ODESSA-MONTOUR CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 55-01-01-04
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Odessa Elem.& High School:
19-1833   Reconstruction               0-001-018  08/21/20     DONE    DONE       DONE      06/10/20   05/28/20   07/30/19   05/21/19   2,4,7,8,9,10,155,15,  12,922,880    12,922,880  JSS             0           0           0 King & King Architects                  0        /  /                         05/28/20           
21-1613   Reconstruction               0-001-019  08/11/22     DONE    DONE       DONE      04/06/22   04/06/22   09/30/21   05/21/19   2,4,7,8,9,14,155,15,   3,000,000     3,000,000  SLC             0           0           0 King & King Architects                  0        /  /                         04/06/22           

          B.C. Cate Elementary:
19-1834   Reconstruction               0-004-011  08/21/20     DONE    DONE       DONE      06/10/20   05/28/20   07/30/19   05/21/19   8,16                   1,546,000     1,546,000  JSS             0           0           0 King & King Architects                  0      03/17/23                       05/28/20           
23-0889   Reconstruction               0-004-012  12/21/23     DONE    DONE       DONE      11/06/23   10/23/23   09/29/23   05/16/23   16                       100,000       100,000  JLB             0           0           0 Arcadis Architects, Engineers           0        /  /                         10/23/23           

          Bus Garage:
23-0138PR Reconstruction               5-003-012               DONE                         07/26/23     /  /     06/21/23     /  /     2,4,7,8,9,155,15,16            0             0  MSK             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WATKINS GLEN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 55-03-01-06
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School:
20-0937   Reconstruction               0-002-015  03/24/21     DONE    DONE       DONE      12/08/20   12/03/20   11/10/20   03/28/17   7                        218,130       218,130  SLC             0           0           0 Hunt Engineers,Architects & l           0      11/18/22                       12/03/20           
20-1251   Reconstruction               0-002-016  03/22/21     DONE    DONE       DONE      02/08/21   01/25/21   12/11/20   03/28/17   2,4,7,8,9              2,137,380     2,137,380  SLC             0           0           0 Hunt Engineers,Architects & l           0      11/18/22                       01/25/21           

          High School:
20-0938   Reconstruction               0-004-020  03/24/21     DONE    DONE       DONE      12/08/20   12/03/20   11/10/20   03/28/17   7                        901,755       901,755  SLC             0           0           0 Hunt Engineers,Architects & l           0      11/18/22                       12/03/20           
20-1252   Reconstruction               0-004-021  03/22/21     DONE    DONE       DONE      02/08/21   01/25/21   12/11/20   03/28/17   2,4,7,9,155,15,16      1,713,940     1,713,940  SLC             0           0           0 Hunt Engineers,Architects & l           0      11/18/22                       01/25/21           
22-1954   Reconstruction               0-004-022  09/22/23     DONE    DONE       DONE      03/29/23   03/27/23   03/09/23   03/28/17   2,9                      286,563       286,563  MSK             0           0           0 Hunt Engineers,Architects & l           0        /  /                         03/27/23           

          Shared Doc Storage(frmrly bus garage:
20-1253   Reconstruction               2-003-007  03/22/21     DONE    DONE       DONE      02/08/21   01/25/21   12/11/20   03/28/17   7,16                     184,750             0  SLC             0           0           0 Hunt Engineers,Architects & l           0      11/18/22                       01/25/21           

          2001 Bus Garage:
20-0939   Reconstruction               5-011-004  03/24/21     DONE    DONE       DONE      12/08/20   12/03/20   11/10/20   03/28/17   7                        334,100       334,100  SLC             0           0           0 Hunt Engineers,Architects & l           0      11/18/22                       12/03/20           
20-1254   Reconstruction               5-011-005  03/22/21     DONE    DONE       DONE      02/08/21   01/25/21   12/11/20   03/28/17   4,7,9,155,15,16          212,700       212,700  SLC             0           0           0 Hunt Engineers,Architects & l           0      11/18/22                       01/25/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES GREATER SOUTHERN TIER STATUS REPORT ON CAPITAL PROJECTS
District No.: 55-90-00-00
last updated on 04/25/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bush Campus-Bldg. 1:
20-0088   Reconstruction               0-001-026  11/10/20     DONE    DONE       DONE      07/21/20   06/22/20   05/15/20   06/02/20   8,9,10,155,15,16         385,368       385,368  JSS             0           0           0 Hunt Engineers,Architects & l           0      01/03/22                       06/22/20           
21-0192   Reconstruction               0-001-027  12/09/21     DONE    DONE       DONE      08/20/21   08/17/21   06/21/21   06/01/21   8,9,10,155,15,16         871,730       871,730  JLB             0           0           0 Hunt Engineers,Architects & l           0      10/01/22                       08/17/21           
  -       Reconstruction               0-001-028                                              /  /       /  /     03/12/24     /  /     4,8,9,10,13,155,15,1           0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Bush Campus-Bldg. 2:
21-0193   Reconstruction               0-002-011  12/09/21     DONE    DONE       DONE      08/20/21   08/17/21   06/21/21   06/01/21   4,7,8,9,155,15,16         82,125        82,125  JLB             0           0           0 Hunt Engineers,Architects & l           0      10/01/22                       08/17/21           

          Bush Campus-Bldg. 8:
19-0460   Reconstruction               0-008-008  02/12/20     DONE    DONE       DONE      09/20/19   09/12/19   08/07/19   08/27/19   2,4,8,9,10,155,15,16   1,094,480             0  JSS             0           0           0 Hunt Engineers,Architects & l           0        /  /                         09/12/19           

          Coopers Campus-Bldg. 1-Automotive:
20-0089   Reconstruction               0-037-007  11/10/20     DONE    DONE       DONE      07/21/20   06/22/20   05/15/20   06/02/20   155,16                    45,420        45,420  JSS             0           0           0 Hunt Engineers,Architects & l           0      01/03/22                       06/22/20           

          Wildwood Bldg#1-Admin/Dist Learng:
  -    PR Additions and Alterations    0-038-005                                              /  /       /  /     09/13/22     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-0884   Additions and Alterations    0-038-005  05/18/23     DONE    DONE       DONE      11/02/22   11/02/22   09/13/22   03/22/22   02 - 16                5,784,711     3,774,076  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/02/22           

          Wildwood Bldg#3-Cosmetol/Nursing:
19-1380   Reconstruction               0-041-006  02/12/20     DONE    DONE       DONE      02/06/20   01/15/20   12/18/19   08/27/19   7,8,9,155,15,16          230,661       230,661  JSS             0           0           0 Hunt Engineers,Architects & l           0        /  /                         01/15/20           
20-0090   Reconstruction               0-041-007  11/10/20     DONE    DONE       DONE      07/21/20   06/22/20   05/15/20   06/02/20   2,4,7,8,9,10,155,15,   1,208,071     1,208,071  JSS             0           0           0 Hunt Engineers,Architects & l           0      01/03/22                       06/22/20           
21-0194   Reconstruction               0-041-008  12/09/21     DONE    DONE       DONE      08/20/21   08/17/21   06/21/21   06/01/21   7,155,15,16               82,125        82,125  JLB             0           0           0 Hunt Engineers,Architects & l           0      10/01/22                       08/17/21           

          Coopers Campus-Bldg. 2-Heavy Equip.:
20-0091   Reconstruction               0-044-005  11/10/20     DONE    DONE       DONE      07/21/20   06/22/20   05/15/20   06/02/20   155,16                    45,420        45,420  JSS             0           0           0 Hunt Engineers,Architects & l           0      01/03/22                       06/22/20           

          Coopers Campus-Bldg. 3-Career Majors:
21-0195   Reconstruction               0-045-010  12/09/21     DONE    DONE       DONE      08/20/21   08/17/21   06/21/21   06/01/21   7,8,9,10,155,15,16       573,938       573,938  JLB             0           0           0 Hunt Engineers,Architects & l           0      10/01/22                       08/17/21           

          Coopers Bldg#4-Machine Shop:
  -    PR Additions and Alterations    0-046-006                                              /  /       /  /       /  /       /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-0885   Additions and Alterations    0-046-006  05/18/23     DONE    DONE       DONE      11/02/22   11/02/22     /  /     03/22/22   02 - 16                5,201,761     2,776,896  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/02/22           

          Coopers Bldg#5-Computer Graphics:
19-1379   Reconstruction               0-047-005  02/12/20     DONE    DONE       DONE      02/06/20   01/15/20   12/18/19   08/27/19   7,155,16                 163,591       163,591  JSS             0           0           0 Hunt Engineers,Architects & l           0        /  /                         01/15/20           

          Coopers Bldg#8:
19-0461   Reconstruction               0-050-005  02/12/20     DONE    DONE       DONE      09/20/19   09/12/19   08/07/19   08/27/19   7,155,16                 254,780             0  JSS             0           0           0 Hunt Engineers,Architects & l           0        /  /                         09/12/19           
21-0196   Reconstruction               0-050-006  12/09/21     DONE    DONE       DONE      08/20/21   08/17/21   06/21/21   06/01/21   2,8,9,10,15,16           417,332       417,332  JLB             0           0           0 Hunt Engineers,Architects & l           0      10/01/22                       08/17/21           

          Coopers-Modular Classroom:
20-0092   Reconstruction               0-052-003  11/10/20     DONE    DONE       DONE      07/21/20   06/22/20   05/15/20   06/02/20   155,16                    34,240        34,240  JSS             0           0           0 Hunt Engineers,Architects & l           0      01/03/22                       06/22/20           

          Wildwood Campus-Gym:
20-0055PR New Construction             0-070-001               DONE                         07/15/20     /  /     06/26/20     /  /     02 - 16                        0     1,327,500  JSS             0           0           0                                         0        /  /                           /  /             

          Coopers Campus-Gym:
20-0056PR New Construction             0-071-001               DONE                         07/15/20     /  /     06/26/20     /  /     02 - 16                        0     1,327,500  JSS             0           0           0                                         0        /  /                           /  /             

          Bush Campus-Bldg 13-Maint Storage:
  -    PR New Construction             2-069-001                                              /  /       /  /     03/05/20     /  /     02 - 16                        0             0  JSS             0           0           0                                         0        /  /                           /  /             
19-1208   New Construction             2-069-001               STARTED DONE       DONE      01/13/20   12/16/19   11/26/19   01/14/20   02 - 16                        0             0  JLB             0           0           0 Hunt Engineers,Architects & l           0        /  /                         12/16/19           

          Apiary Storage Shed:
22-1810DB Discovered Building          2-079-001  06/05/23     DONE    DONE       DONE      03/10/23   03/07/23   10/04/22     /  /                                    0             0  WLC             0           0           0                                         0        /  /                         03/07/23           

          Alpaca Barn:
22-1811DB Discovered Building          7-072-001  06/05/23     DONE    DONE       DONE      03/10/23   03/07/23   02/07/22     /  /                                    0             0  WLC             0           0           0                                         0        /  /                         03/07/23           
  -    DB Discovered Building          7-074-001                                              /  /       /  /     04/11/22     /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             

          District Wide:
19-0462   Reconstruction               7-999-011  02/12/20     DONE    DONE       DONE      09/20/19   09/12/19   08/07/19   08/27/19   16                       312,827             0  JSS             0           0           0 Hunt Engineers,Architects & l           0        /  /                         09/12/19           
20-0093   Reconstruction               7-999-012  11/10/20     DONE    DONE       DONE      07/21/20   06/22/20   05/15/20   06/02/20   16                       281,481             0  JSS             0           0           0 Hunt Engineers,Architects & l           0      01/03/22                       06/22/20           
21-0959   Reconstruction               7-999-013  06/21/22     DONE    DONE       DONE      12/27/21   12/23/21   10/13/21   06/01/21   16                     7,774,952     7,774,952  JLB             0           0           0 Hunt Engineers,Architects & l   7,078,802        /  /                         12/23/21           
22-0886   Reconstruction               7-999-014  05/18/23     DONE    DONE       DONE      11/02/22   11/02/22   09/13/22   03/22/22                          9,013,528     9,013,528  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/02/22           

          Langdon Plaza:
  -    TQ Temporary Quarters           8-076-001                                              /  /       /  /       /  /       /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Corning Community College:
22-0124TQ Temporary Quarters           8-077-001  11/17/22     DONE    DONE       DONE      07/20/22     /  /     05/25/22     /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             

          GST Audlt Education:
  -    TQ Temporary Quarters           8-078-001                                              /  /       /  /     08/08/22     /  /                                    0             0  JLB             0           0           0                                         0        /  /                           /  /             

          New Visions @ The Health Ed. Center:
  -    TQ Temporary Quarters           8-080-001                                              /  /       /  /       /  /       /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             

          New Visions @ Cowles Hall:
  -    TQ Temporary Quarters           8-081-001                                              /  /       /  /       /  /       /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED