GILBOA CONESVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 54-08-01-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
21-0015 Reconstruction 0-001-012 10/05/21 DONE DONE DONE 07/08/21 07/06/21 02/24/21 01/13/21 2,13,15 250,000 250,000 SLC 0 0 0 IBI GROUP 0 09/13/22 07/06/21
Bus Garage Demolition:
20-1955 Reconstruction 5-007-003 08/09/21 DONE DONE DONE 06/30/21 06/29/21 02/24/21 03/10/21 2 72,100 72,100 SLC 0 0 0 IBI GROUP 0 12/31/21 06/29/21
New Bus Garage:
20-1921PR New Construction 5-014-001 UNREVIEWED 06/28/21 06/25/21 02/24/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / 06/25/21
20-1956 New Construction 5-014-001 08/09/21 DONE DONE DONE 06/30/21 06/29/21 02/24/21 03/10/21 02 - 16 2,610,000 2,610,000 SLC 0 0 0 IBI GROUP 0 / / 06/29/21
UV Disinfection Building:
21-0016 New Construction 7-015-001 10/05/21 DONE DONE DONE 07/08/21 07/06/21 04/30/21 01/13/21 02 - 16 37,000 0 SLC 0 0 0 IBI GROUP 0 09/13/22 07/06/21
District-Wide:
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 SLC 0 0 0 0 / / / /
Bus Garage Storage Trailer 1 (Swing):
21-1547XX New Construction 8-010-001 CANCELLED 03/23/22 01/25/22 10/06/20 / / 02 - 16 0 0 WLC 0 0 0 0 / / 01/25/22
Bus Garage Storage Trailer 2 (Swing):
21-1548XX New Construction 8-011-001 CANCELLED 03/23/22 01/25/22 10/06/20 / / 02 - 16 0 0 WLC 0 0 0 0 / / 01/25/22
Highway Dept. Garage (Const Swing):
21-1549SS New Construction 8-012-001 ADDENDUM REQ'D 03/23/22 01/25/22 10/19/20 / / 02 - 16 0 0 WLC 0 0 0 0 / / 01/25/22
Bus Garage Office Trailer (Swing):
21-1550SS New Construction 8-013-001 ADDENDUM REQ'D 03/23/22 01/25/22 10/20/20 / / 02 - 16 0 0 WLC 0 0 0 0 / / 01/25/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
JEFFERSON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 54-09-01-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Jefferson Central School:
21-0632 Reconstruction 0-001-012 01/27/22 DONE DONE DONE 11/03/21 11/02/21 07/21/21 05/18/21 14,16 90,750 90,750 SLC 0 0 0 Collins & Scoville Architects 0 06/26/23 11/02/21
23-1471 Reconstruction 0-001-013 UNREVIEWED 02/05/24 02/01/24 07/07/23 05/16/23 2,4,7,8,9,155,15,16 0 0 WLC 0 0 0 Collins & Scoville Architects 0 / / 02/01/24
- Reconstruction 0-001-014 / / / / 07/10/23 / / 2,4,7,8,9,155,15,16 0 0 WLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
MIDDLEBURGH CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 54-10-01-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Jr/Sr High School:
19-0676 Reconstruction 0-001-017 02/21/20 DONE DONE DONE 11/04/19 10/25/19 04/16/19 12/12/18 2,4,7,8,9,10,155,15, 9,529,472 9,529,472 SLC 0 0 0 SEI Design Group 0 06/14/22 10/25/19
19-1578 Reconstruction 0-001-018 04/30/20 DONE DONE DONE 03/16/20 03/09/20 01/30/20 05/21/19 155 100,000 100,000 JSS 0 0 0 SEI Design Group 0 06/30/20 03/09/20
20-1347 Reconstruction 0-001-019 03/05/21 DONE DONE DONE 02/24/21 02/02/21 01/05/21 06/17/20 2,8,9,16 100,000 100,000 JSS 0 0 0 SEI Design Group 0 06/29/21 02/02/21
22-1880 Reconstruction 0-001-020 04/28/23 DONE DONE DONE 03/20/23 03/16/23 10/11/22 05/17/22 8 100,000 100,000 JLB 0 0 0 SEI Design Group 0 06/29/23 03/16/23
- Reconstruction 0-001-021 / / / / 10/11/22 / / 2,4,9,15 0 0 SLC 0 0 0 0 / / / /
Elementary School:
19-0677 Reconstruction 0-007-010 02/21/20 DONE DONE DONE 11/04/19 10/25/19 04/16/19 12/12/18 2,4,7,8,9,10,155,15, 5,470,528 5,470,528 SLC 0 0 0 SEI Design Group 0 06/15/22 10/25/19
21-0113 Reconstruction 0-007-011 09/07/21 DONE DONE DONE 07/30/21 07/29/21 03/24/21 05/18/21 9 100,000 100,000 SLC 0 0 0 SEI Design Group 0 06/14/22 07/29/21
23-0554 Reconstruction 0-007-012 01/30/24 DONE DONE DONE 09/27/23 09/25/23 10/12/22 05/16/23 8 100,000 100,000 JLB 0 0 0 SEI Design Group 0 / / 09/25/23
District-Wide:
18-2028SB Reconstruction 7-999-001 DONE / / / / 05/31/19 / / 16 0 0 BMJ 0 0 0 0 / / / /
19-1579 Reconstruction 7-999-001 05/15/20 DONE DONE DONE 03/16/20 03/09/20 05/31/19 07/13/17 16 418,333 0 JSS 0 0 0 SEI Design Group 0 06/25/21 03/09/20
- SB Reconstruction 7-999-BA1 DONE / / / / / / / / 16 0 0 BMJ 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
COBLESKILL-RICHMONDVILLE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 54-11-02-06
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
George D. Ryder School:
20-1731 Reconstruction 0-002-012 07/26/21 DONE DONE DONE 05/18/21 05/14/21 03/12/21 02/03/21 2,7 1,000,000 1,000,000 SLC 0 0 0 Mosaic Associates 0 / / 05/14/21
21-0514 Reconstruction 0-002-013 10/05/22 DONE DONE DONE 10/13/21 10/12/21 03/23/21 02/03/21 2,4,7,8,9,10,155,15, 2,800,000 1,860,681 SLC 0 0 0 Mosaic Associates 0 / / 10/12/21
Golding Middle School(Jr/Sr):
19-1569 Reconstruction 0-003-013 06/23/20 DONE DONE DONE 03/13/20 03/06/20 06/25/19 05/14/19 2,155,15 50,000 50,000 JSS 0 0 0 Mosaic Associates 0 09/30/20 03/06/20
20-1732 Reconstruction 0-003-014 07/26/21 DONE DONE DONE 05/18/21 05/14/21 03/12/21 02/03/21 2,7 1,040,000 0 SLC 0 0 0 Mosaic Associates 0 / / 05/14/21
21-0515 Reconstruction 0-003-015 10/05/22 DONE DONE DONE 10/13/21 10/12/21 03/23/21 02/03/21 2,4,7,8,9,10 2,415,000 1,938,193 SLC 0 0 0 Mosaic Associates 0 / / 10/12/21
Main Building - Radez Elem.:
20-1733 Reconstruction 0-015-014 07/26/21 DONE DONE DONE 05/18/21 05/14/21 03/12/21 02/03/21 2,7 860,000 0 SLC 0 0 0 Mosaic Associates 0 / / 05/14/21
21-0516 Reconstruction 0-015-015 10/05/22 DONE DONE DONE 10/13/21 10/12/21 03/23/21 02/03/21 2,4,7,8,9,10,155,15, 2,650,000 1,205,273 SLC 0 0 0 Mosaic Associates 0 / / 10/12/21
High School:
21-0517 Reconstruction 0-018-008 10/05/22 DONE DONE DONE 10/13/21 10/12/21 03/23/21 02/03/21 7,8,9,10,13,155,15,1 3,400,000 3,400,000 SLC 0 0 0 Mosaic Associates 0 / / 10/12/21
Pump House:
21-1428 New Construction 7-025-001 04/26/22 DONE DONE DONE 03/04/22 03/02/22 01/19/22 02/03/21 02 - 16 176,250 0 FMJ 0 0 0 Mosaic Associates 0 / / 03/02/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
SCHOHARIE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 54-12-01-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Jr/Sr High School:
20-0518 Reconstruction 0-001-022 02/04/21 DONE DONE DONE 10/06/20 09/14/20 06/02/20 05/16/17 4,7,8,9,155,15,16 531,500 531,500 JSS 0 0 0 Mosaic Associates 0 12/01/21 09/14/20
22-1089 Reconstruction 0-001-023 03/31/23 DONE DONE DONE 11/29/22 11/23/22 10/04/22 05/17/22 2,8,9,16 5,723,000 5,723,000 WLC 0 0 0 Mosaic Associates 0 / / 11/23/22
22-0936 Reconstruction 0-001-024 02/02/23 DONE DONE DONE 11/09/22 11/04/22 10/12/22 05/17/22 2,9 100,000 100,000 WLC 0 0 0 Mosaic Associates 0 05/11/23 11/04/22
23-1192 Reconstruction 0-001-025 STARTED DONE DONE 12/14/23 12/07/23 08/16/23 05/17/22 2,16 2,887,270 0 WLC 0 0 0 Mosaic Associates 2,523,464 / / 12/07/23
23-1043 Reconstruction 0-001-026 UNREVIEWED 11/17/23 11/15/23 09/29/23 05/17/22 2,4,7,8,9,10,155,15, 0 0 WLC 0 0 0 Mosaic Associates 0 / / 11/15/23
23-1511 Reconstruction 0-001-027 03/19/24 DONE DONE DONE 02/16/24 02/14/24 01/25/24 05/16/23 8 100,000 100,000 WLC 0 0 0 Mosaic Associates 0 / / 02/14/24
Elementary School:
21-0735 Reconstruction 0-002-016 03/09/22 DONE DONE DONE 11/17/21 11/16/21 08/12/21 05/18/21 2 100,000 100,000 SLC 0 0 0 Mosaic Associates 0 05/15/22 11/16/21
22-1090 Reconstruction 0-002-017 03/31/23 DONE DONE DONE 11/29/22 11/23/22 11/10/22 05/17/22 16 200,000 200,000 WLC 0 0 0 Mosaic Associates 0 / / 11/23/22
23-0345 Reconstruction 0-002-018 05/16/23 DONE DONE DONE 08/29/23 08/24/23 04/19/23 05/16/23 2,7,155,15,16 316,229 316,229 WLC 0 0 0 Mosaic Associates 0 11/30/23 08/24/23
23-1044 Reconstruction 0-002-019 UNREVIEWED 11/17/23 11/15/23 09/29/23 05/17/22 2,4,7,8,9,10,155,15, 0 0 WLC 0 0 0 Mosaic Associates 0 / / 11/15/23
District-Wide:
- Reconstruction 7-999-002 / / / / 07/29/21 / / 16 0 0 SLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
SHARON SPRINGS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 54-14-01-04
last updated on 04/24/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Main Building:
19-1148 Reconstruction 0-001-022 02/07/20 DONE DONE DONE 01/03/20 12/30/19 12/04/19 05/21/19 4,8,9 100,000 100,000 SLC 0 0 0 Teitsch-Kent 0 06/12/20 12/30/19
20-0327 Reconstruction 0-001-023 11/03/20 DONE DONE DONE 09/02/20 08/19/20 06/23/20 06/09/20 4,8,9,10,155,15,16 100,000 100,000 SLC 0 0 0 Teitsch-Kent 0 06/28/21 08/19/20
21-0382 Reconstruction 0-001-024 01/28/22 DONE DONE DONE 09/20/21 09/20/21 06/25/21 05/18/21 2,4,8,9,155,15,16 100,000 100,000 SLC 0 0 0 Teitsch-Kent 0 06/24/22 09/20/21
- PR Additions and Alterations 0-001-025 / / / / 11/29/21 / / 02 - 16 0 0 SLC 0 0 0 0 / / / /
21-1829FA Additions and Alterations 0-001-025 10/04/22 DONE DONE DONE 05/18/22 05/12/22 11/23/21 12/14/21 02 - 16 502,421 0 SLC 0 0 0 Teitsch-Kent 0 / / 05/12/22
22-1092 Reconstruction 0-001-026 04/03/23 DONE DONE DONE 11/29/22 11/28/22 05/19/22 05/17/22 2,4,7,8,9,155,15,16 4,148,860 4,073,860 JLB 0 0 0 Teitsch-Kent 0 / / 11/28/22
22-0200 Reconstruction 0-001-027 08/02/22 DONE DONE DONE 08/01/22 08/01/22 05/23/22 05/17/22 8,9 100,000 100,000 SLC 0 0 0 Teitsch-Kent 0 10/12/23 08/01/22
22-0345 Reconstruction 0-001-028 09/12/22 DONE DONE DONE 08/26/22 08/25/22 08/10/22 08/09/22 4,9,16 175,000 175,000 SLC 0 0 0 Teitsch-Kent 0 10/12/23 08/25/22
23-1034 Reconstruction 0-001-029 12/20/23 DONE DONE DONE 11/16/23 11/16/23 05/24/23 05/16/23 8,9,13,16 100,000 100,000 JLB 0 0 0 Teitsch-Kent 0 / / 11/16/23
Maintenance Building:
- DB Discovered Building 3-007-001 / / / / 02/13/20 / / 0 0 SLC 0 0 0 0 / / / /
Bus Maintenance Facility see 0-002:
22-1093 Reconstruction 5-005-002 04/03/23 DONE DONE DONE 11/29/22 11/28/22 08/04/22 05/17/22 2,7,9,16 401,140 401,140 JLB 0 0 0 Teitsch-Kent 0 / / 11/28/22
Outdoor Pavilion:
22-0619FA New Construction 7-008-001 10/04/22 DONE DONE DONE 10/03/22 09/30/22 06/22/22 12/13/21 02 - 16 144,514 0 SLC 0 0 0 Teitsch-Kent 0 / / 09/30/22
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED