ALBION CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 45-01-01-06
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Bergerson Middle School:
21-0171 Reconstruction 0-001-012 10/22/21 DONE DONE DONE 08/16/21 08/11/21 05/28/21 05/18/21 14,16 100,000 100,000 JLB 0 0 0 ning & King Architects 0 06/17/22 08/11/21
22-0405 Reconstruction 0-001-013 12/13/22 DONE DONE DONE 09/07/22 09/06/22 02/28/22 12/14/21 2,4,8,9,10,14,155,15 8,671,030 8,671,030 JLB 0 0 0 ning & King Architects 0 / / 09/06/22
Ronald D. Sodoma Primary School:
22-0406 Reconstruction 0-002-016 12/13/22 DONE DONE DONE 09/07/22 09/06/22 02/28/22 12/14/21 2,8,9,10,155,15,16 6,710,397 6,710,397 JLB 0 0 0 ning & King Architects 0 / / 09/06/22
22-1270 Reconstruction 0-002-017 02/23/23 DONE DONE DONE 12/19/22 12/16/22 10/13/22 05/17/22 14,16 100,000 100,000 JJH 0 0 0 ning & King Architects 0 / / 12/16/22
Charles D. Amico High School:
22-0407 Reconstruction 0-004-009 12/13/22 DONE DONE DONE 09/07/22 09/06/22 02/28/22 12/14/21 2,4,8,9,10,155,15,16 10,400,155 10,400,155 JLB 0 0 0 ning & King Architects 0 / / 09/06/22
Bus Garage:
22-0408 Reconstruction 5-003-010 12/13/22 DONE DONE DONE 09/07/22 09/06/22 02/28/22 12/14/21 2,7,8,9,10,16 908,418 908,418 JLB 0 0 0 ning & King Architects 0 / / 09/06/22
- Reconstruction 5-003-011 / / / / 03/27/24 / / 8 0 0 JJH 0 0 0 0 / / / /
Districtwide:
21-1551SB Reconstruction 7-999-001 DONE / / / / 03/24/22 / / 16 0 0 JLB 0 0 0 0 / / / /
22-1486 Reconstruction 7-999-001 05/19/23 DONE DONE DONE 01/13/23 01/12/23 03/24/22 05/09/22 16 1,801,172 0 JJH 0 0 0 ning & King Architects 0 / / 01/12/23
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 JLB 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
KENDALL CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 45-06-07-04
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Kendall Elementary:
18-1259 Reconstruction 0-001-009 08/23/19 DONE DONE DONE 01/15/19 12/26/18 03/01/18 05/15/18 2,4,8,9,10,155,15,16 5,264,709 5,264,709 SLC 0 0 0 SWBR Architects P.C. 0 11/06/20 12/26/18
- Reconstruction 0-001-010 / / / / 03/01/24 / / 2,4,8,9,155,16 0 0 WLC 0 0 0 0 / / / /
Jr/Sr High School:
18-1260 Reconstruction 0-004-009 08/23/19 DONE DONE DONE 01/15/19 12/26/18 03/01/18 05/15/18 2,4,7,9,10,14,155,15 7,664,839 7,664,839 SLC 0 0 0 SWBR Architects P.C. 0 11/06/20 12/26/18
- Reconstruction 0-004-010 / / / / 03/01/24 / / 9,155,16 0 0 WLC 0 0 0 0 / / / /
Buildings & Grounds Shop:
18-1261 Reconstruction 2-002-003 08/23/19 DONE DONE DONE 01/15/19 12/26/18 03/01/18 05/15/18 2,8 137,800 0 SLC 0 0 0 SWBR Architects P.C. 0 / / 12/26/18
- Reconstruction 2-002-004 / / / / 03/01/24 / / 7,13,155,16 0 0 WLC 0 0 0 0 / / / /
XXKendall Storage Building-cancelled:
18-1262 New Construction 2-011-001 08/23/19 DONE DONE DONE 01/15/19 12/26/18 11/01/18 05/15/18 02 - 16 80,688 0 SLC 0 0 0 SWBR Architects P.C. 0 / / 12/26/18
XXAthletic Track/StorageBldg-See7013:
- XX Reconstruction 2-015-001 12/02/20 CANCELLED 10/02/20 10/01/20 05/28/20 / / 0 0 SLC 0 0 0 0 / / 10/01/20
Bus Garage (SubstantialComp2003):
18-1263 Reconstruction 5-005-005 08/23/19 DONE DONE DONE 01/15/19 12/26/18 03/01/18 05/15/18 7,155,15,16 753,016 753,016 SLC 0 0 0 SWBR Architects P.C. 0 11/06/20 12/26/18
- Reconstruction 5-005-006 / / / / 03/01/24 / / 9,13,16 0 0 WLC 0 0 0 0 / / / /
Athletic Track Storage Bldg:
20-0509DB Discovered Building 7-009-001 12/02/20 DONE DONE DONE 10/02/20 10/01/20 03/27/13 / / 02 - 16 0 0 SLC 0 0 0 0 / / 10/01/20
Field Toilet Facility (2019):
18-1264 New Construction 7-010-001 08/23/19 DONE DONE DONE 01/15/19 12/26/18 03/01/18 05/15/18 02 - 16 225,088 0 SLC 0 0 0 SWBR Architects P.C. 0 12/07/20 12/26/18
Kendall Press Box:
19-0603 New Construction 7-012-001 11/14/19 DONE DONE DONE 10/23/19 10/22/19 10/03/19 05/15/18 02 - 16 80,000 0 SLC 0 0 0 SWBR Architects P.C. 0 10/23/20 10/22/19
Concession Bldg/Storage:
20-0508DB Discovered Building 7-013-001 12/02/20 DONE DONE DONE 10/02/20 10/01/20 05/28/20 / / 0 0 SLC 0 0 0 0 / / 10/01/20
XXAnnouncers Booth (Demolished):
- DB Discovered Building 7-014-001 / / / / 05/28/20 / / 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HOLLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 45-07-04-04
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Elementary School:
19-0989 Reconstruction 0-002-011 02/04/20 DONE DONE DONE 12/13/19 11/27/19 10/10/19 05/21/19 2,7,8,9 100,000 100,000 BMJ 0 0 0 LaBella Associates P.C. 0 09/14/20 11/27/19
21-1408 Reconstruction 0-002-012 07/22/22 DONE DONE DONE 03/01/22 02/25/22 05/18/21 11/04/14 16 50,000 50,000 FMJ 0 0 0 LaBella Associates P.C. 0 / / 02/25/22
- PR Additions and Alterations 0-002-013 / / / / 02/08/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / / /
23-0278 Additions and Alterations 0-002-013 02/16/24 DONE DONE DONE 08/18/23 08/16/23 02/08/23 12/13/22 02 - 16 9,941,072 9,195,379 WLC 0 0 0 LaBella Associates P.C. 0 / / 08/16/23
- PR Reconstruction 0-002-BA1 DONE / / / / / / / / 16 0 32,778,153 JSS 0 0 0 0 / / / /
Jr-Sr High School:
21-1409 Reconstruction 0-008-009 07/22/22 DONE DONE DONE 03/01/22 02/25/22 05/13/21 11/04/14 50,000 50,000 FMJ 0 0 0 LaBella Associates P.C. 0 / / 02/25/22
21-0253 Reconstruction 0-008-010 02/07/22 DONE DONE DONE 08/30/21 08/30/21 05/24/21 05/18/21 2,8,9,10,16 100,000 100,000 SLC 0 0 0 LaBella Associates P.C. 0 06/23/23 08/30/21
23-0279 Reconstruction 0-008-011 02/16/24 DONE DONE DONE 08/18/23 08/16/23 02/08/23 12/13/22 2,4,7,8,9,10,155,15, 6,399,117 6,399,117 WLC 0 0 0 LaBella Associates P.C. 0 / / 08/16/23
23-1152 Reconstruction 0-008-012 01/22/24 DONE DONE DONE 12/08/23 12/07/23 11/07/23 05/16/23 2,4,8,9,16 100,000 100,000 JLB 0 0 0 LaBella Associates P.C. 0 / / 12/07/23
- SB Reconstruction 0-008-BA1 DONE / / / / / / / / 16 0 0 JSS 0 0 0 0 / / / /
Storage Building:
23-0280 Reconstruction 2-020-002 02/16/24 DONE DONE DONE 08/18/23 08/16/23 06/22/23 12/13/22 8,9,155,15,16 47,945 0 WLC 0 0 0 LaBella Associates P.C. 0 / / 08/16/23
23-0281 New Construction 2-023-001 02/16/24 DONE DONE DONE 08/18/23 08/16/23 02/08/23 12/13/22 02 - 16 381,736 0 WLC 0 0 0 LaBella Associates P.C. 0 / / 08/16/23
Bus Garage-Bldgs&GroundsStor.NoBldgA:
23-0282 Reconstruction 5-001-004 02/16/24 DONE DONE DONE 08/18/23 08/16/23 02/08/23 12/13/22 2,4,7,8 226,057 226,057 WLC 0 0 0 LaBella Associates P.C. 0 / / 08/16/23
Bus Garage:
23-0283 Reconstruction 5-019-002 02/16/24 DONE DONE DONE 08/18/23 08/16/23 02/08/23 12/13/22 2,4,8,155,15,16 890,760 890,760 WLC 0 0 0 LaBella Associates P.C. 0 / / 08/16/23
Concession Stand:
23-0284 Reconstruction 7-007-002 02/16/24 DONE DONE DONE 08/18/23 08/16/23 02/08/23 12/13/22 2,4,7,8,9,10,155,15, 213,312 0 WLC 0 0 0 LaBella Associates P.C. 0 / / 08/16/23
District-Wide:
19-0160 Reconstruction 7-999-001 09/13/19 DONE DONE DONE 07/25/19 07/23/19 12/18/17 11/20/17 16 270,000 270,000 BMJ 0 0 0 SEI Design Group 0 04/20/20 07/23/19
- Reconstruction 7-999-002 / / / / 09/30/20 / / 16 0 0 JSS 0 0 0 0 / / / /
Holley Sports Boosters Club Inc:
- TQ Temporary Quarters 8-022-001 / / / / 12/14/21 / / 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
MEDINA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 45-08-01-06
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Oak Orchard Elementary School:
23-0335 Reconstruction 0-002-011 STARTED ADD. REQ'D DONE 08/28/23 08/28/23 04/04/23 02/14/23 2,4,7,8,9,10,155,15, 6,048,987 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 08/28/23
Clifford H. Wise MS:
22-2101 Reconstruction 0-003-011 08/18/23 DONE DONE DONE 04/26/23 04/26/23 03/15/23 02/14/23 155,15,16 567,300 567,300 WLC 0 0 0 Gordon W. Jones Associates 0 / / 04/26/23
23-0336 Reconstruction 0-003-012 STARTED ADD. REQ'D DONE 08/28/23 08/28/23 04/04/23 02/14/23 2,4,7,8,9,10,155,15, 7,648,804 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 08/28/23
Medina High School:
22-2203PR Additions and Alterations 0-006-011 UNREVIEWED 05/12/23 05/11/23 04/04/23 / / 02 - 16 0 0 WLC 0 0 0 0 / / 05/11/23
23-0337 Additions and Alterations 0-006-011 STARTED ADD. REQ'D DONE 08/28/23 08/28/23 04/04/23 02/14/23 02 - 16 17,810,147 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 08/28/23
Bus Garage:
23-0338 Reconstruction 5-005-007 STARTED ADD. REQ'D DONE 08/28/23 08/28/23 04/04/23 02/14/23 7,15 1,480,565 0 WLC 0 0 0 Gordon W. Jones Associates 0 / / 08/28/23
Greenhouse:
23-0339 New Construction 7-017-001 STARTED ADD. REQ'D DONE 08/28/23 08/28/23 04/04/23 02/14/23 02 - 16 801,474 145,590 WLC 0 0 0 Gordon W. Jones Associates 0 / / 08/28/23
District-Wide:
19-1016 Reconstruction 7-999-001 02/07/20 DONE DONE DONE 12/17/19 12/11/19 11/28/17 06/17/19 16 425,000 425,000 SLC 0 0 0 Gordon W. Jones Associates 0 09/03/21 12/11/19
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
LYNDONVILLE CENTRAL SCHOOL DISTRICT STATUS REPORT ON CAPITAL PROJECTS
District No.: 45-10-01-04
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
L A Webber High School:
23-0348 Reconstruction 0-001-016 03/13/23 DONE DONE DONE 08/29/23 08/29/23 05/19/23 03/13/23 7 320,000 320,000 WLC 0 0 0 SEI Design Group 0 / / 08/29/23
Elementary School:
22-0626 Reconstruction 0-002-007 04/13/23 DONE DONE DONE 10/03/22 10/03/22 07/19/22 07/13/22 7 580,000 531,500 WLC 0 0 0 SEI Design Group 0 05/15/23 10/03/22
23-0774 Reconstruction 0-002-008 02/05/24 DONE DONE DONE 10/23/23 10/17/23 08/11/23 05/16/23 8,9,10,155,15,16 100,000 100,000 WLC 0 0 0 SEI Design Group 0 / / 10/17/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
BOCES ORLEANS-NIAGARA STATUS REPORT ON CAPITAL PROJECTS
District No.: 45-90-00-00
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Special Ed. Building:
21-0845 Reconstruction 0-001-006 06/10/22 DONE DONE DONE 12/06/21 12/03/21 02/04/21 11/10/21 2,10,16 142,926 142,926 JLB 0 0 0 Young And Wright Architectura 0 / / 12/03/21
Niagara Academy(fmlyNewEH Bldg):
18-1668 Reconstruction 0-009-008 06/10/19 DONE DONE DONE 03/18/19 03/08/19 10/05/18 02/13/19 2,4,8,9,10,155,15,16 1,230,907 1,230,907 JLB 0 0 0 LaBella Associates P.C. 0 05/27/20 03/08/19
- Reconstruction 0-009-009 / / / / 11/01/23 / / 2,155 0 0 WLC 0 0 0 0 / / / /
Orleans Area Center:
21-0846 Reconstruction 0-011-013 06/10/22 DONE DONE DONE 12/06/21 12/03/21 02/04/21 11/10/21 2,10,155,16 3,357,074 3,357,074 JLB 0 0 0 Young And Wright Architectura 0 / / 12/03/21
Niagara Area Center:
18-1669 Reconstruction 0-012-013 06/10/19 DONE DONE DONE 03/18/19 03/08/19 10/05/18 02/13/19 2,4,8,9,10,13,155,15 1,937,868 1,937,868 JLB 0 0 0 LaBella Associates P.C. 0 05/27/20 03/08/19
- Reconstruction 0-012-014 / / / / 06/16/23 / / 2,16 0 0 WLC 0 0 0 0 / / / /
O/N BOCES Lockport Center:
19-1826 Reconstruction 0-028-002 07/02/20 DONE DONE DONE 06/09/20 05/26/20 01/31/20 05/13/20 7 299,400 0 JSS 0 0 0 LaBella Associates P.C. 0 / / 05/26/20
Pole Barn:
22-1424DB Discovered Building 7-029-001 11/17/23 DONE DONE DONE 01/06/23 01/05/23 07/11/22 / / 0 0 WLC 0 0 0 0 / / 01/05/23
Pole Barn 2:
22-1425DB Discovered Building 7-030-001 11/17/23 DONE DONE DONE 01/06/23 01/05/23 / / / / 0 0 WLC 0 0 0 0 / / 01/05/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED