TOMPKINS COUNTY

TOMPKINS COUNTY

DRYDEN 610301
GEORGE JR REPU 610327
GROTON 610501
ITHACA 610600
LANSING 610801
NEWFIELD 610901
TRUMANSBURG 611001
TOMPKINS BOCES 619000
















Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 04/19/24 at 06:55:14




DRYDEN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-03-01-06
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Cassavant Elementary:
19-0391   Reconstruction               0-001-010  12/16/19     DONE    DONE       DONE      09/09/19   08/28/19   05/20/19   05/21/19   8,9                      100,000       100,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      06/25/20                       08/28/19           
21-0323   Reconstruction               0-001-011  11/15/21     DONE    DONE       DONE      09/13/21   09/09/21   06/01/21   05/18/21   8                        100,000       100,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      06/22/22                       09/09/21           
  -       Reconstruction               0-001-012                                              /  /       /  /     04/25/22     /  /     7,15                           0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Dryden Elementary:
20-0443   Reconstruction               0-003-027  01/08/21     DONE    DONE       DONE      09/24/20   09/22/20   04/07/20   06/09/20   8                        100,000       100,000  JLB             0           0           0 Hunt Engineers,Architects & l           0      06/25/21                       09/22/20           
21-0240   Reconstruction               0-003-028  02/08/22     DONE    DONE       DONE      08/26/21   08/26/21   06/01/21   03/28/17   2,16                   1,140,500     1,140,500  SLC             0           0           0 Hunt Engineers,Architects & l           0      09/20/23                       08/26/21           
22-0031   Reconstruction               0-003-029  02/07/23     DONE    DONE       DONE      07/05/22   07/05/22   04/25/22   04/05/22   7,155,15,16            1,750,000     1,750,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         07/05/22           
22-1071   Reconstruction               0-003-030  02/01/23     DONE    DONE       DONE      11/28/22   11/21/22   04/25/22   04/05/22   2,7,8,9,10,155,15,16   5,822,000     5,822,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/21/22           

          Freeville Elementary:
18-1634   Reconstruction               0-004-014  05/23/19     DONE    DONE       DONE      03/14/19   03/01/19   02/04/19   03/28/17   155                      285,000       285,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      02/06/20                       03/01/19           
22-0032   Reconstruction               0-004-015  02/07/23     DONE    DONE       DONE      07/05/22   07/05/22   04/25/22   04/05/22   2,7,155,15,16            500,000       500,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         07/05/22           
22-0096   Reconstruction               0-004-016  10/24/22     DONE    DONE       DONE      07/15/22   07/13/22   04/25/22   05/17/22   4,7,8,9,155,16           100,000       100,000  WLC             0           0           0 Hunt Engineers,Architects & l           0      06/21/23                       07/13/22           
22-1754   Reconstruction               0-004-017  05/31/23     DONE    DONE       DONE      02/27/23   02/23/23   12/01/22   04/05/22   7                        450,000       450,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         02/23/23           
23-0551   Reconstruction               0-004-018  11/08/23     DONE    DONE       DONE      09/25/23   09/19/23   07/25/23   05/22/23   2,15,16                  100,000       100,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         09/19/23           

          Junior/Senior High School:
19-1552   Reconstruction               0-005-028  06/01/20     DONE    DONE       DONE      03/09/20   02/21/20   12/17/19   12/10/19   2,4,8,9,155,15,16      2,500,000     2,500,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      01/05/21                       02/21/20           
21-0241   Reconstruction               0-005-029  02/08/22     DONE    DONE       DONE      08/26/21   08/26/21   06/01/21   03/28/17   2,8,9,155,15,16        1,613,438     1,613,438  SLC             0           0           0 Hunt Engineers,Architects & l           0      09/20/23                       08/26/21           
22-0033   Reconstruction               0-005-030  02/07/23     DONE    DONE       DONE      07/05/22   07/05/22   04/25/22   04/05/22   7,155,15,16            2,207,000     2,207,000  WLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         07/05/22           

          Maint Facility (To be Demo'd):
20-0500   Reconstruction               2-010-004  10/07/20     DONE    DONE       DONE      09/30/20   09/30/20   02/09/18   03/28/17   2                         70,000             0  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         09/30/20           

          Football Storage:
19-1816DB Discovered Building          2-021-001                       ADDENDUM REQ'D       06/05/20   06/05/20   05/16/19     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                         06/05/20           

          Bike Storage:
19-1817DB Discovered Building          2-022-001                       ADDENDUM REQ'D       06/05/20   06/05/20   05/16/19     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                         06/05/20           

          Track Storage:
19-1818DB Discovered Building          2-023-001                       ADDENDUM REQ'D       06/05/20   06/05/20   05/16/19     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                         06/05/20           

          A-Verdi Athletic Bike Storage:
  -    DB Discovered Building          2-025-001                                              /  /       /  /       /  /       /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             

          A-Verdi Athletic Storage:
  -    DB Discovered Building          2-026-001                                              /  /       /  /       /  /       /  /                                    0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Residential House Demolition:
22-0034DB Discovered Building          7-024-001               UNREVIEWED
                                                                       DONE       DONE      07/11/22   07/05/22   04/26/22     /  /                                    0             0  WLC             0           0           0                                         0        /  /                         07/05/22           

          District-Wide:
21-0593SB Reconstruction               7-999-005               DONE                           /  /       /  /     10/27/21     /  /     16                             0             0  SLC             0           0           0                                         0        /  /                           /  /             
21-0736   Reconstruction               7-999-005  02/08/22     DONE    DONE       DONE      11/17/21   11/16/21   10/27/21   11/04/14   16                       491,000             0  SLC             0           0           0 Hunt Engineers,Architects & l           0        /  /                         11/16/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GROTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-05-01-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Junior/Senior High School:
21-0731   Reconstruction               0-002-020  03/29/22     DONE    DONE       DONE      11/16/21   11/16/21   08/17/21   12/07/21   2,155,15               5,162,500     5,162,500  SLC             0           0           0 Ashley McGraw                           0      10/03/22                       11/16/21           
22-0515   Reconstruction               0-002-021  01/10/23     DONE    DONE       DONE      09/16/22   09/16/22   07/19/22   12/07/21   2,7,155,15,16            900,700       900,700  WLC             0           0           0 Ashley McGraw                           0      09/18/23                       09/16/22           
  -       Reconstruction               0-002-022                                              /  /       /  /     06/15/23     /  /     7,13                           0             0  WLC             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-002-023                                              /  /       /  /     08/21/23     /  /     4,7,8,9,15                     0             0  WLC             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-002-024                                              /  /       /  /     02/29/24     /  /     8                              0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Elementary School:
21-0732   Reconstruction               0-003-014  03/29/22     DONE    DONE       DONE      11/16/21   11/12/21   08/17/21   12/07/21   2,155,15               1,525,500     1,525,500  SLC             0           0           0 Ashley McGraw                           0      10/03/22                       11/12/21           
22-0516   Reconstruction               0-003-015  01/10/23     DONE    DONE       DONE      09/16/22   09/16/22   07/19/22   12/07/21   4,8,9,155,15,16        1,566,000     1,566,000  WLC             0           0           0 Ashley McGraw                           0      09/18/23                       09/16/22           

          XXStorage Building - cancelled:
  -    XX New Construction             2-015-001                         CANCELLED            /  /       /  /     08/17/21     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Bus Garage Maint. Storage:
22-0517   Reconstruction               5-001-008  01/10/23     DONE    DONE       DONE      09/16/22   09/16/22   07/19/22   12/07/21   7,155,15,16              973,300       973,300  WLC             0           0           0 Ashley McGraw                           0      09/18/23                       09/16/22           

          Ross Concession:
  -       Reconstruction               7-009-001                                              /  /       /  /     01/25/22     /  /     2,4,8,9,155,15,16              0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Greenhouse:
  -       New Construction             7-014-001                                              /  /       /  /     11/04/20     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Concessions/Storage:
21-0679   New Construction             7-016-001  04/01/22     DONE    DONE       DONE      11/12/21   11/08/21   08/17/21   12/07/21   02 - 16                  638,000             0  SLC             0           0           0 Ashley McGraw                           0      10/03/22                       11/08/21           

          Pressbox:
21-0750   New Construction             7-017-001  04/01/22     DONE    DONE       DONE      11/19/21   11/19/21   08/17/21   12/07/21   02 - 16                   84,000             0  SLC             0           0           0 Ashley McGraw                           0      10/03/22                       11/19/21           

          District-Wide:
  -    SB Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     16                             0             0  BMJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




ITHACA CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-06-00-01
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Lehman Alt. Community School (6-12):
  -    PR Additions and Alterations    0-003-012                                              /  /       /  /     10/21/19     /  /     02 - 16                        0             0  JSS             0           0           0                                         0        /  /                           /  /             
20-1814   Additions and Alterations    0-003-012  02/08/22     DONE    DONE       DONE      06/01/21   05/26/21   10/21/19   05/21/19   02 - 16                2,583,145     2,333,688  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         05/26/21           

          Enfield Elem School (K-5):
19-0109   Reconstruction               0-004-013  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   11/20/18   05/21/19   8,9,10,155,16             55,000             0  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           
20-1815   Reconstruction               0-004-014  02/08/22     DONE    DONE       DONE      06/01/21   05/26/21   10/21/19   05/21/19   2,155,15,16            4,404,671     4,404,671  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         05/26/21           
21-1989   Reconstruction               0-004-015  10/06/22     DONE    DONE       DONE      06/17/22   06/14/22   01/20/22   05/21/19   2,7,8,16               2,339,655       925,641  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/14/22           
22-0327   Reconstruction               0-004-016  01/06/23     DONE    DONE       DONE      08/24/22   08/23/22   05/12/22   05/21/19   2,4,7,8,9,10,155,15,   1,510,350     1,510,350  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         08/23/22           

          Sherman Elem School(K-5) (see0-028):
19-0110   Reconstruction               0-007-012  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   11/20/18   05/21/19   8,9,155,16                95,000             0  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           
20-1816   Reconstruction               0-007-013  02/08/22     DONE    DONE       DONE      06/01/21   05/26/21   10/21/19   05/21/19   2,7,9                  1,015,017     1,015,017  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         05/26/21           

          Cayuga Heights Elem.(K-5):
19-0111   Reconstruction               0-011-010  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   11/20/18   05/21/19   8,9,10,155,16            195,000       195,000  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           
18-1898   Reconstruction               0-011-011  05/30/19     DONE    DONE       DONE      04/23/19   04/22/19   02/13/19   05/21/19   2,9                      250,000             0  BMJ             0           0           0 Tetra Tech Architects and Eng           0        /  /                         04/22/19           

          Beverly Martin Elementary:
19-0112   Reconstruction               0-012-013  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   11/20/18   05/21/19   8,9,10,155,16            265,000       265,000  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           
22-0328   Reconstruction               0-012-014  01/06/23     DONE    DONE       DONE      08/24/22   08/23/22   01/20/22   05/21/19   2,4,8,9,10,13,14,155   2,475,315     2,475,315  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         08/23/22           
  -       Reconstruction               0-012-015                                              /  /       /  /     05/12/22     /  /     2,9,16                         0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Fall Creek Elem School(K-5):
19-0113   Reconstruction               0-013-009  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   11/20/18   05/21/19   8,9,155,16               103,000       103,000  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           
  -       Reconstruction               0-013-010                                              /  /       /  /     05/12/22     /  /     2,9,10,155,16                  0             0  SLC             0           0           0                                         0        /  /                           /  /             
23-1675   Reconstruction               0-013-011                         UNREVIEWED         03/25/24   03/25/24   02/12/24   02/13/24   4,9,155,15,16            100,000       100,000  MSK             0           0           0 Tetra Tech Architects and Eng           0        /  /                         03/25/24           

          South Hill Elem School(K-5):
19-0114   Reconstruction               0-014-010  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   11/20/18   05/21/19   7,155,15,16            1,475,000             0  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           
  -    PR Additions and Alterations    0-014-011                                              /  /       /  /     10/21/19     /  /     02 - 16                        0             0  JSS             0           0           0                                         0        /  /                           /  /             
20-1817   Additions and Alterations    0-014-011  02/08/22     DONE    DONE       DONE      06/01/21   05/26/21   10/21/19   05/21/19   02 - 16                4,191,729     2,151,271  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         05/26/21           
21-0851   Reconstruction               0-014-012  06/02/22     DONE    DONE       DONE      12/07/21   12/06/21   08/06/21   05/17/22   9,10                      95,000        95,000  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         12/06/21           

          High School(9-12):
19-0115   Reconstruction               0-015-025  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   11/20/18   05/21/19   2,4,7,8,9,10,13,14,1  14,230,162    14,230,162  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           
20-1818   Reconstruction               0-015-026  02/08/22     DONE    DONE       DONE      06/01/21   05/26/21   10/21/19   05/21/19   2,7,9,10,155,15,16     1,296,786     1,296,786  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         05/26/21           
19-1902   Reconstruction               0-015-027  07/28/20     DONE    DONE       DONE      06/29/20   06/23/20   11/04/19   05/21/19   2,7                    7,181,645     7,181,645  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/23/20           
  -    PR Additions and Alterations    0-015-028                                              /  /       /  /     05/16/22     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             
22-1999   Additions and Alterations    0-015-028  10/25/23     DONE    DONE       DONE      04/05/23   04/03/23   05/16/22   05/21/19   02 - 16               23,299,575             0  MSK             0           0           0 Tetra Tech Architects and Eng           0        /  /                         04/03/23           

          Caroline Elem School(K-5):
19-0116   Reconstruction               0-017-012  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   11/20/18   05/21/19   2,15,16                1,305,000     1,305,000  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           
20-1819   Reconstruction               0-017-013  02/08/22     DONE    DONE       DONE      06/01/21   05/26/21   10/21/19   05/21/19   15,16                    600,710       600,710  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         05/26/21           
21-0654   Reconstruction               0-017-014  02/01/22     DONE    DONE       DONE      11/04/21   11/04/21   06/21/21   05/18/21   9,10                      95,000        95,000  SLC             0           0           0 Tetra Tech Architects and Eng           0      12/30/22                       11/04/21           

          Northeast Elem School(K-5):
19-0117   Reconstruction               0-024-008  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   11/20/18   05/21/19   8,9,155,16               160,000       160,000  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           
19-0038   Reconstruction               0-024-009  08/22/19     DONE    DONE       DONE      07/09/19   06/28/19   02/26/19   05/21/19   2,9                      250,000             0  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/28/19           
22-0679   Reconstruction               0-024-010  01/07/23     DONE    DONE       DONE      10/07/22   10/07/22   04/04/22   05/18/22                            328,680       328,680  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         10/07/22           
23-1373   Reconstruction               0-024-011               STARTED DONE       DONE      01/16/24   01/16/24   10/30/23     /  /     9,10                           0    15,138,090  MSK             0           0           0 Tetra Tech Architects and Eng           0        /  /                         01/16/24           
23-1491   Reconstruction               0-024-012                         UNREVIEWED         02/12/24   02/12/24   01/29/24     /  /     9                              0             0  MSK             0           0           0 Tetra Tech Architects and Eng           0        /  /                         02/12/24           

          Boynton MS (6-8):
19-0118   Reconstruction               0-026-016  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   12/21/18   05/21/19   8                        866,814       866,814  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           
20-1820   Reconstruction               0-026-017  02/08/22     DONE    DONE       DONE      06/01/21   05/26/21   10/21/19   05/21/19   2,4,8,9,10,155,15,16   4,266,074     4,266,074  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         05/26/21           
20-1532   Reconstruction               0-026-018  07/26/21     DONE    DONE       DONE      04/02/21   03/29/21   03/03/20   05/21/19   13,155,16                729,736       729,736  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         03/29/21           
20-0498   Reconstruction               0-026-019  01/27/21     DONE    DONE       DONE      09/30/20   09/14/20   08/19/20   05/19/20   2,10                      95,000        95,000  JSS             0           0           0 Tetra Tech Architects and Eng           0      05/12/21                       09/14/20           

          Dewitt MS (6-8):
18-1988   Reconstruction               0-027-015  06/25/19     DONE    DONE       DONE      05/20/19   05/15/19   02/13/19   05/21/19   9,10,16                   97,075        97,075  BMJ             0           0           0 Tetra Tech Architects and Eng           0      01/15/20                       05/15/19           
20-1821   Reconstruction               0-027-016  02/08/22     DONE    DONE       DONE      06/01/21   05/26/21   03/03/20   05/21/19   13,155,16              4,384,117     4,384,117  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         05/26/21           
20-1533   Reconstruction               0-027-017  07/26/21     DONE    DONE       DONE      04/02/21   03/29/21   10/21/19   05/21/19   2,4,8,9,10,155,15,16     729,736       729,736  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         03/29/21           

          Wilson Annex @ Sherman Sch.See 0-007:
19-0119   Reconstruction               0-028-008  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   11/20/18   05/21/19   8,9,155,16               100,000       100,000  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           
20-1822   Reconstruction               0-028-009  02/08/22     DONE    DONE       DONE      06/01/21   05/26/21   10/21/19   05/21/19   2,8,9,10,155,16          558,943       558,943  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         05/26/21           

          Temp. Classroom - Complex A:
  -    PR New Construction             0-060-001                                              /  /       /  /     03/02/23     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-2322   New Construction             0-060-001  10/04/23     DONE    DONE       DONE      06/05/23   06/02/23   03/02/23   05/21/19   02 - 16                1,207,500             0  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/02/23           

          Temp. Classroom - Complex B:
  -    PR New Construction             0-061-001                                              /  /       /  /     03/02/23     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-2323   New Construction             0-061-001  10/04/23     DONE    DONE       DONE      06/05/23   06/02/23   03/02/23   05/21/19   02 - 16                1,207,500             0  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/02/23           

          Storage Building:
  -    PR New Construction             2-058-001                                              /  /       /  /       /  /       /  /     02 - 16                        0             0  JSS             0           0           0                                         0        /  /                           /  /             

          Transportation Cntr-EV Infrastucture:
19-0120   Reconstruction               5-002-011  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   11/20/18   05/21/19   2,155,16               3,245,000     3,245,000  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           
22-2051   Reconstruction               5-002-012  09/07/23     DONE    DONE       DONE      04/17/23   04/14/23   02/16/23   03/28/23   2,16                     104,000       104,000  MSK             0           0           0 Tetra Tech Architects and Eng           0        /  /                         04/14/23           
  -       Reconstruction               5-002-013                                              /  /       /  /     02/01/24     /  /     2,9,16                         0             0  MSK             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               5-002-014                                              /  /       /  /     02/01/24     /  /     2,9,16                         0             0  MSK             0           0           0                                         0        /  /                           /  /             

          PA Booth Demolition:
19-0121   Reconstruction               7-019-001  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   01/14/19   05/21/19   2,7,8,9,13,155,16         50,000             0  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           

          Press Box:
  -    PR New Construction             7-057-001                                              /  /       /  /     06/27/19     /  /     02 - 16                        0             0  BMJ             0           0           0                                         0        /  /                           /  /             
19-0122   New Construction             7-057-001  10/31/19     DONE    DONE       DONE      07/19/19   06/20/19   06/27/19   05/21/19   02 - 16                  150,000             0  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         06/20/19           

          Caroline Pavilion:
21-0576   New Construction             7-059-001  02/08/22     DONE    DONE       DONE      10/22/21   10/21/21   05/27/21   08/31/21   02 - 16                   27,000             0  SLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         10/21/21           

          District-Wide:
19-1688SB Reconstruction               7-999-007               DONE                           /  /       /  /       /  /       /  /     10                             0             0  JSS             0           0           0                                         0        /  /                           /  /             
20-0359   Reconstruction               7-999-007  02/03/21     DONE    DONE       DONE      09/08/20   09/01/20   04/10/20   11/04/14   8,16                     491,627             0  JSS             0           0           0 Hunt Engineers,Architects & l           0        /  /                         09/01/20           
  -       Reconstruction               7-999-BA1               DONE                           /  /       /  /       /  /       /  /     10                             0             0  JSS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LANSING CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-08-01-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Lansing Middle School:
18-2049   Reconstruction               0-001-021  08/30/19     DONE    DONE       DONE      06/03/19   05/24/19   11/19/18   10/24/18   2,8,9,155,15,16        1,174,940     1,174,940  JSS             0           0           0 Tetra Tech Architects and Eng           0      09/03/21                       05/24/19           
23-0176   Reconstruction               0-001-022  03/08/24     DONE    DONE       DONE      08/01/23   07/28/23   04/03/23   11/01/22   2,4,7,9,155,16         3,100,000     3,100,000  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         07/28/23           
23-0220   Reconstruction               0-001-023  02/23/24     DONE    DONE       DONE      08/09/23   08/08/23   05/11/23   01/24/23   155,16                 2,420,000     2,420,000  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         08/08/23           
23-0468   Reconstruction               0-001-024  02/26/24     DONE    DONE       DONE      09/13/23   09/13/23   05/11/23   01/24/23   2,4,7,9,10,155,15,16   2,510,068     2,510,068  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/13/23           
23-1853   Reconstruction               0-001-025                         UNREVIEWED         04/18/24   04/17/24   10/11/23   01/24/23   9                              0             0  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         04/17/24           

          Technology Building:
18-2050   Reconstruction               0-002-006  08/30/19     DONE    DONE       DONE      06/03/19   05/24/19   11/19/18   10/24/18   15                        15,556             0  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         05/24/19           
23-1854   Reconstruction               0-002-007                         UNREVIEWED         04/18/24   04/17/24   10/11/23   01/24/23   2,4,8,9,10,155,15,16           0             0  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         04/17/24           

          Lansing Elementary:
18-2048   Additions and Alterations    0-003-018  08/30/19     DONE    DONE       DONE      06/03/19   05/24/19   11/19/18   10/24/18   02 - 16                4,911,152     3,907,741  JSS             0           0           0 Tetra Tech Architects and Eng           0      09/03/21                       05/24/19           
23-0469   Reconstruction               0-003-019  02/26/24     DONE    DONE       DONE      09/13/23   09/13/23   05/11/23   01/24/23   2,7,155,15,16            575,818       575,818  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/13/23           
23-1855   Reconstruction               0-003-020                         UNREVIEWED         04/18/24   04/17/24   10/11/23   01/24/23   15,16                          0             0  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         04/17/24           

          Senior High:
18-2051   Reconstruction               0-004-026  08/30/19     DONE    DONE       DONE      06/03/19   05/24/19   11/19/18   10/24/18   2,9,155,16               783,294       783,294  JSS             0           0           0 Tetra Tech Architects and Eng           0      09/03/21                       05/24/19           
19-1459   Reconstruction               0-004-027  07/27/20     DONE    DONE       DONE      02/21/20   02/14/20   08/20/19   02/08/16   7,155                     25,000             0  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         02/14/20           
23-0470   Reconstruction               0-004-028  02/26/24     DONE    DONE       DONE      09/13/23   09/13/23   05/11/23   01/24/23   2,7,9,10,15              689,343       689,343  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/13/23           
23-1856   Reconstruction               0-004-029                         UNREVIEWED         04/18/24   04/17/24   10/11/23   01/24/23   2,4,8,9,16                     0             0  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         04/17/24           
23-1528   Reconstruction               0-004-030                         UNREVIEWED         02/20/24   02/20/24   01/31/24   01/24/23   155                            0             0  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         02/20/24           

          Former District Office:
18-2052   Reconstruction               1-005-005  08/30/19     DONE    DONE       DONE      06/03/19   05/24/19   11/19/18   10/24/18   2,4,155,16               122,618             0  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         05/24/19           

          Grounds Building II:
18-2053   Reconstruction               3-013-003  08/30/19     DONE    DONE       DONE      06/03/19   05/24/19   11/19/18   10/24/18   16                        18,302             0  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         05/24/19           

          Bus Maintenance Garage:
18-2054   Reconstruction               5-006-011  08/30/19     DONE    DONE       DONE      06/03/19   05/24/19   11/19/18   10/24/18   2,155,16                 318,990       318,990  JSS             0           0           0 Tetra Tech Architects and Eng           0      09/03/21                       05/24/19           
19-1302   Reconstruction               5-006-012  02/11/20     DONE    DONE       DONE      01/29/20   01/29/20   11/04/19   11/25/19   4,14,16                  212,000             0  JSS             0           0           0 Tetra Tech Architects and Eng           0        /  /                         01/29/20           
22-1667   Reconstruction               5-006-013  03/23/23     DONE    DONE       DONE      02/13/23   02/13/23   01/10/23   05/17/22   16                       100,000       100,000  WLC             0           0           0 Tetra Tech Architects and Eng           0        /  /                         02/13/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NEWFIELD CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-09-01-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Newfield Elementary:
  -       Reconstruction               0-001-019                                              /  /       /  /     04/12/24     /  /     2,4,8,9,16                     0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Junior/Senior High School:
  -       Reconstruction               0-005-015                                              /  /       /  /     04/12/24     /  /     2,4,8,9,10,155,15,16           0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Bus Garage:
23-1452   Reconstruction               5-002-007  03/21/24     DONE    DONE       DONE      01/31/24   01/31/24   11/29/23   03/12/24   15,16                    332,000       332,000  JJH             0           0           0 King & King Architects                  0        /  /                         01/31/24           
  -       Reconstruction               5-002-008                                              /  /       /  /     04/12/24     /  /     16                             0             0  JJH             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               5-002-009                                              /  /       /  /     04/12/24     /  /     2,8,9,14,155,15,16             0             0  JJH             0           0           0                                         0        /  /                           /  /             

          District-Wide:
23-0589   Reconstruction               7-999-002  10/30/23     DONE    DONE       DONE      10/02/23   09/29/23     /  /     05/16/23                            100,000       100,000  JJH             0           0           0 King & King Architects                  0        /  /                         09/29/23           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




TRUMANSBURG CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-10-01-04
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Russell I Doig Middle School:
19-0056   Reconstruction               0-001-016  10/31/19     DONE    DONE       DONE      07/10/19   06/21/19   04/16/19   03/13/18   9,155,15,16           10,743,750     9,987,359  SLC             0           0           0 Hunt Engineers,Architects & l           0      04/28/23                       06/21/19           

          Trumansburg Elementary:
19-0057   Reconstruction               0-003-016  10/31/19     DONE    DONE       DONE      07/10/19   06/21/19   04/16/19   03/13/18   9,16                   7,542,906     6,958,577  SLC             0           0           0 Hunt Engineers,Architects & l           0      04/28/23                       06/21/19           

          Dickerson High School:
19-0058   Reconstruction               0-006-017  10/31/19     DONE    DONE       DONE      07/10/19   06/21/19   04/16/19   03/13/18   9,155,15,16            6,655,062     6,655,062  SLC             0           0           0 Hunt Engineers,Architects & l           0      04/28/23                       06/21/19           
19-0084   Reconstruction               0-006-018  09/11/19     DONE    DONE       DONE      07/15/19   07/02/19   06/18/19   05/21/19   2,8                      100,000       100,000  SLC             0           0           0 Hunt Engineers,Architects & l           0      06/12/20                       07/02/19           

          Storage Container #5:
20-0931TQ Temporary Quarters           2-012-001  06/15/21     DONE    DONE       DONE      12/07/20   12/07/20   10/15/20     /  /                                2,500             0  SLC             0           0           0                                         0      03/24/21                       12/07/20           

          Storage Container #4:
20-0932TQ Temporary Quarters           2-013-001  06/15/21     DONE    DONE       DONE      12/07/20   12/07/20   10/15/20     /  /                                2,500             0  SLC             0           0           0                                         0      03/24/21                       12/07/20           

          Storage Container #3:
20-0933TQ Temporary Quarters           2-014-001  06/15/21     DONE    DONE       DONE      12/07/20   12/07/20   10/15/20     /  /                                2,500             0  SLC             0           0           0                                         0      03/24/21                       12/07/20           

          Storage Container #2:
20-0934TQ Temporary Quarters           2-015-001  06/15/21     DONE    DONE       DONE      12/07/20   12/07/20   10/15/20     /  /                                2,500             0  SLC             0           0           0                                         0      03/24/21                       12/07/20           

          Storage Container #1:
20-0935TQ Temporary Quarters           2-016-001  06/15/21     DONE    DONE       DONE      12/07/20   12/07/20   10/15/20     /  /                                2,500             0  SLC             0           0           0                                         0      03/24/21                       12/07/20           

          Storage Container #6:
  -    DB Discovered Building          2-017-001                                              /  /       /  /     01/27/21     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Storage Container #7:
  -    DB Discovered Building          2-018-001                                              /  /       /  /     01/27/21     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Storage Container #8:
  -    DB Discovered Building          2-019-001                                              /  /       /  /     01/27/21     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          XXMiddle School Farm Shed-Canceled:
  -    XX New Construction             2-020-001                         CANCELLED            /  /       /  /     01/19/22     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             

          I.T. Annex Bldg:
22-0620   Reconstruction               3-005-002  02/14/23     DONE    DONE       DONE      10/03/22   09/30/22   07/26/22   05/17/22   2,4,7,8,9,10,155,15,   1,149,616             0  SLC             0           0           0 Bernier Carr Associates                 0        /  /                         09/30/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




BOCES TOMPKINS-SENECA-TIOGA STATUS REPORT ON CAPITAL PROJECTS
District No.: 61-90-00-00
last updated on 04/19/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          G Powell Bldg B:
19-1893   Reconstruction               0-009-008  08/25/20     DONE    DONE       DONE      06/29/20   06/15/20   12/01/16   07/06/17   2,8,9,155,15,16          638,843             0  JSS             0           0           0 LaBella Associates, P.C.                0        /  /                         06/15/20           

          C Building - Career & Technology:
19-1894   Reconstruction               0-010-009  08/25/20     DONE    DONE       DONE      06/29/20   06/15/20   12/01/16   07/06/17   2,8,9,155,15,16          256,677             0  JSS             0           0           0 LaBella Associates, P.C.                0        /  /                         06/15/20           

          Occ Ed Bldg D:
19-1895   Reconstruction               0-011-008  08/25/20     DONE    DONE       DONE      06/29/20   06/15/20   01/09/17   07/06/17   2,8,9,155,15,16          307,130             0  JSS             0           0           0 LaBella Associates, P.C.                0        /  /                         06/15/20           
  -       Reconstruction               0-011-010                                              /  /       /  /     05/20/19     /  /     10,16                          0             0  JLB             0           0           0                                         0        /  /                           /  /             

          Smith Special Ed Blg:
19-1896   Reconstruction               0-012-012  08/25/20     DONE    DONE       DONE      06/29/20   06/15/20   01/09/17   07/06/17   2,7,8,9,155,15,16      2,949,056             0  JSS             0           0           0 LaBella Associates P.C.                 0        /  /                         06/15/20           

          Building A-Administration:
19-1897   Reconstruction               1-001-007  08/25/20     DONE    DONE       DONE      06/29/20   06/15/20   12/01/16   07/06/17   2,8,9,155,15,16          554,223             0  JSS             0           0           0 LaBella Associates, P.C.                0        /  /                         06/15/20           
19-1156   Reconstruction               1-001-009  01/15/20     DONE    DONE       DONE      01/03/20   11/27/19   05/20/19   09/04/19   10,16                      8,000             0  JSS             0           0           0 LaBella Associates, P.C.                0        /  /                         11/27/19           

          G Bldg Greenhouse:
19-1898   Reconstruction               2-007-005  08/25/20     DONE    DONE       DONE      06/29/20   06/15/20   12/01/16   07/06/17   2,8,9,155,15,16          137,650             0  JSS             0           0           0 LaBella Associates, P.C.                0        /  /                         06/15/20           

          G BLDG Warehouse/Bus Maint.:
19-1157   Reconstruction               5-007-003  01/15/20     DONE    DONE       DONE      01/03/20   11/27/19   05/20/19   09/04/19   10,16                      8,000             0  JSS             0           0           0 LaBella Associates, P.C.                0        /  /                         11/27/19           

          District Wide:
19-1020   Reconstruction               7-999-003  01/30/20     DONE    DONE       DONE      12/17/19   12/11/19   09/30/19     /  /     15,16                  1,153,370             0  JSS             0           0           0 LaBella Associates P.C.                 0        /  /                         12/11/19           

          Tompkins Cortland Community Col TC3:
19-0252TQ Temporary Quarters           8-022-001                       ADDENDUM REQ'D       08/14/19     /  /     07/05/19     /  /                                    0             0  JSS             0           0           0                                         0        /  /                           /  /             

          TC3 Extension Center Tioga Place:
19-0253TQ Temporary Quarters           8-023-001                       ADDENDUM REQ'D       08/14/19     /  /     07/08/19     /  /                                    0             0  JSS             0           0           0                                         0        /  /                           /  /             

          IC3 Community Care Center:
20-1591TQ Temporary Quarters           8-024-001  10/19/21     DONE    DONE       DONE      04/16/21   04/16/21   02/26/21     /  /                                    0             0  JLB             0           0           0                                         0        /  /                         04/16/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED