WARREN COUNTY

WARREN COUNTY

BOLTON 630101
GLENS FALLS 630300
GLENS FALLS CO 630918
HADLEY LUZERNE 630801
JOHNSBURG 630601
LAKE GEORGE 630701
NORTH WARREN 630202
QUEENSBURY 630902
WARRENSBURG 631201
















Construction Project Status

Construction Project Status

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 04/18/24 at 07:18:46




BOLTON CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-01-01-04
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Bolton Central:
18-2212   Additions and Alterations    0-001-011  09/05/19     DONE    DONE       DONE      06/28/19   06/19/19   02/22/19   10/30/18   02 - 16                3,522,231     2,751,482  JLB             0           0           0 JMZ Architects & Planners               0      06/16/22                       06/19/19           

          Maintenance Storage Building:
18-1698   New Construction             2-006-001  05/14/19     DONE    DONE       DONE      03/20/19   03/06/19   11/07/18   10/30/18   02 - 16                  367,541             0  MTM             0           0           0 JMZ Architects & Planners               0      02/04/20                       03/06/19           

          Bus Garage:
18-1699   Reconstruction               5-002-005  05/14/19     DONE    DONE       DONE      03/20/19   03/06/19   11/07/18   10/30/18   13                       177,228       177,228  JLB             0           0           0 JMZ Architects & Planners               0      02/04/20                       03/06/19           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




NORTH WARREN CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-02-02-04
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          K-12 Building:
19-0819   Reconstruction               0-014-007  03/03/20     DONE    DONE       DONE      11/19/19   11/07/19     /  /     05/21/19   2,4,9,10,14,155,15,1     551,000       551,000  BMJ             0           0           0 Bernier Carr Associates                 0      10/15/21                       11/07/19           
21-0923FB Reconstruction               0-014-008  12/20/21     DONE    DONE       DONE      12/17/21   12/17/21   09/24/21   10/18/21   155,15,16              1,011,069             0  JLB             0           0           0 Bernier Carr Associates                 0      01/31/23                       12/17/21           
21-1991   Reconstruction               0-014-009  09/09/22     DONE    DONE       DONE      06/17/22   06/14/22   01/11/22   05/17/22   9,155,15,16            2,750,000     2,750,000  JLB             0           0           0 Bernier Carr Associates                 0        /  /                         06/14/22           
  -       Reconstruction               0-014-010                                              /  /       /  /     01/16/24     /  /     4,7,8,9,10,155,15,16           0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Garage Storage:
21-0915   New Construction             2-020-001  04/22/22     DONE    DONE       DONE      12/17/21   12/16/21   12/01/20     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                         12/16/21           

          New Bus Garage (#2):
  -       New Construction             5-019-001                                              /  /       /  /     07/27/20     /  /     02 - 16                        0             0  JSS             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GLENS FALLS CITY SCHOOLS STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-03-00-01
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle/High School:
20-0105   Reconstruction               0-001-030  09/18/20     DONE    DONE       DONE      07/21/20   07/14/20   02/13/20   05/16/17   2,4,7,8,9,155,15,16    1,830,000     1,830,000  SLC             0           0           0 Mosaic Associates                       0      03/15/22                       07/14/20           
21-1794   Reconstruction               0-001-031  08/05/22     DONE    DONE       DONE      05/09/22   05/06/22   02/14/22   12/14/21   4,7,8,9,10,155,15,16   3,333,100     3,333,100  JLB             0           0           0 Mosaic Associates                       0      12/01/23                       05/06/22           
22-0697   Reconstruction               0-001-032  01/24/23     DONE    DONE       DONE      10/12/22   10/11/22   09/07/22   12/14/21   2,4,7,8,9,10,155,15,  14,536,815    14,536,815  JLB             0           0           0 Mosaic Associates                       0        /  /                         10/11/22           
23-0706   Reconstruction               0-001-033               UNREVIEWED
                                                                       DONE       STARTED   10/13/23   10/11/23   05/17/23   12/14/21   2,4,7,8,9,10,14,155,           0    62,814,618  JJH             0           0           0 Mosaic Associates                       0        /  /                         10/11/23           

          Big Cross St. Elementary:
20-0106   Reconstruction               0-003-013  09/18/20     DONE    DONE       DONE      07/21/20   07/14/20   02/13/20   05/16/17   4,8,16                   117,150       117,150  SLC             0           0           0 Mosaic Associates                       0      10/26/21                       07/14/20           
21-1795   Reconstruction               0-003-014  08/05/22     DONE    DONE       DONE      05/09/22   05/06/22   02/07/22   12/14/21   2,9,10,155,16            958,600       958,600  JLB             0           0           0 Mosaic Associates                       0      12/01/23                       05/06/22           
22-0100   Reconstruction               0-003-015  10/11/22     DONE    DONE       DONE      07/18/22   07/15/22   05/04/22   06/22/22   155,16                   114,000             0  JLB             0           0           0 Mosaic Associates                       0      12/01/23                       07/15/22           
23-0707   Reconstruction               0-003-016               UNREVIEWED
                                                                       DONE       STARTED   10/13/23   10/11/23   05/17/23   12/14/21   2,7                            0             0  JJH             0           0           0 Mosaic Associates                       0        /  /                         10/11/23           

          Jackson Heights Elementary:
20-0107   Reconstruction               0-005-012  09/18/20     DONE    DONE       DONE      07/21/20   07/14/20   02/13/20   05/16/17   4,8,16                   110,400       110,400  SLC             0           0           0 Mosaic Associates                       0      10/26/21                       07/14/20           
22-0101   Reconstruction               0-005-013  10/11/22     DONE    DONE       DONE      07/18/22   07/15/22   03/07/22   12/14/21   2,155,16                  16,500             0  JLB             0           0           0 Mosaic Associates                       0      12/01/23                       07/15/22           
22-2476   Reconstruction               0-005-014  08/08/23     DONE    DONE       DONE      06/28/23   06/28/23   05/17/23   05/16/23   16                       100,000       100,000  JJH             0           0           0 Mosaic Associates                       0        /  /                         06/28/23           
23-0708   Reconstruction               0-005-015               UNREVIEWED
                                                                       DONE       STARTED   10/13/23   10/11/23   05/17/23   12/14/21   7,8,9,16                       0             0  JJH             0           0           0 Mosaic Associates                       0        /  /                         10/11/23           
  -       Reconstruction               0-005-016                                              /  /       /  /     03/27/24     /  /     16                             0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Sanford St. Elem-LeasedToBOCES:
18-2193   Reconstruction               0-006-011  07/02/19     DONE    DONE       DONE      06/24/19   06/19/19   05/14/19   05/13/19   155,15,16                600,000       600,000  SLC             0           0           0 Mosaic Associates                       0      04/13/20                       06/19/19           
20-0108   Reconstruction               0-006-012  09/18/20     DONE    DONE       DONE      07/21/20   07/14/20   02/13/20   05/16/17   4,8,16                    83,800        83,800  SLC             0           0           0 Mosaic Associates                       0      10/26/21                       07/14/20           

          Kensington Road Elementary:
20-0109   Reconstruction               0-007-012  09/18/20     DONE    DONE       DONE      07/21/20   07/14/20   02/13/20   05/16/17   4,8,16                    73,735        73,735  SLC             0           0           0 Mosaic Associates                       0      10/26/21                       07/14/20           

          Administration Bldg:
20-0110   Reconstruction               1-008-007  09/18/20     DONE    DONE       DONE      07/21/20   07/14/20   02/13/20   05/16/17   2,4,7,8,16               147,200             0  SLC             0           0           0 Mosaic Associates                       0      11/19/21                       07/14/20           
21-1796   Reconstruction               1-008-008  08/05/22     DONE    DONE       DONE      05/09/22   05/06/22   02/07/22   12/14/21   8                        140,171             0  JLB             0           0           0 Mosaic Associates                       0      12/01/23                       05/06/22           

          35 Glenwood Avenue House:
18-2213DB Discovered Building          2-021-001  08/09/19     DONE    DONE       DONE      06/28/19     /  /     01/11/19     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          35 Glenwood Avenue Barn:
18-2214DB Discovered Building          2-022-001  08/09/19     DONE    DONE       DONE      06/28/19     /  /     01/11/19     /  /                                    0             0  SLC             0           0           0                                         0        /  /                           /  /             

          Jackson Heights Storage:
19-1874DB Discovered Building          2-023-001  07/20/20     DONE    DONE       DONE      06/26/20   06/26/20   02/04/20     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         06/26/20           

          Stor/Concession/Toilet @ MS HS:
21-1797   Reconstruction               7-015-002  08/05/22     DONE    DONE       DONE      05/09/22   05/06/22   04/11/22   12/14/21   16                         6,000             0  JLB             0           0           0 Mosaic Associates                       0      12/01/23                       05/06/22           

          Press Box:
18-2173DB Discovered Building          7-020-001               UNREVIEWED
                                                                       DONE       DONE      06/20/19   06/19/19   04/19/18     /  /                                    0             0  SLC             0           0           0                                         0        /  /                         06/19/19           

          Kitchen Cooler/Freezer:
  -    PR New Construction             7-024-001                                              /  /       /  /     03/08/22     /  /     02 - 16                        0             0  SLC             0           0           0                                         0        /  /                           /  /             
22-0102   New Construction             7-024-001  10/11/22     DONE    DONE       DONE      07/18/22   07/15/22   03/08/22   12/14/21   02 - 16                  117,000             0  JLB             0           0           0 Mosaic Associates                       0      12/01/23                       07/15/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




JOHNSBURG CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-06-01-04
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Building:
22-0908FB Reconstruction               0-001-010  01/19/23     DONE    DONE       DONE      11/07/22   09/29/22   07/22/22   09/19/22   2,9,155,16             1,076,701     1,076,701  JLB             0           0           0 Tetra Tech Architects and Eng           0        /  /                         09/29/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




LAKE GEORGE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-07-01-04
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Main Bldg.Jr/Sr High School:
19-0466   Reconstruction               0-004-012  12/26/19     DONE    DONE       DONE      09/20/19   09/17/17   01/22/19   12/04/18   2,8,9,10,155,15,16     4,130,207     4,130,207  BMJ             0           0           0 Tetra Tech Architects and Eng           0      04/18/22                       09/17/17           
21-1009FB Reconstruction               0-004-013  02/15/22     DONE    DONE       DONE      01/03/22   12/20/21   09/29/21   02/08/22   2,9,155,16               673,949       673,949  JLB             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         12/20/21           
21-1910   Reconstruction               0-004-014  08/10/22     DONE    DONE       DONE      06/01/22   05/27/22   04/26/22   05/17/22   155,16                   100,000       100,000  JLB             0           0           0 Tetra Tech Engineers, Archite           0      06/23/23                       05/27/22           
23-0964   Reconstruction               0-004-015  12/21/23     DONE    DONE       DONE      11/10/23   11/10/23   10/30/23   05/16/23   155                      100,000       100,000  JJH             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         11/10/23           

          Lake George Elementary School:
19-0467   Reconstruction               0-006-018  12/26/19     DONE    DONE       DONE      09/20/19   09/17/17   01/22/19   12/04/18   2,8,9,16               1,141,984     1,141,984  BMJ             0           0           0 Tetra Tech Architects and Eng           0      04/18/22                       09/17/17           
21-1010FA Reconstruction               0-006-019  02/15/22     DONE    DONE       DONE      01/03/22   12/20/21   09/29/21   02/08/22   2,7,9,155,16             791,999       791,999  JLB             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         12/20/21           

          COVID-19 Storage Shed:
20-0905   New Construction             2-010-001  01/18/22     DONE    DONE       DONE      12/01/20   11/30/20   10/23/20   12/04/18   02 - 16                   22,000             0  JSS             0           0           0 Tetra Tech Architects and Eng           0      12/06/21                       11/30/20           

          XXTransportation Facility #2 (EV):
  -    XX New Construction             5-014-001                         CANCELLED            /  /       /  /     01/19/24     /  /     02 - 16                        0             0  JJH             0           0           0                                         0        /  /                           /  /             
23-1472   New Construction             5-014-001                         UNREVIEWED         02/06/24   02/05/24   01/19/24   12/06/22   02 - 16                        0             0  JJH             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/05/24           

          Transportation Facility:
23-1473   New Construction             7-013-001                         UNREVIEWED         02/06/24   02/05/24   04/19/23   12/06/22   02 - 16                        0             0  JJH             0           0           0 Tetra Tech Engineers, Archite           0        /  /                         02/05/24           

          Storage Container 1:
20-1115XX Alterations                  8-011-001                         CANCELLED          01/13/21   01/08/21   11/20/20     /  /                                    0             0  JSS             0           0           0                                         0        /  /                         01/08/21           

          Storage Container 2:
20-1116XX Alterations                  8-012-001                         CANCELLED          01/13/21   01/08/21   11/20/20     /  /                                    0             0  JSS             0           0           0                                         0        /  /                         01/08/21           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




HADLEY-LUZERNE CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-08-01-04
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Jr/Sr High School:
20-1944   Reconstruction               0-001-022  07/15/21     DONE    DONE       DONE      06/30/21   06/28/21   05/11/21   06/09/20   7                        100,000       100,000  JLB             0           0           0 Bernier Carr Associates                 0      11/18/21                       06/28/21           
22-0599   Reconstruction               0-001-023  10/24/22     DONE    DONE       DONE      09/28/22   09/27/22   06/24/22   05/17/22   9                        100,000       100,000  JLB             0           0           0 Bernier Carr Associates                 0      04/13/23                       09/27/22           

          Stuart M Townsend Elem School:
  -       Reconstruction               0-004-013                                              /  /       /  /     05/05/21     /  /     7                              0             0  JSS             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-004-014                                              /  /       /  /     12/01/23     /  /     155                            0             0  JJH             0           0           0                                         0        /  /                           /  /             

          High School Maintenance Shed #1:
  -    DB Discovered Building          2-020-001                                              /  /       /  /     01/30/20     /  /                                    0             0  BMJ             0           0           0                                         0        /  /                           /  /             


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




QUEENSBURY UFSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-09-02-03
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Middle School:
19-1190   Reconstruction               0-001-035  03/06/20     DONE    DONE       DONE      01/10/20   01/07/20   12/20/19   05/21/19   16                       230,000       230,000  SLC             0           0           0 Collins & Scoville Architects           0      04/01/21                       01/07/20           
20-0160   Reconstruction               0-001-036  08/17/20     DONE    DONE       DONE      08/07/20   08/06/20   07/17/20   08/10/20   2,15                     115,000       115,000  SLC             0           0           0 Collins & Scoville Architects           0      01/15/21                       08/06/20           
20-1055   Reconstruction               0-001-037  04/07/21     DONE    DONE       DONE      12/28/20   12/21/20   12/15/20   06/09/20   16                       700,000       700,000  SLC             0           0           0 Collins & Scoville Architects           0      03/31/23                       12/21/20           
21-0662   Reconstruction               0-001-038  03/18/22     DONE    DONE       DONE      11/05/21   11/04/21   10/21/21   05/18/21   2,7,8,9,16             1,000,000     1,000,000  SLC             0           0           0 Collins & Scoville Architects           0      11/11/22                       11/04/21           
21-0754   Reconstruction               0-001-039  03/21/22     DONE    DONE       DONE      11/19/21   11/19/21   10/21/21   12/14/21   2,7,9,10,15,16         2,310,000     2,310,000  SLC             0           0           0 Collins & Scoville Architects           0        /  /                         11/19/21           
22-0082   Reconstruction               0-001-040  11/28/22     DONE    DONE       DONE      07/13/22   07/13/22   06/13/22   12/14/21   2,9,155,15,16            295,000       295,000  JLB             0           0           0 Collins & Scoville Architects           0      09/07/23                       07/13/22           
22-0255   Reconstruction               0-001-041  01/19/23     DONE    DONE       DONE      08/15/22   08/09/22   07/22/22   05/17/22   2,8,9,10,155,15,16       890,000       890,000  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         08/09/22           
22-2425   Reconstruction               0-001-042  10/19/23     DONE    DONE       DONE      06/20/23   06/20/23   03/15/23   05/16/23   9,155,15,16            1,566,272     1,566,272  WLC             0           0           0 Mosaic Associates                       0        /  /                         06/20/23           
  -       Reconstruction               0-001-043                                              /  /       /  /     04/10/23     /  /     2,4,7,8,9,10,155,15,           0             0  WLC             0           0           0                                         0        /  /                           /  /             
  -    SB Reconstruction               0-001-BA1               DONE                           /  /       /  /       /  /       /  /     10                             0             0  SLC             0           0           0                                         0        /  /                           /  /             

          High School:
19-1070   Reconstruction               0-002-026  03/25/20     DONE    DONE       DONE      12/26/19   12/16/19   11/04/19   01/12/16   9,16                   1,200,000     1,200,000  SLC             0           0           0 Collins & Scoville Architects           0      09/28/20                       12/16/19           
19-1055   Reconstruction               0-002-027  06/16/20     DONE    DONE       DONE      12/26/19   12/16/19   11/12/19   11/12/19   9,15,16                  125,000             0  SLC             0           0           0 Collins & Scoville Architects           0      10/30/20                       12/16/19           
20-0068   Reconstruction               0-002-028  08/17/20     DONE    DONE       DONE      07/20/20   07/20/20   06/12/20   07/13/20   155,16                   367,178       367,178  SLC             0           0           0 Collins & Scoville Architects           0      04/15/21                       07/20/20           
22-1708   Reconstruction               0-002-029  11/08/21     DONE    DONE       DONE      02/21/23   02/21/23   02/08/22   11/08/21   15                        47,500        47,500  WLC             0           0           0 Collins & Scoville Architects           0      12/15/21                       02/21/23           
21-1490   Reconstruction               0-002-030  08/04/22     DONE    DONE       DONE      03/10/22   03/10/22   03/02/22   05/17/22   7,8,9,10,155,15,16       410,000       410,000  WLC             0           0           0 Collins & Scoville Architects           0        /  /                         03/10/22           
  -       Reconstruction               0-002-031                                              /  /       /  /     04/11/22     /  /     2                              0             0  SLC             0           0           0                                         0        /  /                           /  /             
22-0083   Reconstruction               0-002-032  11/28/22     DONE    DONE       DONE      07/13/22   07/13/22   06/13/22   12/14/21   2,155,16               4,080,000     4,080,000  JLB             0           0           0 Collins & Scoville Architects           0      09/07/23                       07/13/22           
  -       Reconstruction               0-002-033                                              /  /       /  /     04/09/24     /  /     2,4,8,9,10,155,15,16           0             0  WLC             0           0           0                                         0        /  /                           /  /             

          K-3 Elementary School:
18-1932   Reconstruction               0-003-018  06/13/19     DONE    DONE       DONE      05/08/19   05/06/19   03/29/19   05/21/19   7                        100,000       100,000  SLC             0           0           0 Collins & Scoville Architects           0      05/12/20                       05/06/19           
19-1191   Reconstruction               0-003-019  03/06/20     DONE    DONE       DONE      01/10/20   01/07/20   12/20/19   05/21/19   16                       200,000       200,000  SLC             0           0           0 Collins & Scoville Architects           0      04/01/21                       01/07/20           
22-1639   Reconstruction               0-003-020  09/13/21     DONE    DONE       DONE      02/08/23   02/07/23   08/20/21   09/13/21   15                        40,690        40,690  WLC             0           0           0 Collins & Scoville Architects           0      09/30/21                       02/07/23           
21-0755   Reconstruction               0-003-021  03/21/22     DONE    DONE       DONE      11/19/21   11/19/21   10/21/21   12/14/21   2,7,9,15,16            5,425,000     5,425,000  SLC             0           0           0 Collins & Scoville Architects           0        /  /                         11/19/21           
21-2056FA Reconstruction               0-003-022  10/05/22     DONE    DONE       DONE      06/29/22   06/08/22   04/17/22   04/11/22   9,155,16               1,046,000     1,046,000  WLC             0           0           0 Collins & Scoville Architects           0        /  /                         06/08/22           
22-0084   Reconstruction               0-003-023  11/28/22     DONE    DONE       DONE      07/13/22   07/13/22   06/13/22   12/14/21   2,4,7,8,9,155,15,16    2,475,000     2,475,000  JLB             0           0           0 Collins & Scoville Architects           0      09/07/23                       07/13/22           
  -       Reconstruction               0-003-024                                              /  /       /  /     02/14/23     /  /     2,9,155,15,16                  0             0  WLC             0           0           0                                         0        /  /                           /  /             
23-1028PR Reconstruction               0-003-025               STARTED                      11/16/23     /  /     04/10/23     /  /     2,4,7,8,9,10,155,15,           0             0  WLC             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               0-003-026                                              /  /       /  /     04/12/24     /  /     2,4,7,8,9,10,155,15,           0             0  WLC             0           0           0                                         0        /  /                           /  /             

          William H. Barton Intermediate Schl:
19-1192   Reconstruction               0-019-008  03/06/20     DONE    DONE       DONE      01/10/20   01/07/20   12/20/19   05/21/19   16                       170,000       170,000  SLC             0           0           0 Collins & Scoville Architects           0      04/01/21                       01/07/20           
21-0756   Reconstruction               0-019-009  03/21/22     DONE    DONE       DONE      11/19/21   11/19/21   10/21/21   12/14/21   7,10,15,16             1,512,500     1,512,500  SLC             0           0           0 Collins & Scoville Architects           0        /  /                         11/19/21           
21-1744   Reconstruction               0-019-010  08/16/22     DONE    DONE       DONE      05/02/22   04/29/22   04/17/22   12/14/21   15,16                    250,000       250,000  WLC             0           0           0 Collins & Scoville Architects           0        /  /                         04/29/22           
  -    PR Additions and Alterations    0-019-011                                              /  /       /  /     06/13/22     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                           /  /             
22-0085   Additions and Alterations    0-019-011  11/28/22     DONE    DONE       DONE      07/13/22   07/13/22   06/13/22   12/14/21   02 - 16                3,245,000             0  JLB             0           0           0 Collins & Scoville Architects           0      09/07/23                       07/13/22           
23-1609   Reconstruction               0-019-012                         UNREVIEWED         03/12/24   03/08/24   11/29/22   12/12/22   14                       120,000             0  WLC             0           0           0 Collins & Scoville Architects           0        /  /                         03/08/24           

          Modular - Admin. Bldg. (fmly 0-016):
  -       Reconstruction               1-016-002                                              /  /       /  /     04/09/24     /  /     7,8,9,10,155,15,16             0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Field Storage:
  -    PR New Construction             2-028-001                                              /  /       /  /     06/13/22     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                           /  /             
22-0086   New Construction             2-028-001  11/28/22     DONE    DONE       DONE      07/13/22   07/13/22   06/13/22   12/14/21   02 - 16                  565,000             0  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         07/13/22           

          Bus Garage B:
21-0757   Reconstruction               5-020-009  03/21/22     DONE    DONE       DONE      11/19/21   11/19/21   10/21/21   12/14/21   9,14,16                  447,500     1,512,500  SLC             0           0           0 Collins & Scoville Architects           0        /  /                         11/19/21           
  -       Reconstruction               5-020-010                                              /  /       /  /     04/10/23     /  /     2,9,155,15,16                  0             0  WLC             0           0           0                                         0        /  /                           /  /             
  -       Reconstruction               5-020-011                                              /  /       /  /     02/12/24     /  /     2,16                           0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Parks & Recreation Tent:
21-1755TQ Temporary Quarters           7-027-001                       ADDENDUM REQ'D       05/03/22     /  /     03/22/22     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                           /  /             

          Press Box:
  -    PR New Construction             7-029-001                                              /  /       /  /     10/19/22     /  /     02 - 16                        0             0  WLC             0           0           0                                         0        /  /                           /  /             
22-0919   New Construction             7-029-001  03/07/23     DONE    DONE       DONE      11/07/22   11/03/22   10/19/22   12/14/21   02 - 16                  161,000             0  WLC             0           0           0 Collins & Scoville Architects           0      01/25/24                       11/03/22           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




GLENS FALLS COMMON SCHOOL STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-09-18-08
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Abraham Wing School:
21-0873   Reconstruction               0-001-008  01/27/22     DONE    DONE       DONE      12/08/21   12/08/21   10/12/21   05/18/21   2,8                      100,000       100,000  SLC             0           0           0 Collins & Scoville Architects           0      06/30/22                       12/08/21           
21-2053   Reconstruction               0-001-009  08/04/22     DONE    DONE       DONE      06/29/22   06/13/22   06/04/22   05/17/22   7,8                      100,000       100,000  WLC             0           0           0 Collins & Scoville Architects           0      03/07/23                       06/13/22           
23-1682   Reconstruction               0-001-010                         UNREVIEWED         03/26/24   03/25/24   03/14/24   05/16/23   9                        100,000             0  WLC             0           0           0 Collins & Scoville Architects           0        /  /                         03/25/24           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED




WARRENSBURG CSD STATUS REPORT ON CAPITAL PROJECTS
District No.: 63-12-01-04
last updated on 04/18/24
REVIEW    BUILDING NAME/               BLDG./       SED        FINAL PROJECT REVIEW         PLAN/SPEC  PLAN/SPEC  LETTER OF   VOTER                           PROJECT      ESTIMATED    PRJ.     RESCUE 1    RESCUE 2  EXCEL     ARCHITECT/ENGINEER            ENERGY PERF      SUBS. COMPL.     PARTIAL       FINAL       CERTIFICATE OF
No.       PROJECT SCOPE                PROJ. NO.  APPROVAL  Prj. Mgr.  Const.     Mech.     COMPLETE   RECEIVED   INTENT      AUTHOR.   CSI CODES             COST         COST ALLOW.  MGR.     AID         AID       AID       FIRM                          CONTRACT         DATE                 CSC REC'D   APPORTIONMENT
_________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

          Elementary School (fmly Main Bldg):
20-1612   Reconstruction               0-001-018  06/18/21     DONE    DONE       DONE      04/22/21   04/22/21   03/29/21   06/09/20   16                       100,000       100,000  JLB             0           0           0 Collins & Scoville Architects           0      04/27/22                       04/22/21           
20-1910   Reconstruction               0-001-019  08/09/21     DONE    DONE       DONE      06/23/21   06/11/21   05/12/21   05/18/21   4,155                    170,000       170,000  JLB             0           0           0 Collins & Scoville Architects           0      09/13/22                       06/11/21           
  -       Reconstruction               0-001-020                                              /  /       /  /     11/02/22     /  /     2,4,155,15                     0             0  JLB             0           0           0                                         0        /  /                           /  /             
23-0989   Reconstruction               0-001-021                         UNREVIEWED         11/14/23   11/08/23   11/22/22   10/25/22   2,4,7,8,9,155,16       2,834,000             0  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         11/08/23           

          Middle/High School:
18-2176   Reconstruction               0-008-015  07/22/19     DONE    DONE       DONE      06/20/19   06/13/19   05/28/19   05/21/19   2,9                      100,000       100,000  JLB             0           0           0 Bernier Carr Associates                 0      06/23/20                       06/13/19           
  -    PR Additions and Alterations    0-008-016                                              /  /       /  /     09/29/21     /  /     02 - 16                        0             0  JLB             0           0           0                                         0        /  /                           /  /             
22-1396FC Additions and Alterations    0-008-016  06/21/23     DONE    DONE       DONE      01/04/23   12/27/22   09/29/21   05/09/22   02 - 16                  683,300             0  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         12/27/22           
22-0199   Reconstruction               0-008-017  09/27/22     DONE    DONE       DONE      08/01/22   08/01/22   03/28/22   05/17/22   9,15,16                  350,000       350,000  JLB             0           0           0 Collins & Scoville Architects           0        /  /                         08/01/22           
22-1370   Reconstruction               0-008-018  03/28/23     DONE    DONE       DONE      12/28/22   12/27/22   11/02/22   05/17/22   9,10                     100,000       100,000  JJH             0           0           0 Collins & Scoville Architects           0      06/28/23                       12/27/22           
23-0990   Reconstruction               0-008-019                         UNREVIEWED         11/14/23   11/08/23   11/22/22   10/25/22   2,4,7,8,9,10,155,15,   9,586,945     9,586,945  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         11/08/23           
22-2482   Reconstruction               0-008-020  08/01/23     DONE    DONE       DONE      06/30/23   06/29/23   05/09/23   05/16/23   9                        100,000       100,000  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         06/29/23           
  -    XX Reconstruction               0-008-021                         CANCELLED            /  /       /  /     05/09/23     /  /     9                              0             0  JJH             0           0           0                                         0        /  /                           /  /             

          Maintenance Storage (Garage):
23-0991   Reconstruction               3-004-003                         UNREVIEWED         11/14/23   11/08/23   11/22/22   10/25/22   2,9,155,16               131,600             0  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         11/08/23           

          New Bus Garage:
23-0992   Reconstruction               5-010-004                         UNREVIEWED         11/14/23   11/08/23   11/22/22   10/25/22   8,9,155,16               431,300             0  JJH             0           0           0 Collins & Scoville Architects           0        /  /                         11/08/23           

          District Wide Project:
18-0280   Reconstruction               7-999-001  04/26/19     DONE    DONE       DONE      08/23/18   08/15/18   11/02/17   11/04/14   9,10,16                  750,000       750,000  JLB             0           0           0 Bernier Carr Associates                 0      08/26/20                       08/15/18           


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition
Note: ADD. REQ'D = ADDENDUM REQUIRED            UNREVIEWED = FINAL REVIEW NOT STARTED