / 05/17/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED