ALTMAR-PARISH-WILLIAMSTOWN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 46-01-02-04
last updated on 04/17/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Jr/Sr High School:
20-1698 Reconstruction 0-001-020 07/13/21 DONE DONE DONE 05/11/21 05/07/21 02/03/21 05/21/21 8 100,000 100,000 SLC 0 0 0 Ashley McGraw 0 06/01/21 05/07/21
22-0137 Reconstruction 0-001-021 12/06/22 DONE DONE DONE 07/25/22 07/22/22 12/23/21 12/07/21 2,4,7,8,9,15,16 4,212,500 4,212,500 SLC 0 0 0 Ashley McGraw 0 / / 07/22/22
- PR Additions and Alterations 0-001-022 / / / / 05/16/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-1280 Additions and Alterations 0-001-022 05/10/23 DONE DONE DONE 12/19/22 12/16/22 05/16/22 12/07/21 02 - 16 14,878,000 12,920,500 JLB 0 0 0 Ashley McGraw 0 / / 12/16/22
Elementary School (frmly MS):
23-0929 Reconstruction 0-005-011 UNREVIEWED 11/08/23 11/03/23 02/16/23 12/07/21 2,4,7,8,9,10,155,15, 0 0 MSK 0 0 0 Ashley McGraw 0 / / 11/03/23
- PR Additions and Alterations 0-005-012 / / / / 05/23/23 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
23-0465FA Additions and Alterations 0-005-012 11/01/23 DONE DONE DONE 09/13/23 08/21/23 05/23/23 06/08/23 02 - 16 700,000 0 MSK 0 0 0 Ashley McGraw 0 / / 08/21/23
Storage Building:
- PR New Construction 2-027-001 / / / / 05/18/22 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
22-1281 New Construction 2-027-001 05/10/23 DONE DONE DONE 12/19/22 12/16/22 05/18/22 12/07/21 02 - 16 158,000 0 JLB 0 0 0 Ashley McGraw 0 / / 12/16/22
Transportation Facility:
22-0138 Reconstruction 5-019-006 12/06/22 DONE DONE DONE 07/25/22 07/22/22 12/23/21 12/07/21 2,4,7,8,9,15,16 2,604,000 2,604,000 SLC 0 0 0 Ashley McGraw 0 / / 07/22/22
Waste Water Treatment:
22-1282 Reconstruction 7-017-003 05/10/23 DONE DONE DONE 12/19/22 12/16/22 05/12/22 12/07/21 15,16 3,481,500 0 JLB 0 0 0 Ashley McGraw 0 / / 12/16/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
FULTON CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 46-05-00-01
last updated on 04/17/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Fulton Jr High School:
19-1470 Reconstruction 0-005-013 05/19/20 DONE DONE DONE 02/24/20 02/21/20 07/02/19 05/21/19 2,4,8,9,10,155,15,16 2,912,000 2,912,000 JSS 0 0 0 King & King Architects 0 09/02/21 02/21/20
20-0219 Reconstruction 0-005-014 11/10/20 DONE DONE DONE 08/14/20 07/30/20 03/09/20 07/07/20 7,155,16 756,616 756,616 JSS 0 0 0 King & King Architects 756,616 08/01/22 07/30/20
- Reconstruction 0-005-015 / / / / 05/31/23 / / 2,4,7,8,9,14,155,15, 0 0 JJH 0 0 0 0 / / / /
James E. Lannigan:
19-1471 Reconstruction 0-006-011 05/19/20 DONE DONE DONE 02/24/20 02/21/20 07/02/19 05/21/19 2,4,8,9,10,155,15,16 1,777,000 1,777,000 JSS 0 0 0 King & King Architects 0 09/02/21 02/21/20
20-0220 Reconstruction 0-006-012 11/10/20 DONE DONE DONE 08/14/20 07/30/20 03/09/20 07/07/20 7,155,16 269,344 269,344 JSS 0 0 0 King & King Architects 269,344 04/14/22 07/30/20
20-1183 Reconstruction 0-006-013 04/19/21 DONE DONE DONE 01/25/21 01/07/21 11/17/20 05/21/19 16 118,000 118,000 JSS 0 0 0 King & King Architects 0 11/01/22 01/07/21
21-1784 Reconstruction 0-006-014 08/04/22 DONE DONE DONE 05/09/22 05/04/22 11/03/21 05/21/19 2,8,9,155,15,16 611,000 611,000 JLB 0 0 0 King & King Architects 0 / / 05/04/22
- Reconstruction 0-006-015 / / / / 05/31/23 / / 2,7,8,155,15,16 0 0 JJH 0 0 0 0 / / / /
Granby Elementary School:
21-1785 Reconstruction 0-009-012 08/04/22 DONE DONE DONE 05/09/22 05/04/22 07/02/19 05/21/19 2,4,8,9,10,14,155,15 1,115,000 1,115,000 JLB 0 0 0 King & King Architects 0 / / 05/04/22
20-0221 Reconstruction 0-009-013 11/10/20 DONE DONE DONE 08/14/20 07/30/20 03/09/20 07/07/20 7,155,16 373,298 373,298 JSS 0 0 0 King & King Architects 373,298 04/14/22 07/30/20
20-1184 Reconstruction 0-009-014 04/19/21 DONE DONE DONE 01/25/21 01/07/21 11/17/20 05/21/19 16 270,000 270,000 JSS 0 0 0 King & King Architects 0 11/01/22 01/07/21
- Reconstruction 0-009-015 / / / / 05/31/23 / / 2,4,7,8,9,155,15,16 0 0 JJH 0 0 0 0 / / / /
Fairgrieve Elementary:
19-0534 Reconstruction 0-012-013 12/09/19 DONE DONE DONE 10/07/19 09/26/19 / / 05/21/19 2,9 100,000 100,000 BMJ 0 0 0 King & King Architects 0 06/04/20 09/26/19
21-1786 Reconstruction 0-012-014 08/04/22 DONE DONE DONE 05/09/22 05/04/22 07/02/19 05/21/19 2,4,8,9,10,155,15,16 369,000 369,000 JLB 0 0 0 King & King Architects 0 / / 05/04/22
20-0222 Reconstruction 0-012-015 11/10/20 DONE DONE DONE 08/14/20 07/30/20 03/09/20 07/07/20 7,155,16 275,043 275,043 JSS 0 0 0 King & King Architects 275,043 04/14/22 07/30/20
- Reconstruction 0-012-016 / / / / 05/31/23 / / 2,4,8,9,10,155,15,16 0 0 JJH 0 0 0 0 / / / /
23-1324 Reconstruction 0-012-017 UNREVIEWED 01/04/24 01/04/24 10/23/23 05/16/23 2,8,155 0 0 JJH 0 0 0 King & King Architects 0 / / 01/04/24
G. Ray Bodley High School:
20-1790 Reconstruction 0-015-014 07/26/21 DONE DONE DONE 05/28/21 05/27/21 07/02/19 05/21/19 2,4,7,8,9,10,155,15, 2,300,000 2,300,000 JLB 0 0 0 King & King Architects 0 10/07/23 05/27/21
20-0223 Reconstruction 0-015-015 11/10/20 DONE DONE DONE 08/14/20 07/30/20 03/09/20 07/07/20 7,155,16 1,590,991 1,590,991 JSS 0 0 0 King & King Architects 1,590,991 04/14/22 07/30/20
20-1185 Reconstruction 0-015-016 04/19/21 DONE DONE DONE 01/25/21 01/07/21 11/17/20 05/21/19 16 590,000 590,000 JSS 0 0 0 King & King Architects 0 11/01/22 01/07/21
21-1787 Reconstruction 0-015-017 08/04/22 DONE DONE DONE 05/09/22 05/04/22 11/03/21 05/21/19 2,8,9,155,15,16 2,457,000 2,457,000 JLB 0 0 0 King & King Architects 0 / / 05/04/22
22-2451FA Reconstruction 0-015-018 07/19/23 DONE DONE DONE 06/23/23 06/07/23 05/01/23 05/23/23 7,9,155,15,16 1,040,200 0 JJH 0 0 0 King & King Architects 0 / / 06/07/23
- Reconstruction 0-015-019 / / / / 05/31/23 / / 2,4,7,8,9,10,14,155, 0 0 JJH 0 0 0 0 / / / /
23-1283 Reconstruction 0-015-020 UNREVIEWED 12/22/23 12/22/23 10/23/23 05/16/23 9,10,16 0 0 JJH 0 0 0 King & King Architects 0 / / 12/22/23
Volney Elementary:
19-1472 Reconstruction 0-017-012 05/19/20 DONE DONE DONE 02/24/20 02/21/20 07/02/19 05/21/19 2,4,7,8,9,10,155,15, 2,223,000 2,223,000 JSS 0 0 0 King & King Architects 0 09/02/21 02/21/20
20-0224 Reconstruction 0-017-013 11/10/20 DONE DONE DONE 08/14/20 07/30/20 03/09/20 07/07/20 7,155,16 611,792 611,792 JSS 0 0 0 King & King Architects 611,792 04/14/22 07/30/20
21-1788 Reconstruction 0-017-014 08/04/22 DONE DONE DONE 05/09/22 05/04/22 11/03/21 05/21/19 2,9,155,15,16 358,000 358,000 JLB 0 0 0 King & King Architects 0 / / 05/04/22
- Reconstruction 0-017-015 / / / / 05/31/23 / / 2,7,8,9,155,16 0 0 JJH 0 0 0 0 / / / /
Education Center:
- Reconstruction 0-018-012 / / / / 07/02/19 / / 2,7,9,14,16 0 0 BMJ 0 0 0 0 / / / /
20-0225 Reconstruction 0-018-013 11/10/20 DONE DONE DONE 08/14/20 07/30/20 03/09/20 07/07/20 7,155,16 375,970 375,970 JSS 0 0 0 King & King Architects 375,970 03/09/22 07/30/20
- Reconstruction 0-018-014 / / / / 05/31/23 / / 4,14,15 0 0 JJH 0 0 0 0 / / / /
23-0646 Reconstruction 0-018-015 11/13/23 DONE DONE DONE 10/06/23 10/04/23 05/31/23 05/16/23 4 100,000 100,000 JJH 0 0 0 King & King Architects 0 / / 10/04/23
District Garage:
- Reconstruction 5-001-001 / / / / 03/09/20 / / 7,155,16 0 0 JSS 0 0 0 0 / / / /
Athletic Complex:
- Reconstruction 7-002-002 / / / / 04/03/20 / / 7 0 0 JSS 0 0 0 0 / / / /
- Reconstruction 7-002-003 / / / / 05/31/23 / / 2,4,7,15,16 0 0 JJH 0 0 0 0 / / / /
District-Wide:
19-0215SB Reconstruction 7-999-004 DONE / / / / 08/06/19 / / 16 0 0 JSS 0 0 0 0 / / / /
20-0244 Reconstruction 7-999-004 11/20/20 DONE DONE DONE 08/21/20 07/23/20 08/06/19 08/27/09 16 86,000 0 JSS 0 0 0 King & King Architects 0 12/12/22 07/23/20
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 JSS 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
HANNIBAL CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 46-07-01-04
last updated on 04/17/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
High School:
19-0490 Reconstruction 0-002-017 01/17/20 DONE DONE DONE 09/25/19 09/20/19 09/14/18 11/29/17 2,8,9,10,14,155,15,1 12,122,239 12,122,239 BMJ 0 0 0 King & King Architects 0 09/30/21 09/20/19
20-1058 Reconstruction 0-002-018 03/05/21 DONE DONE DONE 12/29/20 12/11/20 05/26/20 06/09/20 4,9,16 100,000 100,000 JSS 0 0 0 King & King Architects 0 06/17/21 12/11/20
- XX Reconstruction 0-002-019 CANCELLED / / / / 07/31/20 / / 10,16 0 0 JSS 0 0 0 0 / / / /
21-0876 Reconstruction 0-002-020 01/25/22 DONE DONE DONE 12/10/21 12/06/21 05/26/21 05/18/21 9 100,000 100,000 SLC 0 0 0 King & King Architects 0 06/20/22 12/06/21
21-1865FC Reconstruction 0-002-021 07/27/22 DONE DONE DONE 05/23/22 05/18/22 09/13/21 10/14/21 8,16 400,000 400,000 JLB 0 0 0 King & King Architects 0 09/06/23 05/18/22
22-1498FA Reconstruction 0-002-022 03/24/23 DONE DONE DONE 01/18/23 01/11/23 03/15/22 10/14/21 2,8,9,155,15,16 500,000 500,000 JJH 0 0 0 King & King Architects 0 11/10/23 01/11/23
22-0037FA Reconstruction 0-002-023 09/19/22 DONE DONE DONE 07/05/22 06/30/22 05/18/22 10/14/21 2,7,8 45,865 45,865 JLB 0 0 0 King & King Architects 0 09/06/23 06/30/22
Fairley Elementary:
19-0491 Reconstruction 0-003-017 01/17/20 DONE DONE DONE 09/25/19 09/20/19 09/14/18 11/29/17 2,8,9,155,15,16 2,863,190 2,863,190 BMJ 0 0 0 King & King Architects 0 09/30/21 09/20/19
- XX Reconstruction 0-003-018 CANCELLED / / / / 07/31/20 / / 10 0 0 JSS 0 0 0 0 / / / /
21-1866 Reconstruction 0-003-019 07/27/22 DONE DONE DONE 05/23/22 05/18/22 09/13/21 10/14/21 8,16 240,000 240,000 JLB 0 0 0 King & King Architects 0 09/06/23 05/18/22
23-0560 Reconstruction 0-003-020 ADDENDUM REQ'D 09/27/23 09/20/23 02/28/22 11/29/17 2,8,9,10,155,15,16 0 0 JJH 0 0 0 King & King Architects 0 / / 09/20/23
22-1499FA Reconstruction 0-003-021 03/24/23 DONE DONE DONE 01/18/23 01/11/23 03/15/22 10/14/21 2,8,9,16 1,000,000 1,000,000 JJH 0 0 0 King & King Architects 0 11/10/23 01/11/23
22-1449 Reconstruction 0-003-022 03/07/23 DONE DONE DONE 01/09/23 01/05/23 10/12/22 05/17/22 9,16 100,000 100,000 JJH 0 0 0 King & King Architects 0 06/20/23 01/05/23
23-0382 Reconstruction 0-003-023 11/01/23 DONE DONE DONE 09/05/23 09/05/23 08/08/23 05/16/23 9,16 100,000 100,000 JJH 0 0 0 King & King Architects 0 / / 09/05/23
- Reconstruction 0-003-024 / / / / / / / / 9,16 0 0 JJH 0 0 0 0 / / / /
Kenney Middle School (Cayuga Street):
19-0492 Reconstruction 0-004-015 01/17/20 DONE DONE DONE 09/25/19 09/20/19 09/14/18 11/29/17 2,8,9,10,155,15,16 2,089,750 2,089,750 BMJ 0 0 0 King & King Architects 0 09/30/21 09/20/19
- XX Reconstruction 0-004-016 CANCELLED / / / / 07/31/20 / / 10 0 0 JSS 0 0 0 0 / / / /
21-1867FC Reconstruction 0-004-017 07/27/22 DONE DONE DONE 05/23/22 05/18/22 09/13/21 10/14/21 8,16 216,000 216,000 JLB 0 0 0 King & King Architects 0 09/06/23 05/18/22
23-0561 Reconstruction 0-004-018 ADDENDUM REQ'D 09/27/23 09/20/23 02/28/22 11/29/17 2,8,9,10,155,15,16 0 0 JJH 0 0 0 King & King Architects 0 / / 09/20/23
22-0038FA Reconstruction 0-004-019 09/19/22 DONE DONE DONE 07/05/22 06/30/22 05/18/22 10/14/21 2,8 686,780 686,780 JLB 0 0 0 King & King Architects 0 09/06/23 06/30/22
xxxBus Garagexxx DEMOLISHED:
19-0493 Reconstruction 5-006-009 01/17/20 DONE DONE DONE 09/25/19 09/20/19 08/31/17 11/28/17 2,10 275,500 275,500 BMJ 0 0 0 King & King Architects 0 09/07/21 09/20/19
District-Wide:
18-1888SB Reconstruction 7-999-002 DONE / / / / 04/22/19 / / 8,9,155,16 0 0 BMJ 0 0 0 0 / / / /
21-1215 Reconstruction 7-999-002 04/21/22 DONE DONE DONE 01/31/22 01/31/22 04/22/19 11/04/14 8,9,155,16 1,236,665 0 JLB 0 0 0 King & King Architects 0 / / 01/31/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
CENTRAL SQUARE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 46-08-01-06
last updated on 04/17/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Brewerton Elementary:
19-1315 Reconstruction 0-001-016 05/21/20 DONE DONE DONE 01/30/20 01/13/20 03/18/19 05/21/19 8 1,215,082 1,215,082 BMJ 0 0 0 King & King Architects 0 06/15/22 01/13/20
23-0530 Reconstruction 0-001-017 DONE ADD. REQ'D DONE 09/22/23 09/18/23 04/26/23 05/17/22 8,9,155,15,16 1,124,000 0 MSK 0 0 0 King & King Architects 0 / / 09/18/23
Cole Elementary at Constantia:
19-1316 Reconstruction 0-002-017 05/21/20 DONE DONE DONE 01/30/20 01/13/20 03/18/19 05/21/19 8 2,315,537 2,315,537 BMJ 0 0 0 King & King Architects 0 06/15/22 01/13/20
23-0531 Reconstruction 0-002-018 DONE ADD. REQ'D DONE 09/22/23 09/18/23 04/26/23 05/17/22 2,9,155,15,16 4,300,000 0 MSK 0 0 0 King & King Architects 0 / / 09/18/23
Paul V Moore High School:
19-1317 Reconstruction 0-005-014 05/21/20 DONE DONE DONE 01/30/20 01/13/20 03/18/19 05/21/19 8 2,247,242 2,247,242 BMJ 0 0 0 King & King Architects 0 06/15/22 01/13/20
20-0016 Reconstruction 0-005-015 07/27/20 DONE DONE DONE 07/02/20 06/03/20 04/21/20 05/21/19 8 100,000 100,000 JLB 0 0 0 King & King Architects 0 09/15/20 06/03/20
21-1672 Reconstruction 0-005-016 06/15/22 DONE DONE DONE 04/18/22 04/14/22 04/04/22 05/18/21 155 100,000 100,000 SLC 0 0 0 King & King Architects 0 06/30/22 04/14/22
22-0783 Reconstruction 0-005-017 03/07/23 DONE DONE DONE 10/21/22 10/20/22 09/01/22 05/17/22 2,9 2,945,000 2,945,000 SLC 0 0 0 King & King Architects 0 / / 10/20/22
22-2078 Reconstruction 0-005-018 06/29/23 DONE DONE DONE 04/21/23 04/21/23 04/11/23 05/17/22 8 100,000 100,000 MSK 0 0 0 King & King Architects 0 / / 04/21/23
23-0532 Reconstruction 0-005-019 DONE ADD. REQ'D DONE 09/22/23 09/18/23 04/26/23 05/17/22 9,14,155,15,16 5,256,000 0 MSK 0 0 0 King & King Architects 0 / / 09/18/23
Hawk Primary School:
19-1318 Reconstruction 0-006-011 05/21/20 DONE DONE DONE 01/30/20 01/13/20 03/18/19 05/21/19 8 1,106,686 1,106,686 BMJ 0 0 0 King & King Architects 0 06/15/22 01/13/20
23-0533 Reconstruction 0-006-012 DONE ADD. REQ'D DONE 09/22/23 09/18/23 04/26/23 05/17/22 9,155,15,16 1,230,000 0 MSK 0 0 0 King & King Architects 0 / / 09/18/23
Central Square Intermediate:
19-1319 Reconstruction 0-007-012 05/21/20 DONE DONE DONE 01/30/20 01/13/20 03/18/19 05/21/19 8 336,437 336,437 BMJ 0 0 0 King & King Architects 0 06/15/22 01/13/20
22-0784SS Reconstruction 0-007-013 03/07/23 DONE DONE DONE 10/21/22 10/20/22 09/01/22 05/17/22 7 1,331,000 0 SLC 0 0 0 King & King Architects 0 / / 10/20/22
Hastings Mallory Elementary:
19-1320 Reconstruction 0-008-012 05/21/20 DONE DONE DONE 01/30/20 01/13/20 03/18/19 05/21/19 8 2,423,932 2,423,932 BMJ 0 0 0 King & King Architects 0 06/15/22 01/13/20
22-0785 Reconstruction 0-008-013 03/07/23 DONE DONE DONE 10/21/22 10/20/22 09/01/22 05/17/22 2,9,155,15,16 4,310,000 4,310,000 SLC 0 0 0 King & King Architects 0 / / 10/20/22
Middle School:
19-1321 Reconstruction 0-019-009 05/21/20 DONE DONE DONE 01/30/20 01/13/20 03/18/19 05/21/19 8 1,563,243 1,563,243 BMJ 0 0 0 King & King Architects 0 06/15/22 01/13/20
20-1599 Reconstruction 0-019-010 05/18/21 DONE DONE DONE 04/19/21 03/29/21 03/05/21 06/09/20 8 100,000 0 JSS 0 0 0 King & King Architects 0 06/30/21 03/29/21
22-0786 Reconstruction 0-019-011 03/07/23 DONE DONE DONE 10/21/22 10/20/22 09/01/22 05/17/22 8,9 1,668,000 1,668,000 SLC 0 0 0 King & King Architects 0 / / 10/20/22
23-0534 Reconstruction 0-019-012 DONE ADD. REQ'D DONE 09/22/23 09/18/23 04/26/23 05/17/22 2,9,16 1,273,000 0 MSK 0 0 0 King & King Architects 0 / / 09/18/23
- Reconstruction 0-019-013 / / / / 04/26/23 / / 155 0 0 JLB 0 0 0 0 / / / /
- Reconstruction 0-019-014 / / / / 03/27/24 / / 9,155 0 0 MSK 0 0 0 0 / / / /
Stadium Building:
23-0535 Reconstruction 0-023-003 DONE ADD. REQ'D DONE 09/22/23 09/18/23 04/26/23 05/17/22 9,155,15,16 315,000 0 MSK 0 0 0 King & King Architects 0 / / 09/18/23
Bus Garage (Maintenance Ctr):
23-0536 Reconstruction 5-009-006 DONE ADD. REQ'D DONE 09/22/23 09/18/23 04/26/23 05/17/22 8,155,16 420,000 0 MSK 0 0 0 King & King Architects 0 / / 09/18/23
Transportation Center:
23-0537 Reconstruction 5-020-004 DONE ADD. REQ'D DONE 09/22/23 09/18/23 04/26/23 05/17/22 7,155 828,000 0 MSK 0 0 0 King & King Architects 0 / / 09/18/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
MEXICO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 46-09-01-06
last updated on 04/17/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
New Haven Elementary:
- Reconstruction 0-001-014 / / / / 10/26/23 / / 155,16 0 0 JJH 0 0 0 0 / / / /
Palermo Elementary School:
- Reconstruction 0-002-015 / / / / 10/26/23 / / 155,16 0 0 JJH 0 0 0 0 / / / /
Mexico Elementary School:
19-0972XX Reconstruction 0-003-015 01/21/20 CANCELLED 12/10/19 11/26/19 05/16/19 05/21/19 7,8,9,155,15,16 100,000 100,000 JLB 0 0 0 Bernier Carr Associates 0 / / 11/26/19
19-1404XX Reconstruction 0-003-016 CANCELLED 02/11/20 02/07/20 01/29/20 / / 8,9,10,155,15,16 0 10,308,556 JLB 0 0 0 Bernier Carr & Associates 0 / / 02/07/20
20-0154 Reconstruction 0-003-017 09/22/20 DONE DONE DONE 08/05/20 07/30/20 07/10/20 06/09/20 8,9,10,155,15,16 525,000 525,000 JLB 0 0 0 Bernier Carr Associates 0 04/23/21 07/30/20
21-0007 Reconstruction 0-003-018 07/28/21 DONE DONE DONE 07/06/21 07/02/21 05/20/21 06/24/21 155,16 250,000 0 JLB 0 0 0 Bernier Carr Associates 0 / / 07/02/21
22-1741 Reconstruction 0-003-019 04/25/22 DONE DONE DONE 02/22/23 02/22/23 05/09/22 04/25/22 7,9 1,119,879 1,119,879 JJH 0 0 0 Clark Patterson Lee Architect 0 12/22/22 02/22/23
- Reconstruction 0-003-020 / / / / 10/26/23 / / 2,155,15,16 0 0 JJH 0 0 0 0 / / / /
Mexico High School:
18-0312 Reconstruction 0-004-022 05/03/19 DONE DONE DONE 08/27/18 08/24/18 06/19/18 11/04/14 2,4,15,16 800,000 800,000 MTM 0 0 0 SWBR Architects P.C. 0 / / 08/24/18
22-1694FA Reconstruction 0-004-023 04/12/23 DONE DONE DONE 02/17/23 01/30/23 12/22/22 12/15/22 16 500,000 500,000 JJH 0 0 0 Clark Patterson Lee Architect 0 / / 01/30/23
- Reconstruction 0-004-024 / / / / 10/26/23 / / 2,15 0 0 JJH 0 0 0 0 / / / /
Mexico Middle School:
- Reconstruction 0-005-011 / / / / 10/26/23 / / 155,16 0 0 JJH 0 0 0 0 / / / /
Bus Garage:
18-2197 Reconstruction 4-008-009 02/21/19 DONE DONE DONE 06/25/19 05/28/19 03/21/19 02/14/19 2,14 55,000 55,000 JLB 0 0 0 SWBR Architects P.C. 0 08/16/19 05/28/19
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
OSWEGO CITY SCHOOL STATUS REPORT ON CAPITAL PROJECTS
District No.: 46-13-00-01
last updated on 04/17/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Oswego Middle School:
22-1133 Reconstruction 0-001-016 01/12/23 DONE DONE DONE 12/02/22 11/30/22 01/19/18 12/18/18 2,4,7,8,9,10,155,15, 11,089,818 11,089,818 SLC 0 0 0 King & King Architects 0 / / 11/30/22
18-1729 Reconstruction 0-001-017 05/03/19 DONE DONE DONE 03/27/19 03/21/19 01/07/19 12/18/18 155,15,16 785,000 785,000 SLC 0 0 0 King & King Architects 0 12/06/19 03/21/19
19-0951 Reconstruction 0-001-018 04/15/20 DONE DONE DONE 12/10/19 11/25/19 02/14/19 12/18/18 2,155,15,16 1,575,000 1,575,000 SLC 0 0 0 King & King Architects 0 03/01/21 11/25/19
23-0833 Reconstruction 0-001-019 UNREVIEWED 10/30/23 10/27/23 06/22/23 03/21/23 155,15,16 0 0 MSK 0 0 0 King & King Architects 0 / / 10/27/23
Park Elementary School:
19-0952 Reconstruction 0-002-014 04/15/20 DONE DONE DONE 12/10/19 11/25/19 01/19/18 12/18/18 2,4,7,8,9,10,155,15, 950,000 950,000 SLC 0 0 0 King & King Architects 0 03/01/21 11/25/19
20-1569 Reconstruction 0-002-015 02/18/22 DONE DONE DONE 04/09/21 03/30/21 01/25/19 12/18/18 2,4,8,9,155,16 1,540,533 1,540,533 SLC 0 0 0 King & King Architects 0 / / 03/30/21
23-0834 Reconstruction 0-002-016 UNREVIEWED 10/30/23 10/27/23 06/22/23 03/21/23 155,15,16 0 0 MSK 0 0 0 King & King Architects 0 / / 10/27/23
Kingsford Park Elementary School:
19-0953 Reconstruction 0-003-015 04/15/20 DONE DONE DONE 12/10/19 11/25/19 01/19/18 12/18/18 2,4,7,8,9,10,155,15, 950,000 950,000 SLC 0 0 0 King & King Architects 0 03/01/21 11/25/19
20-1570 Reconstruction 0-003-016 02/18/22 DONE DONE DONE 04/09/21 03/30/21 / / 12/18/18 2,4,8,9,155,16 2,133,890 2,133,890 SLC 0 0 0 King & King Architects 0 / / 03/30/21
23-0835 Reconstruction 0-003-017 UNREVIEWED 10/30/23 10/27/23 06/22/23 03/21/23 155,15,16 0 0 MSK 0 0 0 King & King Architects 0 / / 10/27/23
Riley Elementary School:
20-1571 Reconstruction 0-004-018 02/18/22 DONE DONE DONE 04/09/21 03/30/21 01/19/18 12/18/18 2,4,7,8,9,10,155,15, 2,674,623 2,674,623 SLC 0 0 0 King & King Architects 0 / / 03/30/21
23-0836 Reconstruction 0-004-019 UNREVIEWED 10/30/23 10/27/23 06/22/23 03/21/23 155,15,16 0 0 MSK 0 0 0 King & King Architects 0 / / 10/27/23
- Reconstruction 0-004-020 / / / / 03/27/24 / / 2,4,8,9 0 0 MSK 0 0 0 0 / / / /
Frederick Leighton Elementary School:
19-0954 Reconstruction 0-005-019 04/15/20 DONE DONE DONE 12/10/19 11/25/19 01/19/18 12/18/18 2,4,7,8,9,10,155,15, 1,920,000 1,920,000 SLC 0 0 0 King & King Architects 0 03/01/21 11/25/19
20-1175 Reconstruction 0-005-022 02/01/21 DONE DONE DONE 01/21/21 01/21/21 11/06/20 12/04/20 2 1,600,000 1,524,733 SLC 0 0 0 King & King Architects 0 01/10/22 01/21/21
23-0377 Reconstruction 0-005-023 11/09/23 DONE DONE DONE 09/05/23 09/05/23 06/22/23 08/15/23 2,8,9,155,15,16 480,000 0 MSK 0 0 0 King & King Architects 0 / / 09/05/23
23-0837 Reconstruction 0-005-024 UNREVIEWED 10/30/23 10/27/23 06/22/23 03/21/23 155,15,16 0 0 MSK 0 0 0 King & King Architects 0 / / 10/27/23
Minetto Elementary School:
20-1572 Reconstruction 0-008-019 02/18/22 DONE DONE DONE 04/09/21 03/30/21 01/19/18 12/18/18 2,4,7,8,9,10,155,15, 2,137,305 2,137,305 SLC 0 0 0 King & King Architects 0 / / 03/30/21
23-0838 Reconstruction 0-008-020 UNREVIEWED 10/30/23 10/27/23 06/22/23 03/21/23 155,15,16 0 0 MSK 0 0 0 King & King Architects 0 / / 10/27/23
Oswego High School:
19-0955 Reconstruction 0-018-029 04/15/20 DONE DONE DONE 12/10/19 11/25/19 01/19/18 12/18/18 2,4,7,8,9,10,155,15, 11,498,000 11,498,000 SLC 0 0 0 King & King Architects 0 03/01/21 11/25/19
20-1176 Reconstruction 0-018-032 02/01/21 DONE DONE DONE 01/21/21 01/21/21 11/23/20 12/04/20 2 4,000,000 4,000,000 SLC 0 0 0 King & King Architects 0 01/10/22 01/21/21
23-0839 Reconstruction 0-018-033 UNREVIEWED 10/30/23 10/27/23 06/22/23 03/21/23 155,15,16 0 0 MSK 0 0 0 King & King Architects 0 / / 10/27/23
District Warehouse:
23-0840 Reconstruction 2-009-005 UNREVIEWED 10/30/23 10/27/23 06/22/23 03/21/23 155,15,16 0 0 MSK 0 0 0 King & King Architects 0 / / 10/27/23
OMS Storage / ToiletFacility:
19-0956 Reconstruction 2-011-002 04/15/20 DONE DONE DONE 12/10/19 11/25/19 05/13/19 12/18/18 9,15 60,000 0 SLC 0 0 0 King & King Architects 0 / / 11/25/19
XXHS StorageBldg/BleachersDemo'd2020:
19-1807 Reconstruction 2-026-002 10/06/20 DONE DONE DONE 06/03/20 05/11/20 03/06/20 12/18/18 2 2,500 0 SLC 0 0 0 King & King Architects 0 / / 05/11/20
OMS Storage Bldg. (PoleBarn):
- PR New Construction 2-049-001 / / / / 05/13/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
19-0957 Alterations 2-049-001 04/15/20 DONE DONE DONE 12/10/19 11/25/19 05/13/19 12/18/18 02 - 16 215,000 0 SLC 0 0 0 King & King Architects 0 / / 11/25/19
Stadium Equipment Storage:
- PR New Construction 2-050-001 / / / / 05/13/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
19-0958 New Construction 2-050-001 04/15/20 DONE DONE DONE 12/10/19 11/25/19 05/13/19 12/18/18 02 - 16 50,000 0 SLC 0 0 0 King & King Architects 0 / / 11/25/19
Bus Storage Bldg:
23-0841 Reconstruction 4-014-004 UNREVIEWED 10/30/23 10/27/23 06/22/23 03/21/23 155,15,16 0 0 MSK 0 0 0 King & King Architects 0 / / 10/27/23
XXPress Box @HS Demo'd 2020:
19-1808 Reconstruction 7-012-001 10/06/20 DONE DONE DONE 06/03/20 05/11/20 03/06/20 12/18/18 2 2,500 0 SLC 0 0 0 King & King Architects 0 / / 05/11/20
XXConcessionStand Demo'd 2020:
19-1809 Reconstruction 7-017-002 10/06/20 DONE DONE DONE 06/03/20 05/11/20 03/06/20 12/18/18 2 2,500 0 SLC 0 0 0 King & King Architects 0 / / 05/11/20
XXDugout Home Team Demo'd 2020:
19-1810 Reconstruction 7-042-002 10/06/20 DONE DONE DONE 06/03/20 05/11/20 03/06/20 12/18/18 2 2,500 0 SLC 0 0 0 King & King Architects 0 / / 05/11/20
XXDugout Visiting Team-Demo'd 2020:
19-1811 Reconstruction 7-043-002 10/06/20 DONE DONE DONE 06/03/20 05/11/20 03/06/20 12/18/18 2 2,500 0 SLC 0 0 0 King & King Architects 0 / / 05/11/20
Stadium Locker Faciliy - Field House:
19-0959 Alterations 7-048-001 04/15/20 DONE DONE DONE 12/10/19 11/25/19 01/11/19 12/18/18 02 - 16 480,000 0 SLC 0 0 0 King & King Architects 0 03/01/21 11/25/19
OMS Press Box:
- PR New Construction 7-051-001 / / / / 05/13/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
19-0960 New Construction 7-051-001 04/15/20 DONE DONE DONE 12/10/19 11/25/19 05/13/19 12/18/18 02 - 16 120,000 0 SLC 0 0 0 King & King Architects 0 / / 11/25/19
Stadium Concession Facility:
- PR New Construction 7-052-001 / / / / 05/13/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
19-0961 New Construction 7-052-001 04/15/20 DONE DONE DONE 12/10/19 11/25/19 05/13/19 12/18/18 02 - 16 600,000 0 SLC 0 0 0 King & King Architects 0 03/01/21 11/25/19
Stadium Press Box (HS):
- PR New Construction 7-053-001 / / / / 05/13/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
19-0962 New Construction 7-053-001 04/15/20 DONE DONE DONE 12/10/19 11/25/19 05/13/19 12/18/18 02 - 16 180,000 0 SLC 0 0 0 King & King Architects 0 03/01/21 11/25/19
District Wide:
19-0305SB Reconstruction 7-999-003 DONE / / / / 08/27/19 / / 10 0 0 SLC 0 0 0 0 / / / /
23-1305 Reconstruction 7-999-003 UNREVIEWED 12/28/23 12/28/23 08/27/19 08/16/19 10 0 0 MSK 0 0 0 King & King Architects 0 / / 12/28/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
SANDY CREEK CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 46-19-01-04
last updated on 04/17/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
19-1048 Reconstruction 0-002-017 05/29/20 DONE DONE DONE 12/26/19 12/04/19 07/31/18 03/06/18 2,4,7,8,9,10,155,15, 14,548,000 14,548,000 JLB 0 0 479,636 King & King Architects 0 02/28/22 12/04/19
19-0927 Reconstruction 0-002-018 01/10/20 DONE DONE DONE 12/05/19 11/25/19 06/04/19 05/21/19 16 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/12/20 11/25/19
20-1622 Reconstruction 0-002-019 05/04/21 DONE DONE DONE 04/23/21 04/15/21 03/09/21 06/09/20 16 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/16/21 04/15/21
21-1029 Reconstruction 0-002-020 02/08/22 DONE DONE DONE 01/03/22 01/03/22 05/12/21 05/18/21 14 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/29/22 01/03/22
21-1670 Reconstruction 0-002-021 07/25/22 DONE DONE DONE 04/18/22 04/14/22 11/01/21 03/06/18 2,4,8,9,10,155,15,16 3,500,000 3,500,000 FMJ 0 0 0 King & King Architects 0 / / 04/14/22
22-0168 Reconstruction 0-002-022 12/07/22 DONE DONE DONE 07/27/22 07/26/22 06/01/22 05/17/22 8,10 100,000 100,000 JJH 0 0 0 King & King Architects 0 04/01/23 07/26/22
23-0539 Reconstruction 0-002-023 10/30/23 DONE DONE DONE 09/22/23 09/20/23 06/21/23 05/16/23 9 100,000 100,000 WLC 0 0 0 King & King Architects 0 / / 09/20/23
Bus Garage Storage Maint.:
19-1049 Reconstruction 5-001-004 05/29/20 DONE DONE DONE 12/26/19 12/04/19 07/31/18 03/16/18 2,4,7,8,9,10,155,15, 930,000 930,000 JLB 0 0 0 King & King Architects 0 04/15/21 12/04/19
New Bus Maintenance Garage:
18-1911PR New Construction 5-016-001 DONE 04/30/19 / / 08/01/18 / / 02 - 16 0 0 MTM 0 0 0 0 / / / /
19-1050 New Construction 5-016-001 05/29/20 DONE DONE DONE 12/26/19 12/04/19 08/01/18 03/06/18 02 - 16 8,040,000 8,040,000 JLB 0 0 0 King & King Architects 0 10/15/21 12/04/19
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
PHOENIX CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 46-20-01-06
last updated on 04/17/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Elm Street School:
19-1184 Reconstruction 0-002-014 03/05/20 DONE DONE DONE 01/10/20 01/07/20 12/16/19 12/10/19 2,9 512,500 512,500 JSS 0 0 0 King & King Architects 0 09/03/21 01/07/20
John Birdlebough High School:
19-0451 Reconstruction 0-003-018 11/26/19 DONE DONE DONE 09/20/19 09/13/19 07/09/19 05/21/19 2 100,000 100,000 JSS 0 0 0 King & King Architects 0 04/01/20 09/13/19
19-1185 Reconstruction 0-003-019 03/05/20 DONE DONE DONE 01/10/20 01/07/20 12/16/19 12/10/19 2,14,155,15,16 1,437,500 1,437,500 JSS 0 0 0 King & King Architects 0 09/03/21 01/07/20
21-0658FC Reconstruction 0-003-020 11/12/21 DONE DONE DONE 11/05/21 11/04/21 09/09/21 10/04/21 2 200,000 200,000 JLB 0 0 0 0 06/15/22 11/04/21
22-2490 Reconstruction 0-003-021 08/14/23 DONE DONE DONE 06/30/23 06/30/23 04/05/23 05/16/23 2,8,9 100,000 100,000 JJH 0 0 0 King & King Architects 0 / / 06/30/23
Junior High School:
19-1186 Reconstruction 0-005-017 03/05/20 DONE DONE DONE 01/10/20 01/07/20 12/16/19 12/10/19 2,8,9,16 650,000 650,000 JSS 0 0 0 King & King Architects 0 09/03/21 01/07/20
20-0984 Reconstruction 0-005-018 03/15/21 DONE DONE DONE 12/16/20 12/08/20 08/10/20 06/16/20 9,10 100,000 100,000 JSS 0 0 0 King & King Architects 0 06/24/21 12/08/20
21-0447 Reconstruction 0-005-019 11/17/21 DONE DONE DONE 09/29/21 09/29/21 07/21/21 05/18/21 2,8,9 100,000 100,000 JLB 0 0 0 King & King Architects 0 06/01/22 09/29/21
21-0937FA Reconstruction 0-005-020 04/11/22 DONE DONE DONE 12/22/21 12/21/21 07/21/21 02/28/17 2,9,155,15,16 2,400,000 2,400,000 JLB 0 0 0 King & King Architects 0 / / 12/21/21
22-0527 Reconstruction 0-005-021 11/01/22 DONE DONE DONE 09/19/22 09/19/22 07/28/22 05/17/22 16 100,000 100,000 JLB 0 0 0 King & King Architects 0 / / 09/19/22
New Bus Garage:
- Reconstruction 5-013-002 / / / / 03/06/24 / / 16 0 0 JJH 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED