Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 04/19/24 at 06:55:13




SOUTH SENECA CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 56-05-01-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Ovid Jr/Sr High School:
21-1499   Reconstruction               0-001-019  08/11/21     DONE    DONE       DONE      03/11/22   03/11/22   06/02/21   05/19/21   15                       170,000       170,000  FMJ             0           0           0 Hunt Engineers,Architects & l           0      02/18/22                       03/11/22           
21-1255   Reconstruction               0-001-020  03/02/22     DONE    DONE       DONE      02/10/22   02/08/22   01/25/22   05/18/21   16                       100,000       100,000  SLC             0           0           0 Wendel Companies                        0      06/30/22                       02/08/22           
  -       Reconstruction               0-001-021                                              /  /       /  /     05/03/22     /  /     155,16                         0             0  SLC             0           0           0                                         0        /  /                           /  /             
23-0009   Reconstruction               0-001-022  02/05/24     DONE    DONE       DONE      07/05/23   07/03/23   01/17/23   12/13/22   2,4,7,8,9,155,15,16    3,550,119     3,550,119  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         07/03/23           
23-0464   Reconstruction               0-001-023  10/31/23     DONE    DONE       DONE      09/13/23   09/11/23   07/11/23   05/16/23   2,10,15,16               100,000       100,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         09/11/23           

          Interlaken Elementary:
19-1183   Reconstruction               0-004-020  02/20/20     DONE    DONE       DONE      01/08/20   12/13/19   10/10/19   05/21/19   16                       100,000       100,000  SLC             0           0           0 Wendel Companies                        0      06/30/20                       12/13/19           
20-1060   Reconstruction               0-004-021  01/30/21     DONE    DONE       DONE      12/29/20   12/22/20   10/19/20   06/16/20   16                       100,000       100,000  SLC             0           0           0 Wendel Companies                        0      08/30/20                       12/22/20           
22-0813FC Reconstruction               0-004-022  01/17/23     DONE    DONE       DONE      10/26/22   10/20/22   05/03/22   10/12/22   7,155,16               2,096,200     2,096,200  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         10/20/22           
21-1926   Reconstruction               0-004-023  11/22/22     DONE    DONE       DONE      06/06/22   06/03/22   05/03/22   05/17/22   10                       100,000       100,000  WLC             0           0           0 Hunt Engineers,Architects & l           0      06/20/23                       06/03/22           
23-0010   Reconstruction               0-004-024  02/05/24     DONE    DONE       DONE      07/05/23   07/03/23   01/17/23   12/13/22   2,7,8,9,15,16          3,048,419     3,048,419  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         07/03/23           

          Bus Garage at Ovid:
23-0011   Reconstruction               5-002-009  02/05/24     DONE    DONE       DONE      07/05/23   07/03/23   01/17/23   12/13/22   2,4,7,8,9,155,15,16       70,000        70,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         07/03/23           

          Transportation Facility:
23-0012   New Construction             5-014-001  02/05/24     DONE    DONE       DONE      07/05/23   07/03/23   01/17/23   12/13/22   02 - 16               12,660,434    12,660,434  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         07/03/23           
23-1323PR New Construction             5-014-001               DONE                         01/04/24     /  /     01/17/23   12/13/22   02 - 16               12,660,434             0  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ROMULUS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 56-06-03-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Romulus Central School:
21-0621SB Reconstruction               0-002-022               DONE                           /  /       /  /     11/01/21     /  /     16                             0    22,430,166  JLB             0           0           0                                         0        /  /                           /  /             
21-2018   Reconstruction               0-002-022  12/01/22     DONE    DONE       DONE      06/22/22   06/21/22   11/01/21   11/04/14   16                       289,852       289,852  WLC             0           0           0 SWBR Architects P.C.                    0        /  /                         06/21/22           
23-0017   Additions and Alterations    0-002-023  01/25/24     DONE    DONE       DONE      07/05/23   07/05/23   08/17/22   10/18/22   02 - 16               13,000,000    11,358,500  WLC             0           0           0 SWBR Architects P.C.                    0        /  /                         07/05/23           
23-1423XX Additions and Alterations    0-002-023                         CANCELLED          01/25/24   12/11/23   08/17/22     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                         12/11/23           
  -    SB Reconstruction               0-002-BA2               DONE                           /  /       /  /       /  /       /  /     16                             0             0  JLB             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               0-002-BA3               DONE                           /  /       /  /       /  /       /  /     13,16                          0             0  JLB             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




SENECA FALLS CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 56-07-01-06
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cady Stanton Elementary:
18-1782   Reconstruction               0-001-018  10/04/19     DONE    DONE       DONE      04/04/19   03/21/19   10/12/17   12/19/17   2,8,9,10,155,15,16       996,000       996,000  BMJ             0           0           0 King & King Architects                  0      11/08/21                       03/21/19           
  -       Reconstruction               0-001-019                                              /  /       /  /     09/28/23     /  /     2,4,7,8,9,155,15,16            0             0  MSK             0           0           0                                         0        /  /                           /  /             

          Frank M. Knight Elementary:
18-1783   Reconstruction               0-002-017  10/04/19     DONE    DONE       DONE      04/04/19   03/21/19   10/12/17   12/19/17   155,16                   188,000       188,000  BMJ             0           0           0 King & King Architects                  0      11/08/21                       03/21/19           
  -       Reconstruction               0-002-018                                              /  /       /  /     09/28/23     /  /     2,4,7,8,9,155,15,16            0             0  MSK             0           0           0                                         0        /  /                           /  /             

          Mynderse Jr/Sr High School:
18-1784   Reconstruction               0-005-021  10/04/19     DONE    DONE       DONE      04/04/19   03/21/19   10/12/17   12/19/17   2,8,9,10,155,15,16     5,742,000     5,742,000  BMJ             0           0           0 King & King Architects                  0      11/08/21                       03/21/19           
  -       Reconstruction               0-005-022                                              /  /       /  /     09/28/23     /  /     2,4,7,8,9,14,155,15,           0             0  MSK             0           0           0                                         0        /  /                           /  /             

          XXBus Garage Demolition 2018:
18-1785   Reconstruction               5-007-006  10/04/19     DONE    DONE       DONE      04/04/19   03/21/19   06/13/18   12/19/17                            272,400       272,400  BMJ             0           0           0 King & King Architects                  0      11/08/21                       03/21/19           

          Bus Garage Facility:
18-1786   New Construction             5-016-001  10/04/19     DONE    DONE       DONE      04/04/19   03/21/19   10/12/17   12/19/17   02 - 16                6,751,600     6,751,600  BMJ             0           0           0 King & King Architects                  0      04/20/21                       03/21/19           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WATERLOO CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 56-10-06-06
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          LaFayette Intermediate:
18-1705   Reconstruction               0-003-017  08/05/19     DONE    DONE       DONE      03/25/19   03/04/19   01/16/19   12/04/14   2,7,8,9,10,155,15,16   2,654,409     2,654,409  BMJ             0           0     250,000 SEI Design Group                        0      10/14/21                       03/04/19           
18-2201   Reconstruction               0-003-018  07/10/19     DONE    DONE       DONE      06/26/19   06/25/19   06/25/19   12/04/14   7                        245,438       245,438  BMJ             0           0           0 SEI Design Group                        0      09/27/19                       06/25/19           
23-0776   Reconstruction               0-003-019               UNREVIEWED
                                                                       ADD. REQ'D STARTED   10/23/23   10/17/23   06/05/23   02/07/23   2,4,8,9,155,15,16              0             0  JJH             0           0           0 SEI Design Group                        0        /  /                         10/17/23           

          Skoi Yase Elementary:
18-1704   Reconstruction               0-008-017  08/05/19     DONE    DONE       DONE      03/25/19   03/04/19   01/16/19   12/04/14   2,7,8,9,10,155,15,16   1,842,346     1,842,346  BMJ             0           0     165,000 SEI Design Group                        0      09/22/22                       03/04/19           
23-0777   Reconstruction               0-008-018               UNREVIEWED
                                                                       ADD. REQ'D STARTED   10/23/23   10/17/23   06/05/23   02/07/23   2,4,8,9,155,15,16              0             0  JJH             0           0           0 SEI Design Group                        0        /  /                         10/17/23           

          Middle & High School:
18-1706   Reconstruction               0-011-016  08/05/19     DONE    DONE       DONE      03/25/19   03/04/19   01/16/19   12/04/14   2,4,7,8,9,10,155,15,   2,978,970     2,978,970  BMJ             0           0     265,000 SEI Design Group                        0      11/30/21                       03/04/19           
20-1486   Reconstruction               0-011-017  06/02/21     DONE    DONE       DONE      03/25/21   03/24/21   02/21/20   12/08/20   2,16                   3,706,000     3,706,000  JSS             0           0           0 SEI Design Group                        0        /  /                         03/24/21           
21-0146   Reconstruction               0-011-018  09/23/21     DONE    DONE       DONE      08/06/21   08/05/21   04/16/21   12/08/20   2,4,7,8,9,10,14,155,  19,103,976    19,103,976  JLB             0           0           0 SEI Design Group                        0        /  /                         08/05/21           
22-2161   Reconstruction               0-011-019  09/06/23     DONE    DONE       DONE      05/08/23   05/05/23   03/01/23   12/08/20   2,155,15,16            1,912,000     1,912,000  JJH             0           0           0 SEI Design Group                        0        /  /                         05/05/23           
23-0778   Reconstruction               0-011-020               UNREVIEWED
                                                                       ADD. REQ'D STARTED   10/23/23   10/17/23   06/05/23   02/07/23   2,4,10,155,15,16               0             0  JJH             0           0           0 SEI Design Group                        0        /  /                         10/17/23           

          Storage Barn:
18-1984   New Construction             2-022-001  06/24/19     DONE    DONE       DONE      05/20/19   05/09/19   04/09/19   05/06/19   02 - 16                   70,000             0  BMJ             0           0           0 SEI Design Group                        0        /  /                         05/09/19           

          High School Storage Barn:
18-1985   New Construction             2-023-001  06/24/19     DONE    DONE       DONE      05/20/19   05/09/19   04/09/19   05/06/19   02 - 16                   70,000             0  BMJ             0           0           0 SEI Design Group                        0        /  /                         05/09/19           

          Bus Garage/District Office:
18-1707   Reconstruction               5-005-009  08/05/19     DONE    DONE       DONE      03/25/19   03/04/19   01/16/19   12/04/14   7,9,155,16               389,076             0  BMJ             0           0           0 SEI Design Group                        0        /  /                         03/04/19           

          Bus Garage/Salt Barn:
18-1708   Reconstruction               5-017-004  08/05/19     DONE    DONE       DONE      03/25/19   03/04/19     /  /     12/04/14   8,155,15,16              325,167             0  BMJ             0           0           0 SEI Design Group                        0        /  /                         03/04/19           
23-0779   Reconstruction               5-017-005               UNREVIEWED
                                                                       ADD. REQ'D STARTED   10/23/23   10/17/23   06/05/23   02/07/23   2,13,15,16                     0             0  JJH             0           0           0 SEI Design Group                        0        /  /                         10/17/23           

          49553 Averdi:
20-1925TQ Temporary Quarters           8-024-001  10/26/21     DONE    DONE       DONE      06/30/21   06/30/21   09/03/20     /  /                                    0             0  JLB             0           0           0                                         0        /  /                         06/30/21           

          49653 Averdi:
20-1926TQ Temporary Quarters           8-025-001  10/26/21     DONE    DONE       DONE      06/30/21   06/30/21   09/03/20     /  /                                    0             0  JLB             0           0           0                                         0        /  /                         06/30/21           

          49631 Averdi:
20-1927TQ Temporary Quarters           8-026-001  10/26/21     DONE    DONE       DONE      06/30/21   06/30/21   09/03/20     /  /                                    0             0  JLB             0           0           0                                         0        /  /                         06/30/21           

          49630 Averdi:
20-1928TQ Temporary Quarters           8-027-001  10/26/21     DONE    DONE       DONE      06/30/21   06/30/21   09/03/20     /  /                                    0             0  JLB             0           0           0                                         0        /  /                         06/30/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED