MAHOPAC CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-01-01-06
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Lakeview Elementary:
20-1192 Reconstruction 0-001-016 06/09/21 DONE DONE DONE 01/27/21 01/14/21 08/28/20 05/16/17 2,8,155,16 1,523,734 1,523,734 SLC 0 0 0 ECG Engineering, LLC 1,523,734 / / 01/14/21
21-0500 Reconstruction 0-001-017 03/29/22 DONE DONE DONE 10/08/21 10/08/21 09/21/21 05/21/19 2,4,8,9,10,155,15,16 4,239,000 4,239,000 SLC 0 0 0 Tetra Tech Architects and Eng 0 / / 10/08/21
Austin Road Elementary:
20-1193 Reconstruction 0-002-013 06/09/21 DONE DONE DONE 01/27/21 01/14/21 08/28/20 05/16/17 2,16 566,055 566,055 SLC 0 0 0 ECG Engineering, LLC 566,055 / / 01/14/21
21-0501 Reconstruction 0-002-014 03/29/22 DONE DONE DONE 10/08/21 10/08/21 09/21/21 05/21/19 2,4,8,9,10,155,15,16 2,044,000 2,044,000 SLC 0 0 0 Tetra Tech Architects and Eng 0 / / 10/08/21
22-1143 Reconstruction 0-002-015 04/03/23 DONE DONE DONE 12/05/22 11/29/22 10/04/22 05/21/19 15,16 220,000 220,000 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 11/29/22
Mahopac Falls Elem:
19-1012 Reconstruction 0-003-007 03/13/20 DONE DONE DONE 12/17/19 11/29/19 09/05/19 05/21/19 2,4,7,155,15,16 3,300,000 3,300,000 BMJ 0 0 0 Tetra Tech Architects and Eng 0 10/20/20 11/29/19
20-0510 Reconstruction 0-003-008 02/23/21 DONE DONE DONE 10/02/20 08/26/20 08/17/20 05/21/19 2,4,9,15,16 154,000 0 SLC 0 0 0 Tetra Tech Architects and Eng 0 / / 08/26/20
20-1194 Reconstruction 0-003-009 06/09/21 DONE DONE DONE 01/27/21 01/14/21 08/28/20 05/16/17 2,8,16 338,832 0 SLC 0 0 0 ECG Engineering, LLC 338,832 / / 01/14/21
21-0502 Reconstruction 0-003-010 03/29/22 DONE DONE DONE 10/08/21 10/08/21 09/21/21 05/21/19 2,4,8,9,10,155,15,16 1,624,000 0 SLC 0 0 0 Tetra Tech Architects and Eng 0 / / 10/08/21
22-1144 Reconstruction 0-003-011 04/03/23 DONE DONE DONE 12/05/22 11/29/22 10/04/22 05/21/19 15,16 220,000 0 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 11/29/22
Senior High:
19-1013 Reconstruction 0-004-019 03/13/20 DONE DONE DONE 12/17/19 11/29/19 09/05/19 05/21/19 2,4,7,155,15,16 1,560,000 1,560,000 BMJ 0 0 0 Tetra Tech Architects and Eng 0 10/20/20 11/29/19
20-0511 Reconstruction 0-004-020 02/23/21 DONE DONE DONE 10/02/20 08/26/20 08/17/20 05/21/19 2,4,8,9,10,14,155,15 16,900,000 16,900,000 SLC 0 0 0 Tetra Tech Architects and Eng 0 / / 08/26/20
20-1195 Reconstruction 0-004-021 06/09/21 DONE DONE DONE 01/27/21 01/14/21 08/28/20 05/16/17 2,16 724,809 724,809 SLC 0 0 0 ECG Engineering, LLC 724,809 / / 01/14/21
21-1542 Reconstruction 0-004-022 08/16/22 DONE DONE DONE 03/21/22 03/21/22 12/07/21 05/21/19 2,4,9 1,789,725 1,789,725 SLC 0 0 0 Tetra Tech Architects and Eng 0 / / 03/21/22
Fulmar Road Elementary:
19-1014 Reconstruction 0-005-015 03/13/20 DONE DONE DONE 12/17/19 11/29/19 09/05/19 05/21/19 2,4,7,155,15,16 2,460,000 2,460,000 BMJ 0 0 0 Tetra Tech Architects and Eng 0 10/20/20 11/29/19
20-1196 Reconstruction 0-005-016 06/09/21 DONE DONE DONE 01/27/21 01/14/21 08/28/20 05/16/17 2,16 158,862 158,862 SLC 0 0 0 ECG Engineering, LLC 158,862 / / 01/14/21
- PR Additions and Alterations 0-005-017 / / / / 09/21/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
21-0503 Additions and Alterations 0-005-017 03/29/22 DONE DONE DONE 10/08/21 10/08/21 09/21/21 05/21/19 02 - 16 2,669,000 2,614,340 SLC 0 0 0 Tetra Tech Architects and Eng 0 / / 10/08/21
22-1145 Reconstruction 0-005-018 04/03/23 DONE DONE DONE 12/05/22 11/30/22 10/04/22 05/21/19 15,16 220,000 220,000 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 11/30/22
Mahopac Middle School:
19-1015 Reconstruction 0-006-012 03/13/20 DONE DONE DONE 12/17/19 11/29/19 09/05/19 05/21/19 2,4,7,155,15,16 2,485,000 2,485,000 BMJ 0 0 0 Tetra Tech Architects and Eng 0 10/20/20 11/29/19
20-0512 Reconstruction 0-006-013 02/23/21 DONE DONE DONE 10/02/20 08/26/20 08/17/20 05/21/19 2,4,8,9,15,16 4,544,000 4,544,000 SLC 0 0 0 Tetra Tech Architects and Eng 0 / / 08/26/20
20-1197 Reconstruction 0-006-014 06/09/21 DONE DONE DONE 01/27/21 01/14/21 08/28/20 05/16/17 2,16 328,664 328,664 SLC 0 0 0 ECG Engineering, LLC 328,664 / / 01/14/21
21-0504 Reconstruction 0-006-015 03/29/22 DONE DONE DONE 10/08/21 10/08/21 09/21/21 05/21/19 2,4,8,9,10,155,15,16 6,345,000 6,345,000 SLC 0 0 0 Tetra Tech Architects and Eng 0 / / 10/08/21
District Office (see7-012):
20-1198 Reconstruction 1-012-001 06/09/21 DONE DONE DONE 01/27/21 01/14/21 / / 05/16/17 73,555 0 SLC 0 0 0 ECG Engineering, LLC 73,555 / / 01/14/21
Bus Garage:
20-0513 Reconstruction 5-010-009 02/23/21 DONE DONE DONE 10/02/20 08/26/20 08/17/20 05/21/19 155,16 632,000 632,000 SLC 0 0 0 Tetra Tech Architects and Eng 0 / / 08/26/20
20-1199 Reconstruction 5-010-010 06/09/21 DONE DONE DONE 01/27/21 01/14/21 08/28/20 05/16/17 2,155,16 22,906 22,906 SLC 0 0 0 ECG Engineering, LLC 22,906 / / 01/14/21
Mahopac Public Library:
21-1091 Reconstruction 6-017-004 06/22/22 DONE DONE DONE 01/12/22 01/11/21 12/10/21 06/07/22 2,4,7,8,9,155,16 3,154,283 0 SLC 0 0 0 Tetra Tech Architects and Eng 0 / / 01/11/21
23-0522XX Reconstruction 6-017-005 CANCELLED 09/20/23 09/18/23 07/07/23 08/24/23 2,4,155,15,16 0 0 MSK 0 0 0 Tetra Tech Architects and Eng 0 / / 09/18/23
XXMSHS Pump Station Demolition:
- XX Reconstruction 7-023-002 CANCELLED / / / / 02/03/21 / / 2,16 0 0 SLC 0 0 0 0 / / / /
Mahopac Pump House:
20-0514 New Construction 7-026-001 02/23/21 DONE DONE DONE 10/02/20 08/26/20 08/17/20 05/21/19 02 - 16 642,000 0 SLC 0 0 0 Tetra Tech Architects and Eng 0 / / 08/26/20
22-1146 Reconstruction 7-026-002 04/03/23 DONE DONE DONE 12/05/22 11/30/22 / / 05/21/19 15,16 15,000 0 JLB 0 0 0 Tetra Tech Architects and Eng 0 / / 11/30/22
District-Wide:
20-1539SB Reconstruction 7-999-002 DONE / / / / 04/05/21 / / 16 0 0 SLC 0 0 0 0 / / / /
21-0629 Reconstruction 7-999-002 03/16/22 DONE DONE DONE 11/03/21 11/02/21 04/05/21 05/21/19 16 1,702,421 1,702,421 SLC 0 0 0 Tetra Tech Architects and Eng 0 / / 11/02/21
- SB Reconstruction 7-999-BA2 DONE / / / / / / / / 16 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
CARMEL CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-01-02-06
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Kent Elementary School:
19-0316 Reconstruction 0-001-016 01/29/20 DONE DONE DONE 08/28/19 08/27/19 07/03/19 03/26/19 2,7,16 1,571,170 1,571,170 SLC 0 0 0 Sammel Architecture 0 09/11/20 08/27/19
20-0990 Reconstruction 0-001-017 04/26/21 DONE DONE DONE 12/18/20 12/07/20 08/20/19 03/26/19 2,4,8,9,10,155,15,16 104,174 104,174 SLC 0 0 0 Clark Patterson Lee 0 09/14/21 12/07/20
19-1677 Reconstruction 0-001-018 06/15/20 DONE DONE DONE 04/09/20 03/18/20 11/15/19 10/29/19 2,13,16 542,490 542,490 SLC 0 0 0 Clark Patterson Lee 542,490 05/26/22 03/18/20
Carmel High School:
20-0991 Reconstruction 0-003-022 04/26/21 DONE DONE DONE 12/18/20 12/07/20 07/03/19 03/26/19 2,7,16 432,185 432,185 SLC 0 0 0 Clark Patterson Lee 0 09/14/21 12/07/20
19-0250 Reconstruction 0-003-023 09/20/19 DONE DONE DONE 08/13/19 08/06/19 07/10/19 05/15/18 2,10,16 98,864 0 SLC 0 0 0 Sammel Architecture 0 08/03/20 08/06/19
19-0317 Reconstruction 0-003-024 01/29/20 DONE DONE DONE 08/28/19 08/27/19 08/20/19 03/26/19 2,4,7,8,9,10,155,15, 4,129,705 4,129,705 SLC 0 0 0 Sammel Architecture 0 12/04/20 08/27/19
19-1678 Reconstruction 0-003-025 06/15/20 DONE DONE DONE 04/09/20 03/18/20 11/15/19 10/29/19 2,13,155,16 2,374,894 2,374,894 SLC 0 0 0 Clark Patterson Lee 2,374,894 05/26/22 03/18/20
- Reconstruction 0-003-026 / / / / 07/07/20 / / 7 0 0 SLC 0 0 0 0 / / / /
22-1933FC Reconstruction 0-003-027 05/04/23 DONE DONE DONE 03/24/23 03/08/23 09/27/22 02/23/23 9,155,16 1,000,000 1,000,000 JLB 0 0 0 LaBella Associates 0 / / 03/08/23
- Reconstruction 0-003-028 / / / / 10/12/22 / / 2 0 0 SLC 0 0 0 0 / / / /
Kent Primary School:
19-0318 Reconstruction 0-004-015 01/29/20 DONE DONE DONE 08/28/19 08/27/19 07/03/19 03/26/19 2,7,16 1,988,051 1,988,051 SLC 0 0 0 Sammel Architecture 0 09/11/20 08/27/19
20-0992 Reconstruction 0-004-016 04/26/21 DONE DONE DONE 12/18/20 12/07/20 08/20/19 03/26/19 2,4,8,9,10,155,15,16 80,153 80,153 SLC 0 0 0 Clark Patterson Lee 0 09/14/21 12/07/20
19-1679 Reconstruction 0-004-017 06/15/20 DONE DONE DONE 04/09/20 03/18/20 11/15/19 10/29/19 2,13,155,16 1,024,123 1,024,123 SLC 0 0 0 Clark Patterson Lee 1,024,123 05/26/22 03/18/20
Industrial Arts Bldg:
19-1680 Reconstruction 0-006-006 06/15/20 DONE DONE DONE 04/09/20 03/18/20 11/15/19 10/29/19 13,155,16 37,438 37,438 SLC 0 0 0 Clark Patterson Lee 37,438 05/26/22 03/18/20
Fine Arts Bldg:
19-1681 Reconstruction 0-007-006 06/15/20 DONE DONE DONE 04/09/20 03/19/20 11/15/19 10/29/19 13,155,16 62,056 62,056 SLC 0 0 0 Clark Patterson Lee 62,056 05/26/22 03/19/20
20-1075 Reconstruction 0-007-007 04/27/21 DONE DONE DONE 12/30/20 12/16/20 07/07/20 06/09/20 9 104,816 104,816 SLC 0 0 0 Clark Patterson Lee 0 / / 12/16/20
George Fisher Middle School:
19-0319 Reconstruction 0-008-017 01/29/20 DONE DONE DONE 08/28/19 08/27/19 07/03/19 03/26/19 2,7,16 4,676,100 4,676,100 SLC 0 0 0 Sammel Architecture 0 09/11/20 08/27/19
20-0993 Reconstruction 0-008-018 04/26/21 DONE DONE DONE 12/18/20 12/07/20 08/20/19 03/26/19 2,4,8,9,10,155,15,16 947,045 947,045 SLC 0 0 0 Clark Patterson Lee 0 02/24/22 12/07/20
19-1682 Reconstruction 0-008-019 06/15/20 DONE DONE DONE 04/09/20 03/18/20 11/15/19 10/29/19 2,13,16 1,769,387 1,769,387 SLC 0 0 0 Clark Patterson Lee 1,769,387 05/26/22 03/18/20
23-1500 Reconstruction 0-008-020 UNREVIEWED 02/15/24 02/08/24 01/19/23 02/23/23 15 0 0 MSK 0 0 0 LaBella Associates 0 / / 02/08/24
Matthew Paterson Elementary:
19-0320 Reconstruction 0-010-012 01/29/20 DONE DONE DONE 08/28/19 08/27/19 07/03/19 03/26/19 2,7,16 2,593,110 2,593,110 SLC 0 0 0 Sammel Architecture 0 09/11/20 08/27/19
20-0994 Reconstruction 0-010-013 04/26/21 DONE DONE DONE 12/18/20 12/07/20 08/20/19 03/26/19 2,4,8,9,10,155,15,16 101,712 101,712 SLC 0 0 0 Clark Patterson Lee 0 09/14/21 12/07/20
19-1683 Reconstruction 0-010-014 06/15/20 DONE DONE DONE 04/09/20 03/18/20 11/15/19 10/29/19 13,16 544,753 544,753 SLC 0 0 0 Clark Patterson Lee 544,753 05/26/22 03/18/20
Administration Building:
19-1684 Reconstruction 1-002-009 06/15/20 DONE DONE DONE 04/09/20 03/18/20 11/15/19 10/29/19 16 36,466 0 SLC 0 0 0 Clark Patterson Lee 36,466 05/26/22 03/18/20
Transportation Office:
19-1685 Reconstruction 1-013-003 06/15/20 DONE DONE DONE 04/09/20 03/18/20 11/15/19 10/29/19 16 6,848 0 SLC 0 0 0 Clark Patterson Lee 6,848 05/26/22 03/18/20
Bus Garage:
19-1686 Reconstruction 5-005-008 06/15/20 DONE DONE DONE 04/08/20 03/18/20 11/15/19 10/29/19 16 8,394 0 SLC 0 0 0 Clark Patterson Lee 8,394 05/26/22 03/18/20
XXTransportationGarageAid77%.NoAid23:
19-1603PR New Construction 5-019-001 DONE 03/18/20 / / 06/06/19 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
19-1718XX New Construction 5-019-001 CANCELLED 05/05/20 03/27/20 06/06/19 03/26/19 02 - 16 10,925,736 10,925,736 SLC 0 0 0 Clark Patterson Lee 0 / / 03/27/20
XXPump House #2 - Canceled:
20-1031XX New Construction 7-020-001 CANCELLED 12/23/20 11/24/20 06/22/20 03/26/19 02 - 16 250,000 0 SLC 0 0 0 Clark Patterson Lee 0 / / 11/24/20
Guard Booth:
- New Construction 7-021-001 / / / / 08/19/20 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
District-Wide:
23-1275 Reconstruction 7-999-004 UNREVIEWED 12/22/23 12/22/23 01/19/23 05/16/23 0 0 MSK 0 0 0 LaBella Associates 0 / / 12/22/23
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
PUTNAM VALLEY CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-05-03-04
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Elementary School:
19-0671 Reconstruction 0-001-011 03/05/20 DONE DONE DONE 11/04/19 10/24/19 03/13/19 12/04/18 2,4,8,9,10,15,16 937,979 937,979 JSS 0 0 0 Kaeyer, Garment & Davidson 0 09/07/20 10/24/19
21-1466 Reconstruction 0-001-012 06/16/22 DONE DONE DONE 03/09/22 03/08/22 10/28/21 01/27/22 15,16 100,000 100,000 SLC 0 0 0 Kaeyer, Garment & Davidson 0 10/24/22 03/08/22
21-1681 Reconstruction 0-001-013 06/16/22 DONE DONE DONE 04/22/22 04/08/22 / / 05/17/22 2 50,000 50,000 SLC 0 0 0 Kaeyer, Garment & Davidson 0 08/03/23 04/08/22
Middle School:
19-0672 Additions and Alterations 0-004-015 03/05/20 DONE DONE DONE 11/04/19 10/24/19 03/13/19 12/04/18 02 - 16 8,018,273 7,377,074 JSS 0 0 0 Kaeyer, Garment & Davidson 0 11/08/21 10/24/19
20-1274 Reconstruction 0-004-016 03/30/21 DONE DONE DONE 02/10/21 02/04/21 01/19/21 12/04/18 2,4,8,9,10,155,15,16 611,593 0 JSS 0 0 0 Kaeyer, Garment & Davidson 0 08/31/21 02/04/21
Elementary (Modular):
21-1682 Reconstruction 0-007-002 06/16/22 DONE DONE DONE 04/22/22 04/08/22 12/06/21 05/17/22 2,8,9,15 200,000 200,000 SLC 0 0 0 Kaeyer, Garment & Davidson 0 08/03/23 04/08/22
Putnam Valley HS 2001 Gr9-12:
19-0673 Reconstruction 0-010-005 03/05/20 DONE DONE DONE 11/04/19 10/24/19 03/13/19 12/04/18 2,7,8,9,10,13,155,15 5,039,830 0 JSS 0 0 0 Kaeyer, Garment & Davidson 0 02/23/21 10/24/19
21-1683 Reconstruction 0-010-006 06/16/22 DONE DONE DONE 04/22/22 04/08/22 12/06/21 05/17/22 2,4,155,16 100,000 100,000 SLC 0 0 0 Kaeyer, Garment & Davidson 0 08/03/23 04/08/22
22-0123 Reconstruction 0-010-007 12/08/22 DONE DONE DONE 07/20/22 07/19/22 12/30/21 05/17/22 4,7 1,000,000 1,000,000 SLC 0 0 0 Kaeyer, Garment & Davidson 0 / / 07/19/22
Putnam Valley Transportation Garage:
21-1684 Reconstruction 5-012-003 06/16/22 DONE DONE DONE 04/22/22 04/08/22 12/06/21 05/17/22 10 25,000 25,000 SLC 0 0 0 Kaeyer, Garment & Davidson 0 08/03/23 04/08/22
Leased Admin Offices:
17-0123TQ Temporary Quarters 8-013-001 05/27/21 DONE DONE DONE 07/26/17 / / / / / / 280,000 0 JSS 0 0 0 Kaeyer, Garment & Davidson 0 03/04/21 / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
BREWSTER CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 48-06-01-06
last updated on 03/28/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Henry Wells MS(plus CV STARR IS):
18-1745 Reconstruction 0-001-025 08/07/19 DONE DONE DONE 03/28/19 03/22/19 01/19/18 11/28/17 2,155,16 875,000 875,000 MTM 0 0 0 Kaeyer, Garment & Davidson 0 08/29/19 03/22/19
21-1764PR Additions and Alterations 0-001-026 DONE 05/04/22 / / 03/02/22 / / 02 - 16 0 42,780,181 JJH 0 0 0 0 / / / /
23-1594 Additions and Alterations 0-001-026 UNREVIEWED 03/06/24 03/06/24 03/02/22 03/21/23 02 - 16 0 42,780,181 JJH 0 0 0 Fuller and D'Angelo 0 / / 03/06/24
- Reconstruction 0-001-027 / / / / 06/12/23 / / 2,4,7,8,9,155,15,16 0 0 JJH 0 0 0 0 / / / /
John F. Kennedy Elementary School:
19-1297 Reconstruction 0-003-012 02/27/20 DONE DONE DONE 01/29/20 01/27/20 01/16/20 05/21/19 8,9 90,000 90,000 BMJ 0 0 0 Kaeyer, Garment & Davidson 0 10/15/20 01/27/20
21-1765XX Additions and Alterations 0-003-013 CANCELLED 05/04/22 / / 03/02/22 / / 02 - 16 0 0 JJH 0 0 0 0 / / / /
- Reconstruction 0-003-014 / / / / 05/25/23 / / 2,4,7,8,9,155,15,16 0 0 JJH 0 0 0 0 / / / /
Brewster High School:
21-1766PR Additions and Alterations 0-004-018 DONE 05/04/22 / / 03/02/22 / / 02 - 16 0 40,093,123 JJH 0 0 0 0 / / / /
23-0813 Additions and Alterations 0-004-018 UNREVIEWED 10/27/23 10/19/23 03/02/22 03/21/23 02 - 16 0 39,573,778 JJH 0 0 0 Fuller and D'Angelo 0 / / 10/19/23
23-1001PR Additions and Alterations 0-004-019 DONE 11/15/23 / / 03/17/22 / / 02 - 16 0 757,666 JJH 0 0 0 0 / / / /
- Reconstruction 0-004-020 / / / / 06/12/23 / / 2,4,7,8,9,155,16 0 0 JJH 0 0 0 0 / / / /
Administration Bldg:
- Reconstruction 1-005-008 / / / / 06/12/23 / / 2 0 0 JJH 0 0 0 0 / / / /
Bus Garage Storage Trailer #17:
- PR New Construction 2-047-001 / / / / 08/08/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
Bus Garage:
- Reconstruction 5-006-011 / / / / 03/02/22 / / 2,8,9,155,16 0 0 JLB 0 0 0 0 / / / /
CVS Modular:
- PR New Construction 7-045-001 / / / / 02/15/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
21-1955 New Construction 7-045-001 05/10/23 DONE DONE DONE 06/10/22 06/09/22 02/15/22 05/17/22 02 - 16 1,170,152 0 JLB 0 0 0 Fuller and D'Angelo 0 / / 06/09/22
JFK Elementary:
- PR New Construction 7-046-001 / / / / 02/15/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
21-1956 New Construction 7-046-001 05/10/23 DONE DONE DONE 06/10/22 06/09/22 02/15/22 05/17/22 02 - 16 1,170,152 0 JLB 0 0 0 Fuller and D'Angelo 0 / / 06/09/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED