ODESSA-MONTOUR CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 55-01-01-04
last updated on 04/25/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Odessa Elem.& High School:
19-1833 Reconstruction 0-001-018 08/21/20 DONE DONE DONE 06/10/20 05/28/20 07/30/19 05/21/19 2,4,7,8,9,10,155,15, 12,922,880 12,922,880 JSS 0 0 0 King & King Architects 0 / / 05/28/20
21-1613 Reconstruction 0-001-019 08/11/22 DONE DONE DONE 04/06/22 04/06/22 09/30/21 05/21/19 2,4,7,8,9,14,155,15, 3,000,000 3,000,000 SLC 0 0 0 King & King Architects 0 / / 04/06/22
B.C. Cate Elementary:
19-1834 Reconstruction 0-004-011 08/21/20 DONE DONE DONE 06/10/20 05/28/20 07/30/19 05/21/19 8,16 1,546,000 1,546,000 JSS 0 0 0 King & King Architects 0 03/17/23 05/28/20
23-0889 Reconstruction 0-004-012 12/21/23 DONE DONE DONE 11/06/23 10/23/23 09/29/23 05/16/23 16 100,000 100,000 JLB 0 0 0 Arcadis Architects, Engineers 0 / / 10/23/23
Bus Garage:
23-0138PR Reconstruction 5-003-012 DONE 07/26/23 / / 06/21/23 / / 2,4,7,8,9,155,15,16 0 0 MSK 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
WATKINS GLEN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 55-03-01-06
last updated on 04/25/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Elementary School:
20-0937 Reconstruction 0-002-015 03/24/21 DONE DONE DONE 12/08/20 12/03/20 11/10/20 03/28/17 7 218,130 218,130 SLC 0 0 0 Hunt Engineers,Architects & l 0 11/18/22 12/03/20
20-1251 Reconstruction 0-002-016 03/22/21 DONE DONE DONE 02/08/21 01/25/21 12/11/20 03/28/17 2,4,7,8,9 2,137,380 2,137,380 SLC 0 0 0 Hunt Engineers,Architects & l 0 11/18/22 01/25/21
High School:
20-0938 Reconstruction 0-004-020 03/24/21 DONE DONE DONE 12/08/20 12/03/20 11/10/20 03/28/17 7 901,755 901,755 SLC 0 0 0 Hunt Engineers,Architects & l 0 11/18/22 12/03/20
20-1252 Reconstruction 0-004-021 03/22/21 DONE DONE DONE 02/08/21 01/25/21 12/11/20 03/28/17 2,4,7,9,155,15,16 1,713,940 1,713,940 SLC 0 0 0 Hunt Engineers,Architects & l 0 11/18/22 01/25/21
22-1954 Reconstruction 0-004-022 09/22/23 DONE DONE DONE 03/29/23 03/27/23 03/09/23 03/28/17 2,9 286,563 286,563 MSK 0 0 0 Hunt Engineers,Architects & l 0 / / 03/27/23
Shared Doc Storage(frmrly bus garage:
20-1253 Reconstruction 2-003-007 03/22/21 DONE DONE DONE 02/08/21 01/25/21 12/11/20 03/28/17 7,16 184,750 0 SLC 0 0 0 Hunt Engineers,Architects & l 0 11/18/22 01/25/21
2001 Bus Garage:
20-0939 Reconstruction 5-011-004 03/24/21 DONE DONE DONE 12/08/20 12/03/20 11/10/20 03/28/17 7 334,100 334,100 SLC 0 0 0 Hunt Engineers,Architects & l 0 11/18/22 12/03/20
20-1254 Reconstruction 5-011-005 03/22/21 DONE DONE DONE 02/08/21 01/25/21 12/11/20 03/28/17 4,7,9,155,15,16 212,700 212,700 SLC 0 0 0 Hunt Engineers,Architects & l 0 11/18/22 01/25/21
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED
BOCES GREATER SOUTHERN TIER STATUS REPORT ON CAPITAL PROJECTS
District No.: 55-90-00-00
last updated on 04/25/24
REVIEW BUILDING NAME/ BLDG./ SED FINAL PROJECT REVIEW PLAN/SPEC PLAN/SPEC LETTER OF VOTER PROJECT ESTIMATED PRJ. RESCUE 1 RESCUE 2 EXCEL ARCHITECT/ENGINEER ENERGY PERF SUBS. COMPL. PARTIAL FINAL CERTIFICATE OF
No. PROJECT SCOPE PROJ. NO. APPROVAL Prj. Mgr. Const. Mech. COMPLETE RECEIVED INTENT AUTHOR. CSI CODES COST COST ALLOW. MGR. AID AID AID FIRM CONTRACT DATE CSC REC'D APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Bush Campus-Bldg. 1:
20-0088 Reconstruction 0-001-026 11/10/20 DONE DONE DONE 07/21/20 06/22/20 05/15/20 06/02/20 8,9,10,155,15,16 385,368 385,368 JSS 0 0 0 Hunt Engineers,Architects & l 0 01/03/22 06/22/20
21-0192 Reconstruction 0-001-027 12/09/21 DONE DONE DONE 08/20/21 08/17/21 06/21/21 06/01/21 8,9,10,155,15,16 871,730 871,730 JLB 0 0 0 Hunt Engineers,Architects & l 0 10/01/22 08/17/21
- Reconstruction 0-001-028 / / / / 03/12/24 / / 4,8,9,10,13,155,15,1 0 0 WLC 0 0 0 0 / / / /
Bush Campus-Bldg. 2:
21-0193 Reconstruction 0-002-011 12/09/21 DONE DONE DONE 08/20/21 08/17/21 06/21/21 06/01/21 4,7,8,9,155,15,16 82,125 82,125 JLB 0 0 0 Hunt Engineers,Architects & l 0 10/01/22 08/17/21
Bush Campus-Bldg. 8:
19-0460 Reconstruction 0-008-008 02/12/20 DONE DONE DONE 09/20/19 09/12/19 08/07/19 08/27/19 2,4,8,9,10,155,15,16 1,094,480 0 JSS 0 0 0 Hunt Engineers,Architects & l 0 / / 09/12/19
Coopers Campus-Bldg. 1-Automotive:
20-0089 Reconstruction 0-037-007 11/10/20 DONE DONE DONE 07/21/20 06/22/20 05/15/20 06/02/20 155,16 45,420 45,420 JSS 0 0 0 Hunt Engineers,Architects & l 0 01/03/22 06/22/20
Wildwood Bldg#1-Admin/Dist Learng:
- PR Additions and Alterations 0-038-005 / / / / 09/13/22 / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-0884 Additions and Alterations 0-038-005 05/18/23 DONE DONE DONE 11/02/22 11/02/22 09/13/22 03/22/22 02 - 16 5,784,711 3,774,076 WLC 0 0 0 Hunt Engineers,Architects & l 0 / / 11/02/22
Wildwood Bldg#3-Cosmetol/Nursing:
19-1380 Reconstruction 0-041-006 02/12/20 DONE DONE DONE 02/06/20 01/15/20 12/18/19 08/27/19 7,8,9,155,15,16 230,661 230,661 JSS 0 0 0 Hunt Engineers,Architects & l 0 / / 01/15/20
20-0090 Reconstruction 0-041-007 11/10/20 DONE DONE DONE 07/21/20 06/22/20 05/15/20 06/02/20 2,4,7,8,9,10,155,15, 1,208,071 1,208,071 JSS 0 0 0 Hunt Engineers,Architects & l 0 01/03/22 06/22/20
21-0194 Reconstruction 0-041-008 12/09/21 DONE DONE DONE 08/20/21 08/17/21 06/21/21 06/01/21 7,155,15,16 82,125 82,125 JLB 0 0 0 Hunt Engineers,Architects & l 0 10/01/22 08/17/21
Coopers Campus-Bldg. 2-Heavy Equip.:
20-0091 Reconstruction 0-044-005 11/10/20 DONE DONE DONE 07/21/20 06/22/20 05/15/20 06/02/20 155,16 45,420 45,420 JSS 0 0 0 Hunt Engineers,Architects & l 0 01/03/22 06/22/20
Coopers Campus-Bldg. 3-Career Majors:
21-0195 Reconstruction 0-045-010 12/09/21 DONE DONE DONE 08/20/21 08/17/21 06/21/21 06/01/21 7,8,9,10,155,15,16 573,938 573,938 JLB 0 0 0 Hunt Engineers,Architects & l 0 10/01/22 08/17/21
Coopers Bldg#4-Machine Shop:
- PR Additions and Alterations 0-046-006 / / / / / / / / 02 - 16 0 0 JLB 0 0 0 0 / / / /
22-0885 Additions and Alterations 0-046-006 05/18/23 DONE DONE DONE 11/02/22 11/02/22 / / 03/22/22 02 - 16 5,201,761 2,776,896 WLC 0 0 0 Hunt Engineers,Architects & l 0 / / 11/02/22
Coopers Bldg#5-Computer Graphics:
19-1379 Reconstruction 0-047-005 02/12/20 DONE DONE DONE 02/06/20 01/15/20 12/18/19 08/27/19 7,155,16 163,591 163,591 JSS 0 0 0 Hunt Engineers,Architects & l 0 / / 01/15/20
Coopers Bldg#8:
19-0461 Reconstruction 0-050-005 02/12/20 DONE DONE DONE 09/20/19 09/12/19 08/07/19 08/27/19 7,155,16 254,780 0 JSS 0 0 0 Hunt Engineers,Architects & l 0 / / 09/12/19
21-0196 Reconstruction 0-050-006 12/09/21 DONE DONE DONE 08/20/21 08/17/21 06/21/21 06/01/21 2,8,9,10,15,16 417,332 417,332 JLB 0 0 0 Hunt Engineers,Architects & l 0 10/01/22 08/17/21
Coopers-Modular Classroom:
20-0092 Reconstruction 0-052-003 11/10/20 DONE DONE DONE 07/21/20 06/22/20 05/15/20 06/02/20 155,16 34,240 34,240 JSS 0 0 0 Hunt Engineers,Architects & l 0 01/03/22 06/22/20
Wildwood Campus-Gym:
20-0055PR New Construction 0-070-001 DONE 07/15/20 / / 06/26/20 / / 02 - 16 0 1,327,500 JSS 0 0 0 0 / / / /
Coopers Campus-Gym:
20-0056PR New Construction 0-071-001 DONE 07/15/20 / / 06/26/20 / / 02 - 16 0 1,327,500 JSS 0 0 0 0 / / / /
Bush Campus-Bldg 13-Maint Storage:
- PR New Construction 2-069-001 / / / / 03/05/20 / / 02 - 16 0 0 JSS 0 0 0 0 / / / /
19-1208 New Construction 2-069-001 STARTED DONE DONE 01/13/20 12/16/19 11/26/19 01/14/20 02 - 16 0 0 JLB 0 0 0 Hunt Engineers,Architects & l 0 / / 12/16/19
Apiary Storage Shed:
22-1810DB Discovered Building 2-079-001 06/05/23 DONE DONE DONE 03/10/23 03/07/23 10/04/22 / / 0 0 WLC 0 0 0 0 / / 03/07/23
Alpaca Barn:
22-1811DB Discovered Building 7-072-001 06/05/23 DONE DONE DONE 03/10/23 03/07/23 02/07/22 / / 0 0 WLC 0 0 0 0 / / 03/07/23
- DB Discovered Building 7-074-001 / / / / 04/11/22 / / 0 0 JLB 0 0 0 0 / / / /
District Wide:
19-0462 Reconstruction 7-999-011 02/12/20 DONE DONE DONE 09/20/19 09/12/19 08/07/19 08/27/19 16 312,827 0 JSS 0 0 0 Hunt Engineers,Architects & l 0 / / 09/12/19
20-0093 Reconstruction 7-999-012 11/10/20 DONE DONE DONE 07/21/20 06/22/20 05/15/20 06/02/20 16 281,481 0 JSS 0 0 0 Hunt Engineers,Architects & l 0 01/03/22 06/22/20
21-0959 Reconstruction 7-999-013 06/21/22 DONE DONE DONE 12/27/21 12/23/21 10/13/21 06/01/21 16 7,774,952 7,774,952 JLB 0 0 0 Hunt Engineers,Architects & l 7,078,802 / / 12/23/21
22-0886 Reconstruction 7-999-014 05/18/23 DONE DONE DONE 11/02/22 11/02/22 09/13/22 03/22/22 9,013,528 9,013,528 WLC 0 0 0 Hunt Engineers,Architects & l 0 / / 11/02/22
Langdon Plaza:
- TQ Temporary Quarters 8-076-001 / / / / / / / / 0 0 JLB 0 0 0 0 / / / /
Corning Community College:
22-0124TQ Temporary Quarters 8-077-001 11/17/22 DONE DONE DONE 07/20/22 / / 05/25/22 / / 0 0 JLB 0 0 0 0 / / / /
GST Audlt Education:
- TQ Temporary Quarters 8-078-001 / / / / 08/08/22 / / 0 0 JLB 0 0 0 0 / / / /
New Visions @ The Health Ed. Center:
- TQ Temporary Quarters 8-080-001 / / / / / / / / 0 0 WLC 0 0 0 0 / / / /
New Visions @ Cowles Hall:
- TQ Temporary Quarters 8-081-001 / / / / / / / / 0 0 WLC 0 0 0 0 / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED UNREVIEWED = FINAL REVIEW NOT STARTED